OPCPR- 03/26/20081 Procurement Under OP/BP 8.0 This presentation will cover… Organizational and Institutional Support Simplified Procurement Arrangements Fiduciary Safeguards
2
OPCPR- 03/26/20082 Organizational and Institutional Procurement Support Exceptionally - the Bank executes start-up activities: In the absence of other alternatives of implementation Requires an authorization from the Managing Director Bank involvement will be through GSD Contracts are financed from a PPF, or a trust fund grant
3
OPCPR- 03/26/20083 Organizational and Institutional Procurement Support Regional Vice President (RVP) with the Country Director (CD) decide to establish a Rapid Response Committee (RRC) Procurement specialists may be delegated higher review authority to task teams Regional emergency designated procurement staff have been assigned Additional resources for Bank supervision
4
OPCPR- 03/26/20084 Organizational and Institutional Procurement Support Harmonization of procurement procedures, thresholds, review arrangements among donors Use of pooled funds with common simplified procurement procedures
5
OPCPR- 03/26/20085 Procurement Agents and Management Contractors Bank maintains a list PA from which Borrowers can draw from in emergency situations Borrower has the option to select a firm using CQS Main criteria for selection may be the timely availability of the key personnel
6
OPCPR- 03/26/20086 Procurement Agents and Management Contractors The selection of the PA is carried out in accordance with Para. 3.10 of the Procurement Guidelines or Para. 3.17 of the Consultant Guidelines Procurement should be carried out in accordance with procurement procedures, Loan Agreement and Procurement Plan Where large numbers of small contracts- management contractor
7
OPCPR- 03/26/20087 Simplified Procurement Arrangements Rapid Capacity Assessments Can be conducted by Bank staff or by any other qualified resource person or entity The Regional Procurement Manager clears Template for simplified RPCA is available
8
OPCPR- 03/26/20088 Simplified Procurement Procedures Single-source selection (SSS) SSS of consulting firms in accordance with (Para. 3.10 (b) of the Consultant Guidelines) Only if it presents a clear advantage over competition Firms that are already working in the country, proven track - may be the most suitable option for the start-up activities Consultants selected on a single-source basis may be given the right to participate in future assignments
9
OPCPR- 03/26/20089 Selection of consulting firms through Consultants’ Qualification (CQS) CQS, carried out in accordance with Para. 3.7 of the Consultant Guidelines…. However, The application is not limited to small assignments (footnote 32 of CG) Ceiling for the use of higher threshold will be determined by the RPM Advertising for expressions of interest may be forgone, or limited to the local/ provincial level
10
OPCPR- 03/26/200810 Pool of Experts Support to counterpart agencies at various steps of project execution Fees may be resolved, at time of pre- selection, and prescribed in a framework agreement – similar in concept to an indefinite Delivery Contracts
11
OPCPR- 03/26/200811 Civil Works and Goods Direct Contracting In accordance with (paras. 3.6 (a) and 3.6 (e) of the Procurement Guidelines Extend an existing contract to respond to a natural disaster The price is reasonable and that no advantage could be obtained by further competition
12
OPCPR- 03/26/200812 Civil Works and Goods Shopping In accordance with (para 3.5 of the Procurement Guidelines) Readily available off-the-shelf goods, standard specification commodities, or simple civil works Threshold may be set on a case by case basis and cleared by the RPM At least three price quotations for the purchase of goods, works, or services (other than consulting services)
13
OPCPR- 03/26/200813 Use of Positive Lists A quick-disbursing component designed to finance a positive list of imported or locally produced goods. Indicators (quantitative or qualitative) to monitor progress during implementation and evaluate outcomes upon completion. Agreement on the conditions for the release of financial trenches and the documentation and certifications—such as customs and tax certificates or invoices—to be required for locally procured goods. Would normally follow the national emergency procedures for government procurement, or commercial practices from the private sector if they are acceptable to the Bank.
14
OPCPR- 03/26/200814 Procurement of Commodities Market prices of commodities, such as grain, fertilizer, and fuel, may be used in accordance with Para. 2.68 of the Procurement Guidelines Customs duties for emergency commodities should be set at reasonable levels Bank’s approval to finance such commodities may be conditional on the temporary exemption or reduction of customs duties
15
OPCPR- 03/26/200815 Civil Works and Goods Pre-qualified suppliers and contractors Using lists of pre-qualified suppliers and contractors to whom periodic invitations are issued This approach may be used for a large number of similar simple contracts of any size Suppliers and contractors would be asked to provide quotations for simple unit prices. Contracts awarded on a competitive basis, may be extended up to two years
16
OPCPR- 03/26/200816 Civil Works and Goods Shorter periods for submission of bids Bidding periods shorter than 21 days for NCB and 6 weeks for ICB should be cleared with the RPM
17
OPCPR- 03/26/200817 Civil Works and Goods Waiving bid and performance security requirements para. 2.14 of the Guidelines leaves to the borrower the option of requiring a bid security Prior review thresholds Based on the capacity assessment of the program management entity Prior review threshold may be set higher than the regional ones Requires establishing a stringent monitoring and review system The objective is to minimize the need of declaring as declaring misprocurement, at post-review
18
OPCPR- 03/26/200818 How to minimize the fiduciary risks Emergency projects has increased risk of fraud and corruption, (abuse of direct contracting, false delivery certification). Team may consider; Sequenced approach allowing low-risk components and activities to move ahead, while necessary preparation are done for activities that represent higher risks
19
OPCPR- 03/26/200819 How to minimize the fiduciary risks Monitoring/ Procurement Agents to provide fiduciary assurance to the Borrower, the Bank and other donors Procurement agents that are given the responsibility to handle procurement on the borrower’s behalf Pre-shipment inspection and/or local independent verification at delivery Intensified Bank supervision to address and mitigate the increased risks associated with such emergency operations (CO and HQ)