1
T-76.115 Project Review Magnificent Seven Project planning iteration 4.11.2004
2
T-76.115 Project Review 2 Agenda Project status (15 min) introduction to the project status of the iteration’s goals status of the iteration’s deliverables realization of the tasks working hours per person changes to the project risks Work results (20 min) project plan requirements document use cases document Used work practices (5 min)
3
T-76.115 Project Review 3 Introduction to the project IRM (Information Resource Manager) is a task tracking software for computers used in the R&D lab at Nokia Networks. Lacks a lot of functionalities to be useful Only for computers Split into several independent versions for different resources -> maintenance problems. IRMii is a new and improved version of IRM A total re-make with the same functionalities as the baseline Any resources can be tracked Easier maintenance through modular development Key aspects Task tracking Resource reservation Re-make of the resource model (hierarcical and abstract) Modular implementation Well-documented Usability and maintenance Integration with Nokia Corporate network
4
T-76.115 Project Review 4 Status of the iteration’s goals Goal 1: Understanding how resource management processes The customer has given us a good understanding about how the processes work in the R&D lab. The situation in the project group is sound regarding this issue. Goal 2: Project planning The startup and initialization of the project has gone quite well. Goal 3: Process definitions Processes used in this project has been defined and we have now together with the outcome from project planning a good foundation for the coming tasks and challenges. Goal 4: Requirements specification and use cases This has been one of the major time consumers in this phase and if we have something to learn from, this would be the issue. Goal 5: Learning required tools and techniques The required tools and techniques have been studied to some extent, but we will continue to do this during the coming phase. Goal 6: Environment setup The environment will be set up during week 45. Note: this should be OK when we have this review. Goal 7: SEPAs Initial selection have been done, but the implementation will come later.
5
T-76.115 Project Review 5 Status of the iteration’s deliverables Project plan OK, except the QA plan, which will be added in the next phase. Requirements document This was the biggest part in this first phase and we have also been using twice the planned effort on it. It is still on a very high level, but this is not seen as a problem due to the iterative approach we are using. Details needs to be added. Use cases document The main use cases have all been described on a general level, but during the coming phase they will be made in more detail. Use cases will be drawn and updated alongside the requirements. Weekly status reports These have been sent on agreed times. SEPAs SEPAs have been selected and only the meeting practices have been taken into practice as of this phase.
6
T-76.115 Project Review 6 Realization of the tasks There were some small estimation problems involving the requirements. We had to add all the functionalities of IRM in order to understand it better. Additional IRMii functionalities were added as well. Total realized effort is lower than the planned, but there are unplanned tasks that takes the grand total to the estimated level. Not started PHP documenting convention was put under some other task. Grand total: 346.5 hours (+1.5)
7
T-76.115 Project Review 7 Working hours by person The requirements needed much more time than expected. The planned effort didn’t include all needed tasks -> added tasks. We needed to change the plan due to new tasks were needed to be done or that we had to put in more effort on some areas. Marko has also been developing our internal documentation system and this has taken time, but will help us in the future and hopefully help us save time and effort. RealPlanDiff Alexei 3840-2 Huan 49.548+1.5 Jing 40.535+5.5 Kalle 2933-4 Marko 62.558+4.5 Tommy 100.599+1.5 Zhiyi 26.532-5.5 Total 346.5345+1.5 Realized hours in this iteration
8
T-76.115 Project Review 8 Working hours by person The requirements needed much more time than expected. The planned effort didn’t include all needed tasks -> added tasks. We needed to change the plan due to new tasks were needed to be done or that we had to put in more effort on some areas. Marko has also been developing our internal documentation system and this has taken time, but will help us in the future and hopefully help us save time and effort. RealPlanDiff Alexei 3840-2 Huan 49.548+1.5 Jing 40.535+5.5 Kalle 2933-4 Marko 62.558+4.5 Tommy 100.599+1.5 Zhiyi 26.532-5.5 Total 346.5345+1.5 Realized hours in this iterationPlan in the beginning of this iteration PP Subtot I1I2FDTotal Alexei 34 645350201 Huan 38 535852201 Jing 32 535954198 Kalle 33 526252199 Marko 46 685830202 Tommy 83 413755216 Zhiyi 32 636442201 Total 298 3943913351418 Latest plan (inc. realized hours and other updates) PP SubtotI1 I2FDTotal Alexei 38 645350205 Huan 49.5 535852212.5 Jing 40.5 535954206.5 Kalle 29 526252195 Marko 62.5 685830218.5 Tommy 100.5 413755233.5 Zhiyi 26.5 636442195.5 Total 346.5 3943913351466.5
9
T-76.115 Project Review 9 Changes to the project We will continue as planned – no changes to the next iterations.
10
T-76.115 Project Review 10 Risks Risks can be found in the Project plan, chapter 7. The major risk is the project schedule and that we will not make the planned deadlines. We will have to plan each iteration very carefully. Close monitoring of the tasks’ progress. Another risk is that we have too little time per person and this will affect the outcome of the project. We need to discuss this and see if we should adjust the working hours. Solution two is to prioritize and drop requirements. Project group members not available for a critical stage in the project. Sickness Other reason
11
T-76.115 Project Review 11 Results of the iteration Project plan Requirements document Use cases document
12
T-76.115 Project Review 12 Project plan (1/4) Stakeholders Staffing
13
T-76.115 Project Review 13 Project plan (2/4) Project goals Customer goals IRM functionalities as the baseline Fully-functional core system Modular and extendable system Implementation and documentation has good quality Light-weight and easy to use Project group’s goals Satisfy the customer’s needs Get a good grade, preferably 5 Learn new software engineering practices
14
T-76.115 Project Review 14 Project plan (3/4) Practices and tools Iterative development Course requirement Iteration planning Planning the phase so everyone knows what we aim for Time reporting Weekly each Sunday Weekly plan is sent to PM each Sunday Weekly status report is sent to customer and mentor Documenting Marko has developed an XML-based system for collecting all project- related information. All members will be responsible for a part of the system. Requirements management Account manager will monitor the progress of the requirements. Version control CVS, SVN PHP conventions PHP standard conventions from PHP.net Communications MSN, e-mail, meetings
15
T-76.115 Project Review 15 Project plan (4/4) Phasing Project planning is ready Implementation 1 should focus on the technical specifications and some of the system’s core framework. Implmentation should implement most of the functionalities. This will be the phase when we put most effort into getting the system developed. Finalization&Delivery is maunly for correcting minor issues and bugs. Delivery to customer is the milestone in this phase.
16
T-76.115 Project Review 16 Requirements document (1/2) The main requirements have been defined and recorded. Detail will be added when we identify the needed issues to add. The focus has been to get the big picture in this iteration and when people will get more into the system we can much easier add more requirements. This document will be updated quite much during the second phase as well, due to the technical specification. Functional requirements Resources Requests Reservations Tasks Reports Users Programs Projects Event log Other modules
17
T-76.115 Project Review 17 Requirements document (2/2) Non-functional requirements Look&feel Usability Performance Operational Maintenance and portability Security Cultural and political Legal Constraints Solutions
18
T-76.115 Project Review 18 Use cases document The main use cases have been identified and recorded. Use cases will be finalized in the second phase. Use cases will be drawn. This contains more or less the essential parts of the system already, but will be modified a bit due to updates in the requirements document and technical specification.
19
T-76.115 Project Review 19 Used work practices Mandatory practices Iteration planning Should be done better in the coming phases, so we might not have the same problems with deadlines Time reporting Fairly good way for the PM to monitor Documentation system good way to have everything in one place easy to transform into other format Version control good when in distributed team Communications this is an issue to tackle when working in distrubuted way More experiences as the team developes this in the coming phases SEPAs Meeting practices Heuristic evaluation (not used) Test-driven development (not used) Static methods (not used) We are going to adopt more practices during the coming phase and we will have much more to tell about these afterwards.
20
Questions?