Permit Process.

Similar presentations


Presentation on theme: "Permit Process."— Presentation transcript:

1 Permit Process

2 Permitting Actions Sequence
1. Levee District is the Permitting Authority 2. Applicant requests permit from local levee district (letter). 3. Joint site visit w/Levee District, Corps & applicant if necessary. 4. Corps provides response and recommendation to Levee District (letter). 5. Levee District approves or denies request. Copy furnished Corps.

3 Permit Information Required
1. Description of proposed work Discuss proposed activities near levee excavation, utility crossing, ramp, etc. Crossing levee or parallel levee 2. Site Map Quad map showing the location of the proposed Coordinates of work (GPS or Lat. Long.) Section, Township, Range 3. Plan Sheet Plan view of proposed work with dimensions from levee 4. Profile Sheet Cross section view of work with dimensions from levee.

4 Some levee districts use permit application forms.

5 Common Permit Actions on Red River Levees
Ramp Construction Utility Crossing Electric Powerline Crossing Pipeline construction, up-and-over & directional drilling Excavation adjacent to levees

6 Ramp Crossing Levee

7 Utility Crossing Levee

8 Pipeline Crossing Levee

9 Excavation Near Levee

10 Power Pole Installation Requirements
MININUM VERTICAL CLEARANCE VOLTS CLEARANCE FEET , FEET 15,000 – 50, FEET LANDSIDE RIVERSIDE POWERPOLE POWERPOLE LEVEE 40’ 40’

11 Directional Drill under Levee without Supporting Soil Borings
300’ minimum distance at maximum depth R/S L/S Red River Levee 25’ minimum depth Below river bed Directional Drill path

12 Directional Drill Supported with Soil Borings
300’ minimum distance for penetrating pervious sands R/S L/S Red River Levee 25’ minimum depth Below river bed Directional drill path Pervious Sands

13 Directional Drill Exit on Riverside of Levee
50 Year Bank Migration Line Levee R/S L/S Min. 10’ Red River Directional Drill Path Exit point and pipeline to be minimum 10 ft. from levee stability control line at all times.

14 Utility Crossing Detail

15

16 Ramp Crossing Detail

17 Ramp Crossing Detail

18 Borrow Pit Detail

19