NORTH FORK SKOKOMISH POWERHOUSE & FISH FACILITIES 2014 NWHA Generation on the Upgrade Matthew Wilson, P.E.
2
PROJECT LOCATION – CUSHMAN HYDROELECTRIC PROJECT
3
GENERAL INFORMATION TIMELINE = FEBRUARY 2011 – JULY 2013 PROVIDES UPSTREAM & DOWNSTREAM FISH PASSAGE ADDITION OF 3.6 MW FEDERAL ARRA GRANT = $4,671,304 CONSTRUCTION CONTRACT = $15,087,007 TURBINE GENERATOR AND EQUIPMENT = $4,313,723 TOTAL LABOR HRS. WORKED = 69,823
5
SOLIDWORKS RENDERINGAERIAL PHOTO
7
SOLIDWORKS RENDERINGAERIAL PHOTO
8
POWERHOUSE AND FISH COLLECTION BEFOREAFTER
9
FISH TRAM BEFOREAFTER
10
LESSONS LEARNED 1. Know Your Geology a)Pre-construction field studies are important but don’t eliminate all risk.
11
1. Know your Geology – Micropiles
12
LESSONS LEARNED 2. Planning Space
13
LESSONS LEARNED 2. Planning Space
14
LESSONS LEARNED 3. Think About Maintenance
15
LESSONS LEARNED 4. Don’t Hide the Details a)If it’s important, make it obvious b)Tell the Contractor your dimensional tolerances c)Design in such a way that eliminates Contractor mistakes
16
16 Trades CategoriesJourneyman Hours Apprenticeship Hours Sub-Total Hours Apprenticeship Share of Total Labor Hours % Carpenters/Millwright/Diving20,1113,92924,0405.6 Laborer/Pipe layer/Fencing13,0703,04016,1104.3 Operators9,6101,86811,4782.6 Electricians9,5613,33012,8914.7 Other4,7825225,3640.8 Total57,13412,68969,82318.2 REC Credits Goal : 15% Apprenticeship Labor Initiative 937, approved by the voters of Washington State in November of 2006, established that renewable energy projects that commence operation after December 31, 2005 having a minimum level of apprenticeship labor will obtain a credit towards the utility’s renewable energy target.