1 Slide 1 Marcel Demarteau Brenna Flaugher Proposal for project space utilization at Sidet

2 Slide 2 Projects at SiDet and their Requests p There are currently 6 silicon projects planned at SiDet: BTeV pixels, BTeV strips, CMS pixels, CMS strips, DØ-2b, CDF-2b p Each project presented their request at a liaison meeting. Presentations can be found at http://sidet.fnal.gov/liaison/http://sidet.fnal.gov/liaison/ p Based on those requests, a possible use of the Lab space for the various projects is presented in the following slides. p Office space for the projects is also addressed

3 Slide 3 Lab D p Boundary conditions:  Accommodate CMS, CDF and DØ 2b production  Minimal perturbation with regard to CMM equipment  Projects needs not far developed yet p Proposal  CMS strip production takes place in current wirebonding area  DØ 2b production takes place in North area »Can retain all CMM’s in that area for the time being  CDF production takes place on East wall »Can retain all CMM’s in that area too for the time being  Wirebonding relocated to semi-cleanroom p Disposition of CMM’s can be deferred to a later date when 2b plans of groups are firmed up

4 Slide 4 Lab D Proposed Layout DØ CMS CDF Wirebonding

5 Slide 5 Lab D Wirebonding Proposed Layout p Wirebonding room more centrally located  Pass-through boxes to burn- in room, corridor (new repair location), lab D production areas p Infrastructure modifications  SiDet will refurbish ceiling  SiDet will add humidification control  SiDet will add card reader access p Retain one probestation in semi cleanroom

6 Slide 6 Lab D Semi Cleanroom p If proposal accepted to move wirebonding into semi-cleanroom, will need to move equipment  CDF »Probestations »Logs, sensors  DØ Equipment »Two laser stands »One probestation p CDF will have to find a new location for all CDF equipment p One DØ laser stand can move to the double trailer p Move all probestations to Lab A

7 Slide 7 Bubble and Double Trailer p Concentrate all repair stations in bubble (no repair work in burn-in space anymore) p CMS pixel work will relocate to the double trailer p DØ Laser stand can move to double trailer Repair Stations CMS Pixels DØ Laser Stand

8 Slide 8 Burn-in Space p Available space is ~1200 square feet (no more repair stations) p Allocation:  CDF retains 500 square feet  DØ retains 200 square feet with the understanding that they have priority and first choice once the AB-Bridge is completed  CMS is allocated 500 square feet with possibility to expand later if necessary CDF CMS DØ

9 Slide 9 Cross Connect p Each project gets one “window” office and one cubicle in the re- arranged office area p Facility will provide one direct phone line and four ethernet lines per cubicle 3 more offices

10 Slide 10 Lab C Cleanroom p CDF has agreed to move out of Lab C North section completely p DØ wishes to retain at least 10% test area p Use of Lab C areas is at the discretion of the facility until the 2b plans of both collider experiments are firmed up. DØ can retain 10% test area

11 Slide 11 Lab C South p DØ wishes to retain the 10% test area p If a 3m CMM is required for 2b assembly, a Zeiss machine will have to be removed.

12 Slide 12 Lab C North p CDF has agreed to move cooling stand to burn-in stand and vacate north clean room p CDF is considering another 1.5m B&S machine to replace one G&L dcc machine

13 Slide 13 Lab A Proposal p Move probestations into Lab A with other probestations for pixel work p Cleanroom currently focused on BTeV and CMS pixel prototyping probestations