Slide 1 Marcel Demarteau Brenna Flaugher Proposal for project space utilization at Sidet
2
Slide 2 Projects at SiDet and their Requests p There are currently 6 silicon projects planned at SiDet: BTeV pixels, BTeV strips, CMS pixels, CMS strips, DØ-2b, CDF-2b p Each project presented their request at a liaison meeting. Presentations can be found at http://sidet.fnal.gov/liaison/http://sidet.fnal.gov/liaison/ p Based on those requests, a possible use of the Lab space for the various projects is presented in the following slides. p Office space for the projects is also addressed
3
Slide 3 Lab D p Boundary conditions: Accommodate CMS, CDF and DØ 2b production Minimal perturbation with regard to CMM equipment Projects needs not far developed yet p Proposal CMS strip production takes place in current wirebonding area DØ 2b production takes place in North area »Can retain all CMM’s in that area for the time being CDF production takes place on East wall »Can retain all CMM’s in that area too for the time being Wirebonding relocated to semi-cleanroom p Disposition of CMM’s can be deferred to a later date when 2b plans of groups are firmed up
4
Slide 4 Lab D Proposed Layout DØ CMS CDF Wirebonding
5
Slide 5 Lab D Wirebonding Proposed Layout p Wirebonding room more centrally located Pass-through boxes to burn- in room, corridor (new repair location), lab D production areas p Infrastructure modifications SiDet will refurbish ceiling SiDet will add humidification control SiDet will add card reader access p Retain one probestation in semi cleanroom
6
Slide 6 Lab D Semi Cleanroom p If proposal accepted to move wirebonding into semi-cleanroom, will need to move equipment CDF »Probestations »Logs, sensors DØ Equipment »Two laser stands »One probestation p CDF will have to find a new location for all CDF equipment p One DØ laser stand can move to the double trailer p Move all probestations to Lab A
7
Slide 7 Bubble and Double Trailer p Concentrate all repair stations in bubble (no repair work in burn-in space anymore) p CMS pixel work will relocate to the double trailer p DØ Laser stand can move to double trailer Repair Stations CMS Pixels DØ Laser Stand
8
Slide 8 Burn-in Space p Available space is ~1200 square feet (no more repair stations) p Allocation: CDF retains 500 square feet DØ retains 200 square feet with the understanding that they have priority and first choice once the AB-Bridge is completed CMS is allocated 500 square feet with possibility to expand later if necessary CDF CMS DØ
9
Slide 9 Cross Connect p Each project gets one “window” office and one cubicle in the re- arranged office area p Facility will provide one direct phone line and four ethernet lines per cubicle 3 more offices
10
Slide 10 Lab C Cleanroom p CDF has agreed to move out of Lab C North section completely p DØ wishes to retain at least 10% test area p Use of Lab C areas is at the discretion of the facility until the 2b plans of both collider experiments are firmed up. DØ can retain 10% test area
11
Slide 11 Lab C South p DØ wishes to retain the 10% test area p If a 3m CMM is required for 2b assembly, a Zeiss machine will have to be removed.
12
Slide 12 Lab C North p CDF has agreed to move cooling stand to burn-in stand and vacate north clean room p CDF is considering another 1.5m B&S machine to replace one G&L dcc machine
13
Slide 13 Lab A Proposal p Move probestations into Lab A with other probestations for pixel work p Cleanroom currently focused on BTeV and CMS pixel prototyping probestations