Air Group One Expansion Project Phase 1 Design and Cost Analysis
2
An Air Group One for the Future, San Diego’s Commemorative Air Force.
3
Overview hangar to maintain 5-6 warbird aircraft. 1 large warbird Relief from costs of commercial lease and exponential rise in costs, securing AG-1’s future. Open to the public Higher priority/status at Gillespie Field Shop and work area for volunteer projects
4
Design
5
Public Viewing Area
6
Workshop for Volunteers
7
Museum open to the public
8
Costs The project can be incremental depending on the financing plan. $20/square foot for the structure of 120’x100’ = $240,000 $5/square foot for concrete 7” deep for hangar = $60,000 Additional ramp area. $40,000 $50,000 for soft costs $390,000 for Total Estimated Costs