NEW GOVERNMENT CENTER WEST DEVELOPMENT OPTIONS January 14, 2015
2
1. New Government Center West on Ag Building Site - Back of Property 2. New Government Center West on Ag Building Site - Corner of Congress & West Jefferson 3. New Government Center West on Ag Building Site - Existing Parking Lot 4. New Government Center West on York Co-Op Site OPTIONS
3
Prices for a New Government Center West include the following for all three options: 83,500 SF new Government Center West building Demolition of existing Ag Building for parking The following Departments will be located in the new facility: County Manager’s OfficeCounty Council Chambers Risk ManagementHuman Resources Information Technology/RecordsFinance Tax Collector’s Office (York)Auditor’s Office (York) Assessor’s Office (York)Register of Deeds EngineeringRegistration and Elections Purchasing NEW GOV’T CENTER WEST
4
OPTION #1: NEW GOV’T WEST ON AG SITE – BACK OF PROPERTY
5
OPTION #1: NEW GOV’T WEST BACK ON AG SITE – BACK OF PROPERTY PRO’S Maximizes Existing Property Sub-Basement Parking Deck Allows Future Development of Site Reuse Existing Parking Lot CON’S Confined Site Low Visibility Construction Logistics Topo / Grading Stream / Wetland Proximity Development Cost Development Schedule Estimated Cost: $24,791,161.00
6
OPTION #2: NEW GOV’T WEST ON AG SITE – CORNER OF CONGRESS & WEST JEFFERSON
7
PRO’S High Visibility Minimizes Impact to Existing Operations Additional Drive Access / Connectivity CON’S Confined Site Will Require Additional Land Purchase Stream / Wetland Proximity Improvements to West Jefferson Estimated Cost: $24,201,109.00
8
OPTION #3: NEW GOV’T WEST ON AG SITE – EXISTING PARKING LOT
9
PRO’S High Visibility Limited Sitework for Building Pad CON’S Confined Site Construction Logistics No Staff Parking on Site During Construction Will Require New Parking Lot Will Impact Operations & Could Require partial Staff Relocation Limits Future Development of Site Estimated Cost: $23,742,098.00
10
OPTION #4: NEW GOV’T WEST CO-OP SITE
11
PRO’S High Visibility Existing Utilities Available Not An Occupied Site /Undeveloped Current Roads could Handle Left Turn Lane (If Required) Schedule Development Cost CON’S Larger Site to Grade Improvement to Arrow Road Estimated Cost: $22,997,982.00
12
SUMMARY Option 1Option 2Option 3Option 4 New Gov’t Center West - Back of Ag Building Property New Gov’t Center West - Corner of Congress & Jefferson New Gov’t Center West - Existing Parking Lot Original Gov’t Center West - Co- Op Site $24,791,161.00$24,201,109.00$23,742,098.00$22,997,982.00