FAIR – Facility for Antiproton and Ion Research Austria China Finnland France Germany Greece India Italy Poland Slovenia Spain Sweden Romania Russia UK Observers Status of FAIR FAIR 2 nd Instit. Meeting, January 15/16 th, 2008 H.H.Gutbrod Leader FAIR Joint Core Team
2
Official start of the FAIR Project on November 7 th, 2007 at Darmstadt...............................................with about 1400 participants
3
FAIR Start Event November 7 th, 2007
4
We have a project under way! Who decided to participate and has not yet started to work should start now! Do not wait to get design drawings from somewhere! You are the designer, producer, installer,commissioner! JCT -later FAIR GmbH - is ‘just’ project management
5
Status of Declarations from FAIR partner countries Red= written declaration, black= no written declaration yet, green=high chance for add. contribution Austria 0.5% China1.=% minimum Finland0.5% minimum France1% minimum Greece?? India3% minimum Italy40 Mio € minimum (3.36%) Poland30 Mio € minimum (2.5%) Romania1% Russia5%, has now initiated steps for 10% Slovenia1% Spain2% minimum Sweden10 Mio € (0.84%) UK 15 Mio € (1.25%), has proposed additional 45 Mio € Sum 22,95% + 5% Russia + 3.79% UK = 31.74 % of FAIR _Project Further candidates: Slovak Republic, The Netherlands, Hungary, Georgia,
6
Call for EoIs sent out October 10th, 2007
7
Status of Response to Call for Expression of Interest (EoI)
8
EoIs still missing from 21 Expression of Interests received so far !
9
WP 2.3 HEBT
10
WP 2.4 Super FRS
11
WP 2.5 Collector Ring CR
12
WP 2.6 NESR
13
WP 2.7 Proton Linac
14
WP 2.8 SIS 100
15
WP 2.9 P-bar Target and Separator
16
WP 2.12 SIS 300
17
WP 2.13 Electron Ring at NESR
19
Call for Expression of Interest to participate in the construction of FAIR is a big success : The FAIR accelerator complex will be built by the leading experts of the FAIR countries! Something money cannot buy! Missing EoIs from: France, Greece, Slowenia, UK –Missing MoU countries most urgently invited to follow up the call, since we need to advance at the ISC meeting on February 18 th, upon recommendations of IKAB on January 8 th –Certain overlap of interests require creation of accelerator consortia, e.g. p- Linac, NESR, Super-FRS etc.. –Next steps..... Status of Response to Call for Expression of Interest (EoI)
20
http://www.ihep.su/FAIR-meeting/index.shtml
21
January 15th, 2008 09:00 – 09:15 Welcome and short presentation of the host laboratoryNikolai Tyurin 09:15 – 09:30 Rosatom and FAIR Russia Oleg Patarakin 09:30 – 10:00 Accelerator complex of IHEP-ProtvinoSergei Ivanov 10:00 – 10:30 FAIR Russia Research CentreBoris Sharkov 10:30-11:00 COFFEE Break 11:00 – 11:20 Status of FAIR Expression of InterestsHans Gutbrod 11:20– 11:40 Report from the IKAB meetingHorst Wenninger 11:40 – 12:10 Status report on FAIR accelerators, general planningDieter Krämer 12:20 – 12:50 Design and Engineering Issues; Standardization and SynergiesDieter Krämer LUNCH break
22
14:20 -17:10 Start of discussions of work packages in detail, milestones, readiness etc., short presentations of representatives of the interested institutions (countries). 14:20 – 14:502.4, Super Fragmentseparator EoIs No. 1, 2, 11a, 13e, 13h, 13i, 14a, 15, 21 VECC (IN), Profex (Ro), CIEMAT (ES), GSI, IMP (CN), Wroclaw UT (PL), Soltan Inst. (PL), (France)for the machine coordination: Markus Steck 14:50 – 15:102.5 CR (Collector Ring) EoIs No.5a, 8b, 13b, 13c, 13h, 13i, 14b, 15, 21 Budker INP (RU), ITEP (RU), GSI, IMP (CN), Wroclaw UT (PL), Soltan Inst. (PL),for the machine coordination: Markus Steck 15:10 – 15:302.6 NESR (New Experimental Storage Ring) EoIs No. 5b, 11b,13b,13i, 21 Budker INP (RU), CIEMAT (ES), GSI, Soltan Inst. (PL) for the machine coordination: Markus Steck 15:30 – 15:502.10 RESR (Recuperated Experimental Storage Ring) EoIs No. 8b, 11c, 13b, 13c, 13h, 13i, 21 ITEP (RU), CIEMAT (ES), GSI, Soltan Inst. (PL) for the machine coordination: Markus Steck COFFEE
23
16:00 – 16:202.3 HEBT (High-Energy Beam Transfer Lines) EoIs No. 13h, 13i, 18, 20, 21 GSI, ICSI (RO), Efremov (RU), Soltan Inst. (PL) for the machine coordination: Peter Spiller 16:20 – 16:502.8 SIS 100 (Heavy-Ion Synchrotron 100 Tm) EoIs No. 4, 7, 8a, 9, 12, 13b, 13f, 13g, 13h, 13i, 15, 18, 21 Finland, Cracow UT (PL), ITEP (RU), JINR, VNIINM (RU), GSI, Wroclaw UT (PL), ICSI (RO), Soltan Inst. (PL) for the machine coordination: Peter Spiller 16:50 – 17:152.12 SIS 300 (Heavy-Ion Synchrotron, 300 Tm) EoIs No. 3, 4, 7, 8a, 12, 19, 21 IHEP (RU), Finland, Cracow UT (PL), ITEP (RU), VNIINM (RU), Italy, Soltan Inst. (PL)for the machine coordination: Peter Spiller 17.15 – 19.00 Excursion to the IHEP accelerator complex and the workshops. 19.30Dinner at the Scientists’ club
24
January 16th, 2008 09:00 – 10:40 Continuation of discussions of work packages in detail, milestones, readiness etc. 9:00 – 9:252.7 Proton Linear Accelerator EoIs No. 8c, 13a, 13b, 16 ITEP (RU), GSI, Dept of Science and Technology (IN), (France) for the machine coordination: Hartmut Eickhoff 9:25 – 9:552.9 Antiproton-Target, and 2.11, HESR (High-Energy Storage Ring) for 2.9: EoIs No. 13h, 13i, 21 for 2.11: EoIs No. 8b, 10, 17, 21 ITEP (RU), Jülich (DE), Sweden, Soltan Inst. (PL) for the machine coordination: Dieter Krämer 9:55 – 10:152.13 ER (Electron Ring) EoIs No. 5c, 21 Budker INP (RU), Soltan Inst. (PL) for the machine coordination: Markus Steck 10:15 – 10:50Items not yet covered Discussion leader: Hans Gutbrod 10:50 – 11:10COFFEE break 11:10 – 13:00 Summary and focus on critical points, multiple interest for one work package, specs, way of collaborations, perhaps formation of collaborations, Technical Design Reports, next steps... Discussion leader: Hans Gutbrod 13:00LUNCH 14.30End of the Meeting
25
2 nd FAIR institutes meeting
26
Next Steps: Detailing of EoIs in upcoming meeting and weeks, especially identification of persons in charge, better specification of items, collaborations.......active collaboration with international FAIR partners strengthening the FAIR project and the FAIR JCT by detaching people to Darmstadt. Preparation of Technical Design Reports Setting up of Machine Advisory Committee Drafting of contracts where possible --------------------------------- ISC meeting 19th of February 2008 Final Act by FAIR countries’ governments Creation of FAIR GmbH early Summer of 2008 Staffing of managing director positions But above all that: Continue or get started with the FAIR accelerator projects you want to work on!