Runoff Pond Design, Lutsen, MN By Mark Greve. Problem Poplar River increases in sediment load near Lutsen ski hills Structure needed to slow flow and.

Similar presentations


Presentation on theme: "Runoff Pond Design, Lutsen, MN By Mark Greve. Problem Poplar River increases in sediment load near Lutsen ski hills Structure needed to slow flow and."— Presentation transcript:

1 Runoff Pond Design, Lutsen, MN By Mark Greve

2 Problem Poplar River increases in sediment load near Lutsen ski hills Structure needed to slow flow and settle sediment out Find a location for structure that does not interfere with ski runs

3 Computer Modeling Used LIDAR data in ArcGIS to determine watersheds, slopes, lengths, etc. Also mapped roads, culverts and other points of interest Flow paths, culverts and watershed boundaries field-validated

4 Computer Modeling (cont.) Water Erosion Prediction Project (WEPP) model used to create slope model Inputs: climate data (10 yr), slope, land cover and soil types Outputs: total runoff, sediment load by particle size and areas of erosion

5 Computer Modeling (cont.) WEPP outputs transferred to Excel Hydrograph created from flow-routing table

6 Pond Design Two-pond system connected by ditch Trapezoidal cross-sections, 2:1 ratio on sides Riser pipe in center as outlet Emergency spillway included

7 More Computer Modeling Used flow equations for both pipe flow and flow over a weir to determine daily discharge Determined dimensions of pipe and ponds Calculated sediment reduction

8 Questions?