Space Planning and Construction. LDR Room Renovations Completed on August 21, 2013 Microbiology Lab Reorganization Completed on October 9, 2013 45 Willard.

Similar presentations


Presentation on theme: "Space Planning and Construction. LDR Room Renovations Completed on August 21, 2013 Microbiology Lab Reorganization Completed on October 9, 2013 45 Willard."— Presentation transcript:

1 Space Planning and Construction

2 LDR Room Renovations Completed on August 21, 2013 Microbiology Lab Reorganization Completed on October 9, 2013 45 Willard Conference Room rehab Completed on August 13, 2013 50 Holden conversion of Video Vault Room Completed on August 16, 2013 RECENTLY COMPLETED PROJECTS

3 Microbiology Temp Lab at Aud C

4 Completed Microbiology

5

6 IN PROGRESS ED Triage – Framing, drywall and utilities in progress Infusion Center One Blackstone – underground plumbing complete, framing in progress

7 ED / Triage July Update

8 ED / Triage October

9

10

11 Infusion

12

13

14 PROJECTS ABOUT TO START Day Hospital / Behavioral Health – awarded, permit received, sccheduling materials and start date Lab Long Term Plan Phase 1 – Phlebotomy – bids received and in for evaluation

15 PROJECTS IN PLANNING Uro Gyn Long Term Plan Sim Center Relocation to Zero Level Auds DaVinci Robot Operating Rooms Philanthropy Office Reorganization / Fit test Nursing Support Staff Reorganization / Fit test

16 Partner Projects DOH Review – New Primary Care Center at Butler DOH Review – WIH Infusion Center at Kent Design and Construction Documents – Isolator Hood Project Design – New USP 797 Chemo Mixing Room Design – Tenant Fit Out of 1 st floor new MOB building

17 Partner Projects Study – New Hyperbaric Chamber Plan Review and Bid Documents – Medical Gas Upgrade Project OTHER PROJECTS Retail Pharmacy Study DOH Review – 5750 Post Road, East Greenwich Space Plan – 171 Service Road