Mathew Watkins: Project Manger Larry Wu: Hardware Engineer Eric Robbins : Software Engineer Libby John: Systems Engineer Sponsor: Jeff Smith Advisor: Dr. Yong-Kyu Jung A.I.R Automated Individual Remote September 13, 2006
2
Functional Design
3
Technical Merit Table Technical Merit Number Technical Merit FactorWeight (max) Earned (est.) 1Contains a clearly described and completely understood technical challenge 0.1 2Contains a requirement for system integration0.2 3Contains a requirement for system testing0.2 4Contains a requirement for analysis0.2 0.0 5Contains a hardware design, development and test0.3 6Contains a software design, development and test0.3 7Contains a hardware fabrication requirement, typically a prototype 0.2 8Contains a requirement for documentation other than the project report 0.2 9Contains a requirement for intellectual property protection0.1 0.0 Total1.8 1.5
4
Deliverable 2006 Due DateDeliverablePrimary Member Status 09/04/2006Summary of ResearchLibby John 09/27/2006PCB #1Matthew Watkins 10/01/2006Modified LON ModuleLarry Wu 10/09/2006Communications Documentation Libby John 11/15/2006PCB #2Matthew Watkins 11/21/2006Program CodeEric Robbins 12/01/2006Technical Report & User Manual Libby John Completed In Progress Not Started Behind 11/21 Program Code 10/9 Communications Documentation 12/1 Technical Report and User Manual 9/4 Summary of Research 10/1 Modified LON Module 11/15 PCB #2 9/27 PCB#1
5
Milestones Due DateMilestonesStatus 09/13/2006Primary Research Completed 09/20/2006Schematic and PCB Layout 09/27/2006Prototype Demo 10/04/2006TV Tuner Module 10/11/2006Setpoint Feedback 10/18/2006Enclosure Options 10/25//2006GUI Presentation 11/1/06 System Demonstration 11/8/062 nd PCB 11/15/06PCB Populated Completed In Progress Not Started Behind
6
Milestones 2006 Completed In Progress Not Started Behind 10/18 Enclosure Options 10/4 TV Tuner Module 10/25 GUI Presentation 9/13 Primary Research Completed 9/27 Prototype Demo 10/11 Setpoint Feed back 9/20 Schematic and PCB Layout 11/1 System Demo 11/8 2 nd PCB 11/15 PCB Populated
7
Open Actions Status What action: I 2 C programming of the tuner Who has responsibility: Eric What is status: In progress
8
Open Actions Status What action: PCB Layout Who has responsibility: Matt What is status: In progress
9
Open Actions Status What action: Setpoint Feedback Who has responsibility: Larry What is status: In progress
10
Open Actions Status What action: Researching Enclosures Who has responsibility: Libby What is status: In progress
11
Earned Value Total Number of hours worked: __384__ Estimate of manpower needed: ___1000__ Total Baseline hours: ___60__ SPI: ___.384___ CPI: __.25__ Projection: –Scope –Time –Cost
12
Technical Assistance AIR does not have a setpoint feedback from LON network
13
Technical Assistance Proposed Solutions 1.LON development kit Capture LON packets from the network 2. LCD decode Decode data that is sent from the µ c of the LON module to the on board LCD 3.7-segment display Decode 7-segment displays
14
Technical Assistance Solution Analysis 1.LON development kit High Cost ($1000) LON credit requirement 2. LCD decode No additional equipment Provides calibrated data from certified TAC devices 3.7-segment display Loses TAC’s capability to install remote temp. sensor Requires additional hardware.