Presentation is loading. Please wait.

Presentation is loading. Please wait.

Chapter 6 Capital Budgeting Techniques Sept 2010 Dr. B. Asiri © 2005 Thomson/South-Western.

Similar presentations


Presentation on theme: "Chapter 6 Capital Budgeting Techniques Sept 2010 Dr. B. Asiri © 2005 Thomson/South-Western."— Presentation transcript:

1 Chapter 6 Capital Budgeting Techniques Sept 2010 Dr. B. Asiri © 2005 Thomson/South-Western

2 2 What is Capital Budgeting?  The process of planning and evaluating expenditures on assets whose cash flows are expected to extend beyond one year  Analysis of potential additions to fixed assets  Long-term decisions; involve large expenditures  Very important to firm’s future

3 3 Generating Ideas for Capital Projects  A firm’s growth and its ability to remain competitive depend on a constant flow of ideas for new products, ways to make existing products better, and ways to produce output at a lower cost.  Procedures must be established for evaluating the worth of such projects.

4 4 Project Classifications  Replacement Decisions:  Replacement Decisions: whether to purchase capital assets to take the place of existing assets to maintain or improve existing operations  Expansion Decisions:  Expansion Decisions: whether to purchase capital projects and add them to existing assets to increase existing operations  Independent Projects:  Independent Projects: Projects whose cash flows are not affected by decisions made about other projects  Mutually Exclusive Projects:  Mutually Exclusive Projects: A set of projects where the acceptance of one project means the others cannot be accepted

5 5 Net Cash Flows for Project S and Project L 1,500 1,200 800 300 400 900 1,300 1,500 ^ Net CashFlows, CF t r edpAExctefte-Tax Year ProjectSPro tL 0$(3,000)$( 0) 1 2 3 4

6 6 1. Payback Period: PB The length of time before the original cost of an investment is recovered from the expected cash flows or... How long it takes to get our money back.

7 7 Payback Period for Project S = Payback S 2 + 300/800 = 2.375 years Net Cash Flow Cumulative Net CF 1,500 -1,500 800 500 1,200 -300 -3,000 300 800 PB S 01234

8 8 = Payback L 3 + 400/1,500 = 3.3 years Net Cash Flow Cumulative Net CF 400 - 2,600 1,300 - 400 900 - 1,700 - 3,000 1,500 1,100 PB L 01234 Payback Period for Project L

9 9 Strengths of Payback: Provides an indication of a project’s risk and liquidity Easy to calculate and understand Weaknesses of Payback: Ignores TVM Ignores CFs occurring after the payback period Strengths and Weaknesses of Payback:

10 10 2.Net Present Value: NPV Sum of the PVs of Inflows + Outflows Cost is CF 0 and is generally negative. ^ ^ ^

11 11 What is Project S’s NPV? k = 10% 1,500 8001,200(3,000) 1,363.64 991.74 601.05 204.90 161.33 300 01234 NPV S =

12 12 What is Project L’s NPV? k = 10% 400 1300900(3,000) 363.64 743.80 976.71 1024.52 108.67 1500 01234 NPV L =

13 13 Rationale for the NPV method: NPV= PV inflows - Cost = Net gain in wealth. Accept project if NPV > 0. Choose between mutually exclusive projects on basis of higher NPV. Which adds most value?

14 14 Using NPV method, which project(s) should be accepted?  If Projects S and L are mutually exclusive, accept S because NPV S > NPV L.  If S & L are independent, accept both; NPV > 0.

15 15 3. Internal Rate of Return: IRR 0123 CF 0 CF 1 CF 2 CF 3 CostInflows IRR is the discount rate that forces PV inflows = cost. This is the same as forcing NPV = 0.

16 16 NPV: IRR: Calculating IRR

17 17 What is Project S’s IRR? NPV S = IRR S = 13.1% 0 (3,000) IRR = ? 01234 Sum of PVs for CF 1-4 = 3,000 1,5008001,200300

18 18 What is Project L’s IRR? NPV L = IRR L = 11.4% 0 IRR = ? 40013009001500 01234 Sum of PVs for CF 1-4 = 3,000 (3,000)

19 19 Rationale for the IRR Method: If IRR (project’s rate of return) > the firm’s required rate of return, k, then some return is left over to boost stockholders’ returns. Example: k = 10%, IRR = 15%. Profitable.

20 20 IRR acceptance criteria:  If IRR > k, accept project.  If IRR < k, reject project. Decisions on Projects S and L per IRR  If S and L are independent, accept both. IRRs > k = 10%.  If S and L are mutually exclusive, accept S because IRR S > IRR L.


Download ppt "Chapter 6 Capital Budgeting Techniques Sept 2010 Dr. B. Asiri © 2005 Thomson/South-Western."

Similar presentations


Ads by Google