IBL Slides G. Darbo – INFN / Genova CSN1, 22 November 2010 o IBL Spare Slides Commissione I – 22 Nov 2010 G. Darbo - INFN / Genova.

Similar presentations


Presentation on theme: "IBL Slides G. Darbo – INFN / Genova CSN1, 22 November 2010 o IBL Spare Slides Commissione I – 22 Nov 2010 G. Darbo - INFN / Genova."— Presentation transcript:

1 IBL Slides G. Darbo – INFN / Genova CSN1, 22 November 2010 o IBL Spare Slides Commissione I – 22 Nov 2010 G. Darbo - INFN / Genova

2 IBL Slides G. Darbo – INFN / Genova CSN1, 22 November 2010 2 Material from Raphael/Neal The Insertable B-Layer (IBL) is a fourth layer added to the present Pixel detector between a new beam pipe and the current inner Pixel layer (B-layer). IST IBL Support Tube Alignment wires PP1 Collar IBL Detector IBL Staves Sealing service ring IBL key Specs / Params 14 staves, = 33.25 mm CO 2 cooling, T < -15ºC @ 0.2 W/cm 2 X/X 0 < 1.5 % (B-layer is 2.7 %) 50 µm x 250 µm pixels 1.8º overlap in ϕ, <2% gaps in Z 32/16 single/double FE-I4 modules per stave Radiation tolerance 5x10 15 n eq /cm 2 IBL key Specs / Params 14 staves, = 33.25 mm CO 2 cooling, T < -15ºC @ 0.2 W/cm 2 X/X 0 < 1.5 % (B-layer is 2.7 %) 50 µm x 250 µm pixels 1.8º overlap in ϕ, <2% gaps in Z 32/16 single/double FE-I4 modules per stave Radiation tolerance 5x10 15 n eq /cm 2

3 IBL Slides G. Darbo – INFN / Genova CSN1, 22 November 2010 3 History of IBL Project - Time Line 1998: Pixel TDR B-layer designed to be substituted every 3 years of nominal LHC (300 fb -1 ): due to then available radiation hard sensor and electronic technologies. 2002: B-layer replacement became part of ATLAS planning and was put into the M&O budget to RRB. 2008: B-layer taskforce B-layer replacement cannot be done – Engineering changes to fulfil delayed on- detector electronics (FE-I3, MCC) made it impossible even in a long shut down. Best (only viable) solution: “make a new smaller radius B-layer insertion using technology being developed for HL-LHC prototypes”. This became the IBL. 2009: ATLAS started IBL project: February: endorsed IBL PL and TC April: IBL organization in place (Endorsed by the ATLAS EB) 2010: TDR and interim-MoU TDR is under approval in ATLAS Interim-MoU is collecting last signatures.

4 IBL Slides G. Darbo – INFN / Genova CSN1, 22 November 2010 4 WGs, Pixel Liaison & Tasks Module WG (WG1) M. Garcia-Sciveres F. Hügging Module WG (WG1) M. Garcia-Sciveres F. Hügging Stave WG (WG2) E. Vigeolas O. Rohne Stave WG (WG2) E. Vigeolas O. Rohne Integration & Installation WG (WG3) F. Cadoux R. Vuillermet Integration & Installation WG (WG3) F. Cadoux R. Vuillermet Off-detector (WG4) T. Flick S. Débieux Off-detector (WG4) T. Flick S. Débieux IBL Management Board (MB) Membership: IBL PL + IBL TC Coordinators of WG Pixel / IBL Liaison Ex-officio IBL Management Board (MB) Membership: IBL PL + IBL TC Coordinators of WG Pixel / IBL Liaison Ex-officio PIXEL / IBL “LIAISON” Common Pixel / IBL Membership: Offline Software: A. Andreazza (untill 9/2010) DAQ: P. Morettini DCS: S. Kersten PIXEL / IBL “LIAISON” Common Pixel / IBL Membership: Offline Software: A. Andreazza (untill 9/2010) DAQ: P. Morettini DCS: S. Kersten WG Description Responsible TASK Module

5 IBL Slides G. Darbo – INFN / Genova CSN1, 22 November 2010 5 Management Board (MB) Module WG (2 cordinators) FE-I4 Sensors Bump-Bonding Modules Procurement & QC Irradiation & Test Beam Module WG (2 cordinators) FE-I4 Sensors Bump-Bonding Modules Procurement & QC Irradiation & Test Beam Stave WG (1 Phys + 1 Eng.) Staves Cooling Design & Stave TM HDI (Flex Hybrid) Internal services Loaded stave Procurement & QC Stave WG (1 Phys + 1 Eng.) Staves Cooling Design & Stave TM HDI (Flex Hybrid) Internal services Loaded stave Procurement & QC Integration & Installation WG (2 Eng.) Stave Integration Global Supports BP procurement Ext. services inst. BP extraction IBL+BP Installation Cooling Plant Integration & Installation WG (2 Eng.) Stave Integration Global Supports BP procurement Ext. services inst. BP extraction IBL+BP Installation Cooling Plant Off-detector (1 Phys + 1 E.Eng.) BOC/ROD Power chain & PP2 DCS & interlocks Opto-link Ext. serv.design/proc. Procurement & QC System Test Off-detector (1 Phys + 1 E.Eng.) BOC/ROD Power chain & PP2 DCS & interlocks Opto-link Ext. serv.design/proc. Procurement & QC System Test IBL Management Board (MB) Membership: IBL PL + IBL TC 2 cordinators from each WG Plus “extra” members IBL Management Board (MB) Membership: IBL PL + IBL TC 2 cordinators from each WG Plus “extra” members MB ad-interim membership IBL Project Leader: G. Darbo IBL Technical Coordinator: H. Pernegger “Module” WG: F. Hügging & M. Garcia-Sciveres “Stave” WG: O. Rohne + E. Vigeolas “Integration & Installation” WG: F. Cadoux + R. Vuillermet “Off-detector” WG: T. Flick + S. Débieux “Extra” members: IBL/Pixel “liaison”: Off-line SW: A. Andreazza, DAQ: P. Morettini, DCS: S. Kersten Ex officio: Upgrade Coordinator (N. Hessey), PO Chair (M. Nessi), Pixel PL (B. Di Girolamo), ID PL (P. Wells), IB Chair (C. Gößling) MB ad-interim membership IBL Project Leader: G. Darbo IBL Technical Coordinator: H. Pernegger “Module” WG: F. Hügging & M. Garcia-Sciveres “Stave” WG: O. Rohne + E. Vigeolas “Integration & Installation” WG: F. Cadoux + R. Vuillermet “Off-detector” WG: T. Flick + S. Débieux “Extra” members: IBL/Pixel “liaison”: Off-line SW: A. Andreazza, DAQ: P. Morettini, DCS: S. Kersten Ex officio: Upgrade Coordinator (N. Hessey), PO Chair (M. Nessi), Pixel PL (B. Di Girolamo), ID PL (P. Wells), IB Chair (C. Gößling)

6 IBL Slides G. Darbo – INFN / Genova CSN1, 22 November 2010 6 Interim-MoU - Institutions 43 institutions in the IBL project Large interest for the sensor (22 Institutions) 300 people have expressed their interest to contribute to the project The list of names is in Ch.11 of IBL TDR

7 IBL Slides G. Darbo – INFN / Genova CSN1, 22 November 2010 7 Money Matrix (A.4) Unknown covers the previously assigned contribution to UK. UK cannot commit until sensor decision, The Annex 4 has been changed in the technology option with the addition of is Munich MPI (D- MPG) – 12 kCH for the IZM order.

8 IBL Slides G. Darbo – INFN / Genova CSN1, 22 November 2010 8 Institutes and Contributions to IBL Note: the numbers in the table "are not final, nor are the suggested financial contributions yet firm, but are meant for a common overall discussion.” Technology options refer to supplementary costs that are sensor technology specific and will be known before the definite MoU takes effect. 42 Institutes in the interim- MoU (few others are “observers” ). 14 Countries + CERN 9.7 MCH total project cost

9 IBL Slides G. Darbo – INFN / Genova CSN1, 22 November 2010 9 Money Matrix (A.4 ext)

10 IBL Slides G. Darbo – INFN / Genova CSN1, 22 November 2010 10 Annex 5: IBL Payment Profile Funding profile follows schedule for “ready to installation by end of 2014” 2010 Expenditures: in large fraction for prototyping of FE- I4, sensors, modules, staves… Two common contracts and several prototype costs already done in the framework of the interim-MoU.

11 IBL Slides G. Darbo – INFN / Genova CSN1, 22 November 2010 11 Institutes (A.3)

12 IBL Slides G. Darbo – INFN / Genova CSN1, 22 November 2010 12 IBL TDR – Endorsed by CB, LHCC IBL TDR endorsed by ATLAS Collaboration Board (8/10/2010): CERN-LHCC-2010-13, ATLAS TDR 19 In printing 200 copies Editorial team: M. Capeans (technical editor), G. Darbo, K. Einsweiller, M. Elsing, T. Flick, M. Garcia-Sciveres, C. Gemme, H. Pernegger, O. Rohne and R. Vuillermet. IBL TDR presented to LHCC 21/9/2010: http://indico.cern.ch/conferenceDisplay.py?confId=107477 The project has received very positive comments and TDR was considered a solid documents. We expect some feedback from the reviewers (hope towards a formal approval) by end of the year/beginning of next year

13 IBL Slides G. Darbo – INFN / Genova CSN1, 22 November 2010 13 IBL TDR in ATLAS e-News http://atlas-service-enews.web.cern.ch/atlas- service- enews/2010/news_10/news_Insertable%20B- layer.php http://atlas-service-enews.web.cern.ch/atlas- service- enews/2010/news_10/news_Insertable%20B- layer.php

14 IBL Slides G. Darbo – INFN / Genova CSN1, 22 November 2010 14 Physics Performance Sound TDR section on Physics and Performance: Pixel / IBL software Group – Coordinated by Attilio Boosted in the last 3 months by the P & P TF – Chaired by Markus Need to channel again the efforts in the Pixel / IBL Offline Software! 2 jets of 500 GeV event with 2 x 10 34 pile- up Same event w/o pile-up IBL

15 IBL Slides G. Darbo – INFN / Genova CSN1, 22 November 2010 15 Physics Performance b-tagging performance crucial for: New Physics (3 rd generation !) observation of H → bb through boosted WH production Main conclusions of IBL performance Task Force: performance at 2x10 34 with IBL is equal to or better than present ATLAS without pile-up w/o IBL and 10% B-layer inefficiency: b-tagging ~ 3 times worse at 2x10 34 than today b-tagging with pile-up & inefficiencies b-tagging with pile-up 2 jets of 500 GeV event with 2 x 10 34 pile-up Same event w/o pile-up IBL IBL Physics & Performance Task Force – M. Elsing et al.

16 IBL Slides G. Darbo – INFN / Genova CSN1, 22 November 2010 16 The New Front-end Chip (FE-I4) 18 160 FE-I3 (Pixel) FE-I4 (IBL) 80 columns 336 rows 19 mm 20.2 mm 60 KGD / Wafer

17 IBL Slides G. Darbo – INFN / Genova CSN1, 22 November 2010 17 FE-I4 Wafer Received! FE-I4 Production 3 wafers received 27/9 7 more expected early december 6 more held back One wafer partially diced 6 chips put on boards All works! One wafer under probed 41/60 are good! FE-I4 8” wafer - 60 KGD / Wafer FE-I4 die ~2x2 cm 2