Download presentation
Presentation is loading. Please wait.
Published byEzra Aron Todd Modified over 9 years ago
1
FNAL Meeting, July 2006 Basti, Bedeschi, Raffaelli, INFN-Pisa 1 ILC cryomodule mechanical work at INFN-Pisa Ongoing work Near term future Manpower summary Outlook
2
FNAL Meeting, July 2006 Basti, Bedeschi, Raffaelli, INFN-Pisa 2 Ongoing work (1) ASME characterization of components Vacuum vessel: Verifications done: Max allowable pressure. Minimum thickness required for Vessel. Nozzle thickness checks. Calculation of the opening reinforcing areas. Stresses from static loads : Reactions from supports (local stress and stress from bending moment). Local loads on Post openings. Local loads from lifting brackets.
3
FNAL Meeting, July 2006 Basti, Bedeschi, Raffaelli, INFN-Pisa 3 Ongoing work (2) ASME characterization of components The GRP, cooling pipes, cold mass: design pressure checks at the operating temperatures, verification of external loads, EXPECT COMPLETION BY SEPTEMBER 2006 Follow-up: Calculation maintenance. Critical revision of design: Many specs exceed ASME Worth considering reducing some requirements
4
FNAL Meeting, July 2006 Basti, Bedeschi, Raffaelli, INFN-Pisa 4 Ongoing work (3) FEM analyses: Simple FEM of CRY-4 module using beam elements. Model used to study: vacuum vessel support positions, POST positions, normal modes of vibrations.
5
FNAL Meeting, July 2006 Basti, Bedeschi, Raffaelli, INFN-Pisa 5 Vacuum Vessel HeGRP Cavities POST Vacuum Vessel supports Quadrupole Y Z
6
FNAL Meeting, July 2006 Basti, Bedeschi, Raffaelli, INFN-Pisa 6 Ongoing work (4) Optimization of vacuum vessel supports: Prefer two support isostatic solution max GRP deflection = 0.19 mm Optimization of POST position: Find solution consistent with analytical model developed at INFN-Mi.
7
FNAL Meeting, July 2006 Basti, Bedeschi, Raffaelli, INFN-Pisa 7 Example of VV support study Displacements with A/2=3500 0.2 mm Y X
8
FNAL Meeting, July 2006 Basti, Bedeschi, Raffaelli, INFN-Pisa 8 Ongoing work (5) : Normal modes of vibration in chosen configuration: two supports (A/2=3500), POST = 4300 mm We considered two limits cases to model the POST connection between the vacuum vessel and the GRP: CASE 1) all degrees of freedom fixed between the vacuum vessel nodes and GRP nodes (in the Post positions). CASE 2) rotation along z axis (perpendicular to vessel axis) free between the vacuum vessel nodes and GRP nodes (in the Post position).
9
FNAL Meeting, July 2006 Basti, Bedeschi, Raffaelli, INFN-Pisa 9 Example of FEM results Normal Mode -1 (Y-X plane) two support points Case-1 Y X 34.9 Hz
10
FNAL Meeting, July 2006 Basti, Bedeschi, Raffaelli, INFN-Pisa 10 Normal Frequencies POST = 4300 Two supports A/2 = 3500 CASE-1CASE-2 1 34.9 Hz (Y-X plane)26.1 Hz (Y-X plane) 2 57.2 Hz (X-Z plane)30.6 Hz (Y- X plane) 3 61.4 Hz (Y-X plane)46.4 Hz (Y-X plane) 4 61.8 Hz (X-Z plane)57.2 Hz (X-Z plane) 5 65.0 Hz (Y-X plane)60.7 Hz (Y-X plane) 6 71.6 Hz (Y-X plane)61.8 Hz (X-Z plane) 7 86.6 Hz (X-Z plane)70.1 Hz (Y-X plane) 8 92.2 Hz (X-Z plane)86.6 Hz (X-Z plane) 9 92.5 Hz (Y-X plane)91.0 Hz (Y-X plane) 10 98.0 Hz (X-Z plane)92.2 Hz (X-Z plane)
11
FNAL Meeting, July 2006 Basti, Bedeschi, Raffaelli, INFN-Pisa 11 Near term future work (1) Mechanical model (room temperature) Vacuum vessel + POST + simplified cold mass Goals: Experimental verification of FEM models predictions Engineering cable and pipe routing/feed-through Engineering assembly and associated fixtures Model can be instrumented/inspected Available stress analysis equipment in INFN-Pisa Model can be easily modified to test project modifications Should be accessible to all ILC collaborators
12
FNAL Meeting, July 2006 Basti, Bedeschi, Raffaelli, INFN-Pisa 12 Near term future work (2) Specific cryomodule R&D: Posts. Vacuum flanges between cavities: Decrease space between cavities. Study “Ultraflex ” low insertion force o-ring. Room/LN temperature tests in Pisa – LHe in Milan
13
FNAL Meeting, July 2006 Basti, Bedeschi, Raffaelli, INFN-Pisa 13 Near term future work (3) Participation to cryomodule fabrication at Zanon (with INFN- Milan) Current and future productions Participation to cryomodule engineering drawings: Possible parts of major Pisa involvement: Posts. Includes coupling to the GRP Vacuum vessel. Thermal shields with associated pipes. Could include some pipe size calculations Parts of the GRP to be defined. New cavity flange if R&D successful.
14
FNAL Meeting, July 2006 Basti, Bedeschi, Raffaelli, INFN-Pisa 14 Manpower A. Basti: project engineer F. Raffaelli: consultant G. Martinelli, S. Linari, A. Sukhanova: engineers S. Bianucci: draftsman Work in progress to procure additional engineering support.
15
FNAL Meeting, July 2006 Basti, Bedeschi, Raffaelli, INFN-Pisa 15 Outlook Plan strong participation to cryomodule engineering, design and industrial production. Expect major INFN funding for a type 4 cryomodule in 2007 to be produced in Italy. Expect INFN involvement in cryomodule production to grow in following years.
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.