Download presentation
Presentation is loading. Please wait.
Published byCollin Houston Modified over 9 years ago
1
Prof. Roy Levow Session 8
2
Steps in Closing a Project Getting Client Acceptance Installing Project Deliverables Documenting the Project Post-Implementation Audit The Final Report Celebrating Success
3
Understand the steps needed to effectively close a project Develop a closing strategy Identify the components of project documentation Conduct a post-implementation audit Explain the significance of each post- implementation audit question Copyright 2007 John Wiley & Sons, Inc.Chapter 113
4
Getting client acceptance of deliverables Ensuring that all deliverables are installed Ensuring that the documentation is in place Getting client sign-off on the final report Conducting the post-implementation audit Celebrating the success Copyright 2007 John Wiley & Sons, Inc.Chapter 114
5
Ceremonial Acceptance Informal in that there is no accompanying sign-off Two situations Client has to accept deliverable by a certain date whether the deliverable meets specifications or not Deliverable requires little or no checking Formal Acceptance Inspection of deliverable expected Checklist Formal sign-off before customer accepts deliverable Copyright 2007 John Wiley & Sons, Inc.Chapter 115
6
The product is turned on when it is delivered to the client Copyright 2007 John Wiley & Sons, Inc.Chapter 116
7
Five Reasons for Documentation Reference for future changes in deliverables Historical record for estimating duration and cost on future projects, activities, and tasks Training resource for new project managers Input for further training and development of the project team Input for performance evaluation by the functional managers of the project team members Copyright 2007 John Wiley & Sons, Inc.Chapter 117
8
Project Overview Statement Project Proposal and backup data Original and revised project schedules Minutes of all project team meetings Copies of all status reports Design documents Copies of all change notices Copies of all written communications Outstanding issues reports Final report Sample deliverables (if appropriate) Client acceptance documents Post-implementation audit report Copyright 2007 John Wiley & Sons, Inc.Chapter 118
9
Six Questions Was the project goal achieved? Does it do what the project team said it would do? Does it do what the client said it would do? Was the project work done on time, within budget, and according to specification? Was the client satisfied with the project results? Was business value realized? (Check success criteria) What lessons were learned about your project management methodology? What worked? What didn’t? Copyright 2007 John Wiley & Sons, Inc.Chapter 119
10
Overall success of the project Organization of the project Techniques used to get results Project strengths and weaknesses Project team recommendations Copyright 2007 John Wiley & Sons, Inc.Chapter 1110
11
What Is the Critical Chain? Variation in Duration: Common Cause versus Special Cause Statistical Validation of the Critical Chain Approach The Critical Chain Project Management Approach Buffers Track Record of Critical Chain Project Management
12
Explain the difference between critical path and the critical chain Identify resource constraints and know how to resolve them Use the critical chain approach to project management for single projects Copyright 2007 John Wiley & Sons, Inc.Chapter 1212
13
The longest path through the project that is both task-dependent and resource-constrained Differs from the critical path, which is the path of the longest duration Critical Chain Project Management is the planning, scheduling, and maintenance of the critical chain Copyright 2007 John Wiley & Sons, Inc.Chapter 1213
14
Common cause variation: “fluctuation in task duration that results from the capacity of that system affecting the task” Natural variations of the system Nothing can be done about this type of variation Special cause variation: fluctuation is caused by a special cause external to the system Variations can be mitigated, planned for, or avoided Copyright 2007 John Wiley & Sons, Inc.Chapter 1214
15
Calculate the 50% duration of a task Calculate the 90% duration of a task The difference between the two is the contingency Copyright 2007 John Wiley & Sons, Inc.Chapter 1215
16
Step One – Create an Early Schedule Project Network Diagram Copyright 2007 John Wiley & Sons, Inc.Chapter 1216
17
Step Two – Convert the Early Schedule to the Late Schedule and Add Resources Copyright 2007 John Wiley & Sons, Inc.Chapter 1217
18
Step Three – Resolve Resource Conflicts Copyright 2007 John Wiley & Sons, Inc.Chapter 1218 One SolutionAnother Solution
19
“Segments of time that are placed at the end of a sequence of tasks for the purpose of protecting the schedule of those tasks.” Types of Buffers Project: Placed at the end of the critical chain to protect the overall project schedule Feeding: Placed at the end of a sequence of tasks that lead into the critical chain Resource: A flag that is placed to alert a resource when it is needed. It has no time length. Copyright 2007 John Wiley & Sons, Inc.Chapter 1219
20
Copyright 2007 John Wiley & Sons, Inc.Chapter 1220
21
Copyright 2007 John Wiley & Sons, Inc.Chapter 1221
22
Successes Honeywell Defense Avionics Systems: Project schedule reduced from 13 months to 6 months Lucent Technologies: Project completed within one year despite estimates it would take longer Harris: Industry standard for factory built and running at 90% capacity is 46 months. Harris factory built and running at 90% capacity in 13 months Israeli aircraft industry: Reduced aircraft maintenance from three months to two weeks Copyright 2007 John Wiley & Sons, Inc.Chapter 1222
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.