Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management
2
Contents n Introduction to Project Integration Management n Project Plan Development n Project Plan Execution n Integrated Change Control n Glossary
3
Introduction to Project Integration Management n Includes processes required to ensure that the various elements of the project are properly coordinated. n Making tradeoffs meet or exceed stakeholders needs and expectations competitive objectives and alternatives
4
Carrying out the project plan Integrating and coordinating project plans: creating a consistent and coherent document Coordinating changes across the entire project Introduction to Project Integration Management Major processes of Project Integration Management Project Plan Development Project Plan Execution Integrated Change Control
5
n Some characteristics of these processes – They are primarily integrative – They interact with each other and with the processes in the other knowledge areas – They occur at least once in every project phase – They may overlap n Focus of this chapter – Processes, tools and techniques used to integrate these processes Introduction to Project Integration Management
6
Project Integration Management Overview Project Plan Execution Integrated Change Control Project Integration Management Inputs Tools and Techniques Outputs Project Plan Development
7
n Create a consistent and coherent document that can be used to guide both project execution and project control n This process is almost always iterated several times – Capture and decompose the work of the project: Work Breakdown Structure (WBS) – The defined work is planned, estimated and scheduled, and authorized: Control Account Plans (CAPs) Project Plan Development The sum of all the integrated management control plans will constitute the total project scope
8
n Project Plan is used to – Guide project execution – Document project planning assumptions – Document project planning decisions regarding alternative chosen – Facilitate communication among stakeholders – Define key management reviews as to content, extent and timing – Provide a baseline for progress measurement and project control Project Plan Development
9
n Other planning outputs – in the other knowledge areas – base documents, such as WBS – application area-specific inputs n Historical information n Organizational policies – Quality management – Personnel administration – Financial controls Project Plan Development - Inputs
10
n Constraints – Applicable restriction that will affect the performance of the project n Assumptions – Factors that are considered to be true, real or certain, for planning purposes – Generally involve a degree of risk Project Plan Development - Inputs
11
n Project planning methodology – structured approach used to guide project team during development of the project plan – it can be simple or complex – makes use of hard and soft tools n Stakeholder skills and knowledge – environment in which stakeholders can contribute appropriately Project Plan Development - Tools and Techniques
12
n Project management information system (PMIS) – tools and techniques used to gather, integrate and disseminate the outputs of project management processes – from initiating through closing – manual and automated systems n Earned value management (EVM) – Integrates project’s scope, schedule and resources – Measures and reports project performance Project Plan Development - Tools and Techniques
13
n Project plan – formal and approved document used to guide both project execution and project control – It may be summary or detailed – the same as Integrated project plan, in some application areas – Project plan X Project performance measurement baselines n Supporting details Project Plan Development - Outputs
14
Inputs Tools and Techniques Outputs Project Integration Management Overview Project Plan Execution Integrated Change Control Project Integration Management Project Plan Development
15
n Some characteristics of this process – Primary process for carrying out the project plan – The vast majority of the project’s budget is expended in performing this process – It is the project process that is most directly affected by the project application area – Performance against the project baseline must be continuously monitored Corrective actions Periodic forecast of the final cost and schedule results Project Plan Execution
16
n Project plan and supporting details – Output of the project plan development process n Organizational policies – It is also Input to the project plan development process n Preventive action – Anything that reduces the probability of potential consequences of project risk events n Corrective action – Anything done to bring expected future project performance in line with the project plan – Output of the various control processes Project Plan Execution - Inputs
17
n General management skills – Essential to effective project plan execution n Product skills and knowledge n Work authorization systems – Formal procedure for sanctioning project work to ensure that work is done at the right time and in the proper sequence – Value of the control X Cost of the control Project Plan Execution - Tools and Techniques
18
n Status review meetings – They will be held at various frequencies and on different levels n Project management information system (PMIS) n Organizational procedures Project Plan Execution - Tools and Techniques
19
n Work results – Information on work results is collected and fed into the performance reporting process – Tangible and intangibles deliverables n Change requests Project Plan Execution - Outputs
20
Inputs Tools and Techniques Outputs Project Integration Management Overview Project Plan Execution Integrated Change Control Project Integration Management Project Plan Development
21
n This process is concerned with – Influencing the factors that create changes to ensure that changes are agreed upon – Determining that a change has occurred – Managing the actual changes when and as they occur n It requires – Maintaining the integrity of the performance measurement baselines – Ensuring that changes to the project scope are reflected in the definition of the project scope – Coordinating changes across knowledge areas Integrated Change Control
22
n Project plan – Provides the baseline against which changes will be controlled n Performance reports – Provide information on project performance n Change requests – Oral / Written – Direct / Indirect – Externally / Internally initiated – Legally mandated / Optional Integrated Change Control - Inputs
23
n Change control system – Collection of formal and documented procedures that define how project performance will be monitored and evaluated – Includes the steps by which official project documents may be changed – Some characteristics Group responsible to approving or rejecting proposed changes Procedures to handle changes that may be approved without prior review Integrated Change Control - Tools and Techniques
24
n Configuration management n Performance measurement n Additional planning – Projects seldom run exactly according to plan n Project management information system (PMIS) Integrated Change Control - Tools and Techniques
25
n Project plan updates n Corrective action n Lessons learned – Include causes of variances, reasoning behind the corrective action chosen and other types of lessons learned should be documented Integrated Change Control - Outputs
26
n Assumptions and Constraints n Baseline n Control Account Plans (CAPs) n Earned Value Management (EVM) n Earned Value (EV) n Project charter n Project management information system (PMIS) n Project management software n Project plan n Work Breakdown Structure (WBS) Glossary
27
Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management