Advanced Scheduling In MS Project Provided by FrontRange MPUG
2
Advanced Scheduling Features MS Project Scheduling Engine –Duration Equation D=W÷(UxPHPD) –Task Type –Effort Driven Advanced Options Calendars –Project –Task –Resource
3
Analyzing/Revising the Schedule Task Relationships Critical Path Resource Allocation –Allocation Analysis –Assignment Contours –Interactive Scheduling/Leveling Revising the Schedule –Schedule Overtime –Add Resources –Reduce Scope
4
Closing Use the logic of the tool to command the schedule Dependencies due to nature of the task and/or company policy only Limit use of constraints Don’t hide schedule manipulation, leave road signs Resource availability is a huge risk to your schedule, resource management is vital