1 CROSS-COUNTRY Pipeline Route Selection
MGIS CAPSTONE PROPOSAL CROSS-COUNTRY Pipeline Route Selection Mitigating “Costs” for Early Concept Development By: Geoff Price Advisor: Dr. Todd Bacastow June 22, 2009

2 Overview Problem Statement Old Way, New Way Route Influences
Least-Cost Path Model Builder Inserting Real Cost Research Q & A

3 Problem Select alignment alternatives for optimal cross-country pipeline construction that meet project requirements. Summarize alignment alternatives to facilitate real dollar cost estimation for early concept development (+/- 50%) B Where? & A How Much?

4 Old Problem, Old Solution
The Manual Method Small Scale Paper Maps (USGS, DOE, State Regulatory Dept, etc…) Hand Delineation Terrain Evaluation from Aerial Photographs

5 Old Problem, New Solution
The GIS Method Digital Maps Spatial Database (retrieval & storage) Data Manipulation Data Conversion Raster Analysis (Map Algebra, LCP, etc.) Used properly, GIS methods are faster, more efficient, more comprehensive, and less expensive than traditional methods.

6 Route Influences Engineering/Cost Biophysical Socioeconomic

7 What is Least-Cost Path?
COST SURFACE LEAST-COST SURFACE LEAST-COST PATH (VECTOR) Land Cover COST SURFACE COST SURFACE LEAST-COST Surface LEAST-COST PATH (VECTOR) + = Land Cover Terrain-Slope

8 Cost-Weighted Surface
Influence LEAST-COST/WEIGHTED * = Land Cover + = * = Terrain-Slope

9 LCP & Model Builder LEAST COST PATH

10 LCP Results

11 Inserting Dollar Costs
Pipe Summary Length Geometry Crossing Report Type Subtype Frequency Productivity PF TF GF Construction Summary Labor Crew Equipment Cost Estimate Spread Sheet GIS Cost Estimating Manual

12 Cost Estimating Manual
Productivity Factors General Economy Project Supervision Labor Conditions Equipment Weather Terrain Factor Terrain-Slope Geology Factor Rock Type TF PF Pipeline Length Expected Linear Feet Per 10 Hour Day GF

13 Cost Estimating Manual cont…
Pipeline Layout (Survey) Labor Crews Equipment Spread Clearing & Grading ROW Ditching & Trenching Cleaning & Testing Clean Up Restoration of ROW Summarize Construction Activities

14 Research What are pipeline route selection rules of thumb? (i.e., Engineering, Biophysical, & Socioeconomic). Is there a favorable standard to apply relative “costs” to individual layers? (i.e.., 1,2,3,4 -OR- 1,3,6,9 -OR- other). Identify a process for determining costs & weights. (i.e., Delphi Method, Analytical Hierarchy Process, etc…) Identify benchmark candidate(s) for calibrating LCP and inserting real cost. Using Cost Estimating Manual For Pipelines to quantify labor/equipment estimates and develop a +/-50% cost estimate for route alternatives.

15 Research Time Line Aug/Sept Rules of thumb Cost Standards
Decision Support Techniques Identify Benchmark Process Def. (Model & Spreadsheet) Calibrate/Re-Run Document Findings Aug/Sept

16 Questions?

17 References: Delavar, M.R., 2003, Pipeline Routing Using Geospatial Information System Analysis, ScanGIS' The 9th Scandinavian Research Conference on Geographical Information Science, 4-6 June 2003, Espoo, Finland – Proceedings, pp Mollard, J.D., Penner, Lyncen., Zimmer, Troy., 2008, Pipeline Geo-Environmental Design and Geohazard Management. Chapter 2 Pipeline Route Selection pp. 5-69 Page, S. John, Cost Estimating Manual for Pipelines and Marine Structures, 3rd Ed Section 1, pp 1-65.