1 Odd Fellows Road Interchange and Roadway Improvements Citizen Information Meeting
April 15, 2015

2 Contract Information Contractor: G.A. & F.C Wagman, Inc.
David Lyle Design-Build Project Manager Paul Phillips Design-Build Construction Manager Designer: Johnson, Mirmiran & Thompson, Inc. Rodney Hayzlett, P.E Design Manager Contract Price: $29,846,350 Awarded: January 2015 Notice to Proceed: February 18, 2015 (Design Start Date) Construction Start: November 2015 Final Completion Date: August 3, 2018

3 Agenda Introductions Contract Information Project Overview Roundabouts Construction Schedule Conclusion

4 Project Overview

5 Project Overview Segment A
Design Features: New interchange with US 29/460 New roundabout at Top Ridge Road Bradley Drive EBL Route 460 Segment B1 Segment A Top Ridge Road Roundabout WBL Route 460

6 Project Overview Segment B1
Design Features: Roadway improvements along Odd Fellows Road New roundabout at Mayflower Drive Segment B2 Mayflower Drive Mayflower Drive Roundabout Segment B1 Bradley Drive Segment A

7 Project Overview Segment B2 (Design Only)
Design Features: Roadway improvements along Odd Fellows Road New Roundabout at Albert Lankford Drive and Murray Place Lynchburg Expressway Albert Lankford Drive Albert Lankford Drive Roundabout Norfolk-Southern Railway Murray Place Segment B2 Segment B1

8 Roundabout Basics Modern roundabout dates to 1960’s (U.K.)
Virginia has 130± in its inventory 3 in Lynchburg District Diameter Typical Features Circular shape Traffic yields entering the circle Splitter islands direct traffic and provide refuge for pedestrians Concrete apron permits turning movements by large trucks Splitter Island Apron Source: NCHRP Report 672, Roundabouts: An Informational Guide (Oct. 2010)

9 Roundabouts What benefits do roundabouts offer? FUNCTIONAL
Delay with Signal 16 sec Keep traffic moving Lower delays than a signalized intersection Lower costs to operate and maintain Reduced vehicle emissions 1000 vehicles/hour Delay with Roundabout 3 sec Source: NCHRP Report 672, Roundabouts: An Informational Guide (Oct. 2010)

10 Roundabouts What benefits do roundabouts offer? SAFETY
Significant safety improvement Lowers vehicle speed Eliminates red-light running Eliminates most serious conflict points Safer for pedestrians and cyclists Compared to Signalized Intersections 90% Reduction in Fatal Crashes 75% Reduction in Crashes with Injury 30% Reduction in Pedestrian Crashes 10% Reduction in Bicycle Crashes Source: NCHRP Report 672, Roundabouts: An Informational Guide (Oct. 2010)

11 Roundabouts What benefits do roundabouts offer? SAFETY
Far fewer conflict points Source: NCHRP Report 672, Roundabouts: An Informational Guide (Oct. 2010)

12 Roundabouts 3 Roundabouts Included on Project 1. Segment A: Top Ridge Road 80’ Diameter 2. Segment B1: Mayflower Drive 120’ Diameter 3. Segment B2: Albert Lankford Drive 85’ Diameter 3 2 1 How do these compare to existing roundabouts in Lynchburg District?

13 Roundabouts 75’ 5th Street Lynchburg, VA 75’ Diameter

14 Roundabouts 15.9% Trucks 85’ Routes 60 and 29 Amherst, VA 85’ Diameter

15 Roundabouts Mayflower Drive 8.6% Trucks 120’

16 Construction Schedule
Targeting 2018 Delivery Utility Relocations – June 2015 thru June 2016 Project Completion – August 2018 Traffic Impacts Restrictions on Single Lane Closures Odd Fellows Road: 7 AM – 9 AM; 4 PM – 6 PM Route 29/460: 7 AM – 9 AM; 2 PM – 6 PM Restrictions on Total Closure 6 AM – 7 PM (15 Minute Maximum)

17 Please Join Us at the Displays For More Information