Presentation is loading. Please wait.

Presentation is loading. Please wait.

Florida High Speed Rail Authority Update for Orange County Board of County Commissioners April 7, 2009.

Similar presentations


Presentation on theme: "Florida High Speed Rail Authority Update for Orange County Board of County Commissioners April 7, 2009."— Presentation transcript:

1 Florida High Speed Rail Authority Update for Orange County Board of County Commissioners April 7, 2009

2 OUTLINE Timelines and Federal Processes Florida’s Strong Position - Previous HSR Work Approach for Florida Response to Stimulus FDOT Participation

3 High Speed Rail on National Agenda Competition for High Speed Rail start-up around the US Federal Bills:  October ’08 Bill: $1.5 billion over 5 yrs (not yet appropriated)  Stimulus ’09 Bill: $8 billion added – 100% Federal Funding – no State match required (fully funded)  Future additional Bills anticipated due to national importance placed by Obama Administration

4 CORRIDORS COMPETING FOR BILLIONS OF $FEDERAL

5 Federal High Speed Rail Corridors* Northeast Corridor California Corridor Empire (NY) Corridor Pacific Northwest Corridor South Central Corridor Gulf Coast Corridor *others may emerge Chicago Hub Network Florida Corridor Keystone (PA) Corridor Northern New England Corridor Southeast Corridor

6 Timeline chart

7 Florida’s Strong Position Over the past 10 years…  1998: Florida Overland eXpress Tampa-Orlando-Miami environmental and engineering  2004: Florida High Speed Rail Authority PD&E for Tampa-Orlando Feasibility study for Orlando-Miami  Approximately $30 million invested in both these efforts

8 Florida High Speed Rail Authority – 2004 TAMPA ORLANDO

9 Review of Tampa-Orlando Corridor Two major components of FHSRA work:  PD&E for Tampa-Orlando corridor  Procurement of Design-Build-Operate-Maintain & Finance vendor

10 NEPA Work Completed FRA Record of Decision (ROD) completes NEPA ROD required to advance into Final Design 20012002200320042005 FHSRA createdMarch ‘02: Notice of Intent April ‘02: Advance Notification and Scoping October ‘03: Draft EIS and Public Hearings Impacts of DBOM&F proposals assessed July ‘05 FEIS signed by FRA and FHSRA Project put on hold FEIS signed No ROD issued

11 Design-Build-Operate-Maintain & Finance- DBOM&F RFP issued October 2002 Investment Grade Ridership Study Issued Nov 2002  Beachline (then Beeline) route: Total riders: 2.4 to 2.8 million; Revenue: $39 -$42 mill  Greeneway route: Total riders: 3.8 to 4.1 million; Revenue: $54- $56 mill Both proposing teams committed to covering Operations & Maintenance costs based on inclusion of the Choice and Captive markets

12 DBOM&F SUBMITTALS FLUOR-BOMBARDIER  Jet-Train Technology – Gas Turbine  Double track Disney to OIA, single track to Tampa  Firm Fixed price of $2.056 Billion GLOBAL RAIL CONSORTIUM  Electric TGV Technology  Double track entire system  Firm Fixed price of $2.4 Billion F-B was ranked first on 6-2 vote Negotiations proceeded until August 2004

13 ORLANDO MIAMI FEASIBILITY – 2004

14 Orlando-Miami Feasibility – FHSRA 2002 Key Findings for Tampa-Orlando-Miami:  Operating Ratios (2020) Will revenues from system cover O&M costs? For 180+mph: Operating Revenue: $531 mill O&M Costs: $174 mill RATIO: 3.05  Benefit-Cost Ratios (30 year NPV) Do Benefits to Society for building this system justify the costs? For 180+mph: RATIO 1.95  Conclusion: Overall benefits of this system greatly exceed costs

15 APPROACH TO RESPONSE Highlights of Proposed Response:  Corridor: Tampa-Orlando-Miami  P3 Approach  “Green” Technology  Includes Stimulus component – “shovel ready” CREATES JOBS!

16 Corridor Definition Tampa-Orlando-Miami Corridor is logical  Much work done on entire corridor  Entire corridor is designated by FRA  Phasing to logical intermediate stations  Provides 180+ mph capability  Reasonable total length (310 miles) compared to other competing corridors: LA - San Francisco is almost 400 miles Boston - DC is 440 miles

17 Public Private Partnership Private partner is critical for success  Leases system for long term  Shares profits in excess of defined thresholds A single system approach is logical  Single technology  One set of standards that is interoperable statewide  WILL REQUIRE ASSUMPTION OF O&M RISK BY PRIVATE PARTNER

18 State of the Art examples Siemens Velaro Alstom AGV GREEN TECHNOLOGY = ELECTRICALLY DRIVEN SYSTEM

19 Stimulus Approach Sequence of work:  Define Minimum Operating Segment (MOS) with FRA within the Tampa-Orlando corridor  Obtain Record of Decision for MOS  Start construction of MOS  Incrementally add segments on  Continue environmental work on next segments GOAL: MOS can start construction in 18 months

20 Board Meeting of April 2 FDOT Letter of Assistance  Offered to take over the application process for stimulus funds to use in-house resources  FHSRA accepted offer, with three requests: $4 million federal funds available to FHSRA from 4 years ago - FDOT to report status in 2 weeks FDOT to provide progress report at future meetings FHSRA requested that “institutional memory” available be used Sunrail: FHSRA passed a support resolution 4-1

21 Florida High Speed Rail Authority Update for Orange County Board of County Commissioners April 7, 2009


Download ppt "Florida High Speed Rail Authority Update for Orange County Board of County Commissioners April 7, 2009."

Similar presentations


Ads by Google