Center for Risk Management of Engineering Systems University of Virginia 1 Business Process Modeling For VDOT – A Demonstration with the Integrated SYIP/STIP Presentation to the Steering Committee November 9, 2004 Center for Risk Management of Engineering Systems and Department of Systems and Information Engineering University of Virginia www.virginia.edu/crmes/stip
2
Center for Risk Management of Engineering Systems University of Virginia 2 Steering Committee Marsha Fiol Charlie Rasnick Murali Rao Ken Myers Jerry Sears Ben Mannell Chad Tucker Joe Runk Ellett Pollard Barbara Turner Russ Neyman Virginia Transportation Research Council Wayne Ferguson
3
Center for Risk Management of Engineering Systems University of Virginia 3 University of Virginia 2004 – 2005 Research Team Jim Lambert - Associate Professor Rachel Jennings - Graduate Student Andrea Aliberti Jef Benbanaste Seon-Ho Choi Isabelle Estripeaut James Perry Daniel Streufert 2003-2004 Team Priya Sarda – Graduate Student Ryan Tiffany Eric Issadore Rory Smith
4
Center for Risk Management of Engineering Systems University of Virginia 4 Acknowledgments Jennifer DeBruhl Ken Lantz John Nahm Amy Costello Frank Dunn Rob Walters Craig Ahlin Kathy Henley Deborah Grant Gene Wells Joe Orcutt Ahmet Anday Dick Jones Michael Hester Bill Pulkowski Larry Hagan Bill Allbright Reginald Beasley Joseph Paulus
5
Center for Risk Management of Engineering Systems University of Virginia 5 Agenda Overview Case 1 – MPO Process Case 2 – Public Involvement Process Case 3 – Urban and Secondary Road Processes Case 4 – Amendment Process Compatibility of Process Modeler with other Applications IDEF Implementation at VDOT IDEF Software Hands-On Session Discussion
6
Center for Risk Management of Engineering Systems University of Virginia 6 Overview
7
Center for Risk Management of Engineering Systems University of Virginia 7 Motivation SYIP/STIP business process spans many divisions and activities across VDOT Need to focus and bound SYIP/STIP business process modeling that is supportive of current FHWA-VDOT initiatives IDEF documentation should provide a basis for action and remedies to current process deficiencies IT Administration Division builds and maintains over 60 major systems across the agency, including iSYP
8
Center for Risk Management of Engineering Systems University of Virginia 8 Goal Develop business process models of Virginia’s highway and transit construction program with the integrated definition (IDEF) standard that is used across diverse applications of systems engineering. Interact with agency managers who are involved in process reengineering. Test and evaluate commercial software including Process Modeler ™ of Computer Associates, Inc. Consider impact to the financial management of over 1500 construction projects and over a billion dollars of annual investment in transportation.
9
Center for Risk Management of Engineering Systems University of Virginia 9 Process Modeling Methodology Capture description of a process and the network of relations that exists between processes Record the raw data resulting from fact-finding interviews in systems analysis activities Document the decision procedures affecting the states and life-cycle of critical shared data, particularly manufacturing, engineering, and maintenance product definition data Manage data configuration and change control policy definition Make system design and design trade-off analysis
10
Center for Risk Management of Engineering Systems University of Virginia 10 IDEF (Integrated Definition) Structure Activity
11
Center for Risk Management of Engineering Systems University of Virginia 11 Data Needs for IDEF Activities Objective Title of responsible department/s Inputs Controls - consist of legislation, regulations, and policies related to the system Mechanisms - refer to the elements that accomplish the actions of the process, such as people, manual or automated tools, established procedures for holding hearings, etc Outputs Key decisions Impacted activities Estimated duration Related models/diagrams
12
Center for Risk Management of Engineering Systems University of Virginia 12 IDEF Diagram Source: http://www.idef.com/Downloads/pdf/Idef3_fn.pdfhttp://www.idef.com/Downloads/pdf/Idef3_fn.pdf
13
Center for Risk Management of Engineering Systems University of Virginia 13 IDEF Workbook Data Needs Activities
14
Center for Risk Management of Engineering Systems University of Virginia 14 STIP/SYIP Process Models Created Several Process Models –Used IDEF3 –Merged into one large process model –Some of activities had sub-activities Above: STIP Process Model Left: IDEF3 Description
15
Center for Risk Management of Engineering Systems University of Virginia 15 STIP Development Process – Flow Diagram Source: Development and Financial Constraint of Virginia's STIP (2002). Joint FHWA/FTA/VDOT/VDRPT Process Review
16
Center for Risk Management of Engineering Systems University of Virginia 16 STIP Development Process: IDEF Example - Tree Diagram View 1 2
17
Center for Risk Management of Engineering Systems University of Virginia 17 STIP Development Process – IDEF Example – Sub-Process View
18
Center for Risk Management of Engineering Systems University of Virginia 18 Revenue Forecasts – Flow Diagram Source: Development and Financial Constraint of Virginia's STIP (2002). Joint FHWA/FTA/VDOT/VDRPT Process Review
19
Center for Risk Management of Engineering Systems University of Virginia 19 Revenue Forecasts: IDEF Example – IDEF View
20
Center for Risk Management of Engineering Systems University of Virginia 20 Case 1 - MPO Process
21
Center for Risk Management of Engineering Systems University of Virginia 21 Approach 1)Set up an interview with employee from MPO 2)Prepare a set of questions and objectives that match IDEF standard 3)Conduct the interview 4)Verify the information gathered with existing information (e.g. local district, VDOT websites) 5)Dissect information to specific IDEF elements 6)Use information to build the IDEF0 models for MPOs
22
Center for Risk Management of Engineering Systems University of Virginia 22 Building IDEF Model Determine the activities to model
23
Center for Risk Management of Engineering Systems University of Virginia 23 I/O, Constraints, Mechanisms Implement inputs, outputs, constraints, and mechanisms Inputs Outputs Mechanisms Constraints
24
Center for Risk Management of Engineering Systems University of Virginia 24 Additional Details Add additional details to activities
25
Center for Risk Management of Engineering Systems University of Virginia 25 MPO Sub-Activities Add sub-activities underneath a main activity
26
Center for Risk Management of Engineering Systems University of Virginia 26 Overall MPO Activities
27
Center for Risk Management of Engineering Systems University of Virginia 27 Case 2 - Public Involvement Process
28
Center for Risk Management of Engineering Systems University of Virginia 28 Advertising 30 day in advance requirement 1 week in advance requirement Public hearing Transportation projects presentation Public comments Comment posting STIP for public review Final STIP Embedded comments Public notice of final STIP IDEF Model: Public Involvement Virginia Department of Transportation. Public Involvement: Your Guide to Participating in the Transportation Planning and Programming Process http://www.virginiadot.org/infoservice/resources/Final%20PI%20Guide.pdf http://www.virginiadot.org/infoservice/resources/Final%20PI%20Guide.pdf
29
Center for Risk Management of Engineering Systems University of Virginia 29 IDEF Model: Public Involvement
30
Center for Risk Management of Engineering Systems University of Virginia 30 Analysis of Public Involvement Activities Advertising requirements of VDOT: 30 days in advance 1 week before the hearing Mechanisms used for advertising: Newspapers TV Radio Kiosks Internet VDOT and DRPT officials receive comments from citizens 1. Advertising Virginia Department of Transportation. Public Involvement: Your Guide to Participating in the Transportation Planning and Programming Process http://www.virginiadot.org/infoservice/resources/Final%20PI%20Guide.pdf http://www.virginiadot.org/infoservice/resources/Final%20PI%20Guide.pdf
31
Center for Risk Management of Engineering Systems University of Virginia 31 Analysis of Public Involvement Activities 2. Public Hearing VDOT or DRPT present STIP projects in a public location Information is provided on how to make follow-up comments VDOT submits a draft of the STIP for public revision VDOT and DRPT offices Public libraries Virginia Department of Transportation. Public Involvement: Your Guide to Participating in the Transportation Planning and Programming Process http://www.virginiadot.org/infoservice/resources/Final%20PI%20Guide.pdf http://www.virginiadot.org/infoservice/resources/Final%20PI%20Guide.pdf
32
Center for Risk Management of Engineering Systems University of Virginia 32 Analysis of Public Involvement Activities 3. Comment Posting Comments from the public hearing: Posted on VDOT’s and DRPT’s website Evaluated and embedded in the STIP 4. STIP Public Review Draft of the STIP: Submitted for public review Access in public libraries and VDOT and DRPT offices Citizens submit comments Virginia Department of Transportation. Public Involvement: Your Guide to Participating in the Transportation Planning and Programming Process http://www.virginiadot.org/infoservice/resources/Final%20PI%20Guide.pdf http://www.virginiadot.org/infoservice/resources/Final%20PI%20Guide.pdf
33
Center for Risk Management of Engineering Systems University of Virginia 33 Analysis of Public Involvement Activities 5. Final STIP 6. Public Notice of Final STIP Corrected version of the STIP based on the comments made by the public Formatted to fit federal requirements Submitted to USDOT Submitted for public access The public can access the final STIP for personal reference VDOT and DRPT use newspapers and their websites to announce the final STIP Virginia Department of Transportation. Public Involvement: Your Guide to Participating in the Transportation Planning and Programming Process http://www.virginiadot.org/infoservice/resources/Final%20PI%20Guide.pdf http://www.virginiadot.org/infoservice/resources/Final%20PI%20Guide.pdf
34
Center for Risk Management of Engineering Systems University of Virginia 34 FHWA’s Review on Public Involvement FHWA’s Guidelines of procedure: Acting in accord with basic democratic principles Continuous contact between agency and non-agency people throughout transportation decision-making Use of a variety of public involvement techniques Active outreach to the public Focusing participation on decisions Steps to plan and implement a public involvement program: Set goals and objectives for your public involvement program. Identify the people to be reached. Develop a general approach or set of general strategies Flesh out the approach with specific techniques. Assure that proposed strategies and techniques aid decision-making to close the loop. Evaluation of Public Participation in Virginia, Review by FHWA, 2002 http://www.virginia.edu/crmes/stip/Statewide+Planning+VDOT.pdfhttp://www.virginia.edu/crmes/stip/Statewide+Planning+VDOT.pdf
35
Center for Risk Management of Engineering Systems University of Virginia 35 STIP Development Process Source: Development and Financial Constraint of Virginia's STIP (2002). Joint FHWA/FTA/VDOT/VDRPT Process Review
36
Center for Risk Management of Engineering Systems University of Virginia 36 Tentative Program Planning Source: Development and Financial Constraint of Virginia's STIP (2002). Joint FHWA/FTA/VDOT/VDRPT Process Review
37
Center for Risk Management of Engineering Systems University of Virginia 37 Secondary Roads Planning Source: Development and Financial Constraint of Virginia's STIP (2002). Joint FHWA/FTA/VDOT/VDRPT Process Review
38
Center for Risk Management of Engineering Systems University of Virginia 38 Urban Programs Planning Source: Development and Financial Constraint of Virginia's STIP (2002). Joint FHWA/FTA/VDOT/VDRPT Process Review
39
Center for Risk Management of Engineering Systems University of Virginia 39 MPO Planning Source: Development and Financial Constraint of Virginia's STIP (2002). Joint FHWA/FTA/VDOT/VDRPT Process Review
40
Center for Risk Management of Engineering Systems University of Virginia 40 Public Involvement Workbook
41
Center for Risk Management of Engineering Systems University of Virginia 41 Public Involvement Toolkit VTRC’s Proposed Toolkit Minnesota’s Public Involvement Toolkit A Public Involvement Toolkit should be implemented for the selection of Public Outreach techniques. Source: VDOT and VTRC 2003 Phase II Report
42
Center for Risk Management of Engineering Systems University of Virginia 42 Case 3 - Urban and Secondary Roads Processes
43
Center for Risk Management of Engineering Systems University of Virginia 43 Research Methodology Collect Information Organize Information Apply Information
44
Center for Risk Management of Engineering Systems University of Virginia 44 Collect Information Schedule an appointment for a phone or personal interview with an upper level employee within appropriate division Prepare a set of questions that will answer objectives described by the IDEF model Conduct the interview at the scheduled time
45
Center for Risk Management of Engineering Systems University of Virginia 45 Organize Information Combine interview notes with other outside information to compile a comprehensive collection of relevant information Organize information into individual elements described by the IDEF standard
46
Center for Risk Management of Engineering Systems University of Virginia 46 Apply Information Apply the information to the elements and create an IDEF model
47
Center for Risk Management of Engineering Systems University of Virginia 47 Urban Programs in IDEF0
48
Center for Risk Management of Engineering Systems University of Virginia 48
49
Center for Risk Management of Engineering Systems University of Virginia 49 Preliminary Engineering Inputs: analysis Controls: budget and requirements Mechanisms: groups working on PE effort Output: draft of programming resolution
50
Center for Risk Management of Engineering Systems University of Virginia 50 Right-of-Way Inputs: draft of programming resolution Controls: budget, utility and residential constraints, and requirements Mechanisms: drafts from FHWA Output: authorized right-of-way, and approved programming resolution
51
Center for Risk Management of Engineering Systems University of Virginia 51 Contract for Construction Inputs: authorized right-of- way, approved programming resolution, federal and state authorization Controls: budget and requirements Mechanisms: external bidders Output: awarded contract
52
Center for Risk Management of Engineering Systems University of Virginia 52 Secondary Roads in IDEF0
53
Center for Risk Management of Engineering Systems University of Virginia 53 Current Process Flow Source: Secondary Roads Six Year Process Presentation
54
Center for Risk Management of Engineering Systems University of Virginia 54 Main Processes
55
Center for Risk Management of Engineering Systems University of Virginia 55 Work Session Sub Process
56
Center for Risk Management of Engineering Systems University of Virginia 56 Approval Sub Process
57
Center for Risk Management of Engineering Systems University of Virginia 57 Case 4 - Amendment Process
58
Center for Risk Management of Engineering Systems University of Virginia 58 Tracking of STIP Amendments Hundreds of amendments are processed each year to revise a current project in the STIP or to add a new project The amendment process has no documented structure We developed an IDEF model and associated flowchart to document all activities
59
Center for Risk Management of Engineering Systems University of Virginia 59 Amendment Process Workbook
60
Center for Risk Management of Engineering Systems University of Virginia 60 Flowchart of Amendment Process
61
Center for Risk Management of Engineering Systems University of Virginia 61 Compatibility of Process Modeler with other Applications
62
Center for Risk Management of Engineering Systems University of Virginia 62 Exporting to Simulation Software Models can be exported from AllFusion to simulation software. Simulation represents a real world system by software to gain insight into the operation of those systems. Used for documenting, animating, and demonstrating the variability and dynamics of a process map such as those done in VISIO or other static drawing packages (such as AllFusion). Simulation can be used to model the SYIP and STIP life-cycles to provide information and visualizations that can help determine bottlenecks, decrease project development time and further understand these processes.
63
Center for Risk Management of Engineering Systems University of Virginia 63 The STIP Project Development Process The project development process was modeled in IDEF3 through the synthesis of: The Virginia Department of Transportation’s memorandum on the preliminary engineering project development process dated September 15, 2003. The “How a Road Gets Built Fact Sheet” from VDOT’s website. An interview with Frank Dunn on project development.
64
Center for Risk Management of Engineering Systems University of Virginia 64 The Project Development Process in IDEF3
65
Center for Risk Management of Engineering Systems University of Virginia 65 Simulating the STIP Development Process The STIP project development process can be exported to simulation software. A single command exports the whole model into Arena. The model can then be run to view the animation.
66
Center for Risk Management of Engineering Systems University of Virginia 66 The Project Development Process in Arena
67
Center for Risk Management of Engineering Systems University of Virginia 67 The Project Development Simulation Benefits of visual representations like simulation: –Animating the STIP and SYIP processes –Facilitate the analysis of these models –Determining bottlenecks –Tracking how a construction project evolves through its life cycle
68
Center for Risk Management of Engineering Systems University of Virginia 68 IDEF Supporting Evolution of iSYP Integrated Six Year Program Brings together data from various source systems to produce an integrated view of the financial aspects of projects in the CTB's Six-Year Program. Detailed database structure of the iSYP found on the Transportation Research Council’s computers. Database modeling and design using Computer Associates’ AllFusion ERwin Data Modeler.
69
Center for Risk Management of Engineering Systems University of Virginia 69 Attributes of entities are listed. Relationships between entities are defined iSYP Database Structure
70
Center for Risk Management of Engineering Systems University of Virginia 70 Descriptions of SYIP Related Attributes Formal definitions of attributes listed in the database structure can be found on VDOT’s Data Shopper
71
Center for Risk Management of Engineering Systems University of Virginia 71 IDEF Implementation at VDOT
72
Center for Risk Management of Engineering Systems University of Virginia 72 Software Packages Relevant to Future Automation of STIP Project Management Three Types of Software Packages: –Document Management Software –Planning and Programming Software –Business Process Management Software
73
Center for Risk Management of Engineering Systems University of Virginia 73 Document Management Software Hummingbird DOCS Open (Document Management System): –Help organizations to effectively and efficiently manage the entire information chain. –Users control, organize, access, and share corporate information quickly, easily, and accurately. –Word processing documents, spreadsheets, presentations, forms, images, e-mail messages, and any other type of file that needs to be saved, secured, and archived can be managed.
74
Center for Risk Management of Engineering Systems University of Virginia 74 Document Management Software Kofax Ascent Capture: –Collect paper documents, forms and e-documents, paper documents, forms and e-documents, transform into accurate, retrievable information, and deliver into business applications and databases. –Remote offices scan documents directly into the central Ascent Capture process. –Forms-processing modules extract information from documents, postal mail scanning, microfilm archiving for long-term records retention. –Deliver information into workflow and content management systems via releasing modules written in Visual Basic.
75
Center for Risk Management of Engineering Systems University of Virginia 75 Document Management Software Adobe Acrobat Capture Cluster: –Optical character recognition (OCR). –Advanced page-layout and content recognition. –Image clean up before applying recognition. –Choose output file format that best suits requirements. –Can integrate Acrobat Capture with existing software. –Find flexible scanning and files input options.
76
Center for Risk Management of Engineering Systems University of Virginia 76 Planning and Programming Software Hummingbird Enterprise 2004 – Workflow: For End Users –Receive assigned tasks and related content via e-mail, browser, instant messaging alert, mobile device, or WebTop. –Alerts to overdue, incomplete and escalated tasks and delegate in one click if permitted For Administrators –Easily define graphical workflows by dragging and dropping steps, setting conditional branching logic, escalations, and business rules. –Simulate process successes and failures during the design stage. –Monitor status at a glance with graphical snapshot views of all processes. –Make rapid adjustments or enhancements to business processes as demanded For Organizations –Move content through creation, approval and publishing lifecycle stages more quickly and consistently. –All information, content and metadata related to processes can be maintained. –React quickly to opportunities, customer requests and changing market conditions.
77
Center for Risk Management of Engineering Systems University of Virginia 77 Business Process Management Software FileNet Compliance Framework –Business Process Manager, Content Manager, Records Manager, eForms Reduce and manage risk to avoid shutdowns, penalties and legal action. Proactive and immediate response to material events. Visibility and control of business processes and related information. Security and privacy of information. Monitoring and reporting capabilities for auditing purposes. Maximum flexibility and agility to better respond to the changing regulatory environment.
78
Center for Risk Management of Engineering Systems University of Virginia 78 Business Process Management Software FileNet Business Process Manager –Optimized operational efficiency and resources utilization. –Enforced corporate standards and process consistency. –Shortened process cycle times while enabling better decisions. –Reduced complexity of integrating people, processes and existing systems.
79
Center for Risk Management of Engineering Systems University of Virginia 79 Locating (STIP) and (SYIP) Business Process Effort in VDOT’s Intranet (Coweb) Business process models were found in the environmental division website. Example: The business process model designed by the environmental division for the hazardous materials review process.
80
Center for Risk Management of Engineering Systems University of Virginia 80 Data Management Division According to the Data Administration website, under Data Modeling Requirements for COTS Systems there is a requirement for what Business Process Models would be acceptable into the Data Management Division –Business Process Model Business process models (BPM) provide a framework for identifying, defining, and organizing the functional strategies, rules and activities needed to manage and support the way an organization does, or wants to do business. It provides a graphical and textual framework for organizing activities into manageable groupings to facilitate their shared use and control throughout the agency. The BPM is required by PMLG “Redesign Core Business Process 2.5”. The Computer Associate’s AllFusion program would fulfill these requirements and is an acceptable Business Process Model to be used by the Data Management Division
81
Center for Risk Management of Engineering Systems University of Virginia 81 Management Services Division The Concurrent Engineering Process Flowchart to the right shows how the IDEF modeling could be used in the Management Services Division Found in Instruction and Information Memorandum on the fifth page at: –http://www.extranet.vdot.state.va.us/ locdes/electronic%20pubs/iim/IIM22 6.pdfhttp://www.extranet.vdot.state.va.us/ locdes/electronic%20pubs/iim/IIM22 6.pdf
82
Center for Risk Management of Engineering Systems University of Virginia 82 IDEF Software Hands-On Session
83
Center for Risk Management of Engineering Systems University of Virginia 83 IDEF Demonstration: An Example of Public Involvement IDEF Framework:
84
Center for Risk Management of Engineering Systems University of Virginia 84 Discussion
85
Center for Risk Management of Engineering Systems University of Virginia 85 Questions for discussion 1. What is the value to better describe who does what, how, and why in major business processes? 2. What are the lessons learned from the demonstration of business process modeling to the STIP/SYIP? 3. What are the opportunities to aid priority-setting and resource allocation across all or particular IT systems? 4. What are the potential uses of business process modeling for other processes of the transportation agencies?
86
Center for Risk Management of Engineering Systems University of Virginia 86 Backup Slides
87
Center for Risk Management of Engineering Systems University of Virginia 87 Project Website (www.virginia.edu/crmes/stip)www.virginia.edu/crmes/stip Source: www.virginia.edu/crmes/stipwww.virginia.edu/crmes/stip
88
Center for Risk Management of Engineering Systems University of Virginia 88 Updated Final Report for this Project (9-07-04) - RKJ DRAFT of the Final Report for this Project (7-14-04) - RKJDRAFT of the Final Report for this Project (7-14-04) - RKJ *Updated 9-03-04 AllFusion Program Screenshots (9-02-04) - RKJ DCC Work Flow Diagram sent by Bill Pulkowski (9-01-04) - RKJ Bill Pulkowski Phone Interview and email from SCC (9-01-04) - RKJ Concurrent Engineering Process Flowchart for Capstone Team to turn into IDEF (8-30-04) - RKJ Original Document Data Modeling Requirements for COTS Systems (8-30-04) - RKJ Project Development Chart created from Dick Jones 8/13 Interview (8-27-04) - RKJ Dick Jones Phone Interview (8-23-04) - RKJ Action Items to do after Monday August 23rd (8-13-04) - RKJ Dick Jones Email, Data Modeling Requirements for COTS Systems (8-13-04) - RKJ Amy Costello Email, Project Life Cycle, Links (8-13-04) - RKJ Frank Dunn Interview on Project Development (8-13-04) - RKJ Progress Since Initiation of Contract (8-12-04) - RKJ Action Items from July 21st Meeting with BioTech (7-26-04) - RKJ Progress Report presented to BioTech (7-23-04) - RKJ Notes from meeting with BioTech (7-22-04) - RKJNotes from meeting with BioTech (7-22-04) - RKJ *Updated 7-27-04 Process Development and Integration for the Six-Year Program and the Statewide Transportation Improvement Program Materials
89
Center for Risk Management of Engineering Systems University of Virginia 89 Process Development and Integration for the Six-Year Program and the Statewide Transportation Improvement Program Materials (Cont.) Transportation & Mobility Planning Division STIP schedule as of June 1, 2004 (Draft) (6-28-04) - RKJ STIP Development Process in AllFusion Program (6-24-04) - RKJSTIP Development Process in AllFusion Program (6-24-04) - RKJ *Need CA AllFusion Program to open document Ahmet Anday and Amy Costello Interview (6-23-04) - RKJ IDEF Worksheet Questions asked during Interviews (6-14-04) - RKJ Financial Planning Section from the National Highway Institute/National Transit Institute class taught by Jennifer DeBruhl (6-11-04) - RKJ Programming Section from the National Highway Institute/National Transit Institute class taught by Jennifer DeBruhl (6-11-04) - RKJ Jennifer DeBruhl Interview (6-09-04) - RKJ IDEF Worksheet Update - Compilation of Previous Worksheets (6-04-04) - RKJIDEF Worksheet Update - Compilation of Previous Worksheets (6-04-04) - RKJ *Updated 6-25-04 Success with CA AllFusionSuccess with CA AllFusion- Document describing SRAs success with the AllFusion Program (6-03-04) - RKJ Example of AllFusion ProjectExample of AllFusion Project - Created by Voluntary Interindustry Commerce Standards (6-03-04) - RKJ Information on AllFusion Process ModelerInformation on AllFusion Process Modeler - (6-03-04) - RKJ IDEF Worksheet Update - Construction Process - RTS - 5/6/04 Craig Ahlin Interview (05-06-04) Progress Report Presentation - April 27th meeting (4-27-04) SIEDS 2003 - Conference Presentation (4-16-04)
90
Center for Risk Management of Engineering Systems University of Virginia 90 Notes from Deborah Grant Interview - 4/14/04 - ELI Deborah Grant Interview - Federal Aid FMIS (4-13-04) - ELI Deborah Grant Interview - Right of Way Template (4-13-04) - ELI Deborah Grant Interview - Preliminary Engineering Estimate Template (4-13-04) - ELI Deborah Grant Interview - Team District Assignments (4-13-04) - ELI Deborah Grant Interview - Blank Construction FMIS Document - (4-13-04) - ELI Deborah Grant Interview - Blank PE-1 Template - (4-13-04) - ELI Deborah Grant Interview - Blank RW-201 Template - (4/13/04) - ELI SIEDS 2004 - Conference Poster (4-12-04) SIEDS 2004 - Conference Paper (4-12-04) Notes from March 24th meeting with VDOT (4-4-04) Progress Report Presentation - March 24th meeting (3-24-04) Vision for Integrated STIP - Charlie Rasnick Email Transcript (03-19-04) Supplementary Emails Explaining the Vision for an Integrated STIP (03-19-04) Progress Report, University of Virginia (02-24-04) IDEF Worksheet - STIP Process (02-23-04) IDEF Worksheet - STIP Process (03-04-04IDEF Worksheet - STIP Process (03-04-04) IDEF Worksheet - Amendment Process (02-24-04) IDEF Worksheet - Amendment Process (03-09-04) Process Development and Integration for the Six-Year Program and the Statewide Transportation Improvement Program Materials (Cont.)
91
Center for Risk Management of Engineering Systems University of Virginia 91 Progress Report, University of Virginia (01-23-04) Progress Report, University of Virginia (11-19-03) Revised STIP Proposal (11-18-03) Materials from Joint FHWA,VTRC and VDOT meeting (11-17-03) STIP Procedures Memorandum of Agreement Evaluation of Public Participation in Virginia, Review by FHWA, 2002 Public Involvement Techniques for Transportation Decision-making-1996 (FHWA site) Assessment of VDOT's Public Involvement Practices -- Final Report, June 2003 Materials from STIP Committee Meeting (10-21-03) STIP-04 TimeLine FY04-06 STIP FY04-09 SYIP Meeting with Mr. Murali Rao (Current STIP Poster, Current STIP Sub-Processes, Recommended STIP ) (10- 15-2003)Current STIP PosterCurrent STIP Sub-ProcessesRecommended STIP Culpeper Public Hearing Meeting (10-09-2003) Six Year Program - Report on Development, Monitoring, Implementation and Best Practices (10-07-2003) STIP - Massachusetts (10-06-2003) Lynchburg Public Hearing Meeting (09-30-2003) Presentation by James H. Lambert (09-15-2003) Changes In Work Plan (07-07-2003Changes In Work Plan (07-07-2003) Process Development and Integration for the Six-Year Program and the Statewide Transportation Improvement Program Materials (Cont.)
92
Center for Risk Management of Engineering Systems University of Virginia 92 VDOT Home VDOT Organization Chart Projects and Plans Public Hearings Meetings and Events Fall 2003 Hearing Schedule SYIP SYIP Public Hearings Powerpoint SYIP 2004-2009 Report SYIP Update Public Hearings Fall 2003 Information Projects in the SYIP STIP Citizen's Guide STIP Amendment Process Draft Letters (provided by Gene Wells 03-03-04) 1 2 3123 CAPSTONE Team Readings STIP FY-05 Timeline STIP and TIP Development Process, Utah DOT - Coordination with MPO, UTA, FHWA and UDOT, September 2001STIP and TIP Development Process, Utah DOT AllFusion Process Getting Started Guide AllFusion Process Modeler Methods Guide FAQ on TIP Development and Financial Constraint of Virginia's STIP - Joint FHWA/FTA/VDOT/VDRPT Process Review, November 2002Development and Financial Constraint of Virginia's STIP Process Development and Integration for the Six-Year Program and the Statewide Transportation Improvement Program Materials (Cont.)