1
P.15.02.07 AIRPORT SURFACE DATALINK ICAO WG-S 3 ICAO Montreal, 09/07/2013
2
ICAO WG-S 3 / Montreal 9th of July 2013 2 | This presentation is created by INDRA and is based on ©SESAR JOINT UNDERTAKING material developed within the frame of the SESAR Programme, co-financed by the EU and EUROCONTROL. The opinions expressed herein reflect the authors view only. The SESAR Joint Undertaking is not liable for the use of any of the information included herein. Reprint of information included herein with approval of publisher and with reference to source code only DISCLAIMER
3
ICAO WG-S 3 / Montreal 9th of July 2013 3 | AGENDA 01 Introduction to P15.02.07 02 Achievements 03 Project status – Closed activities 04 Project status – Ongoing activities
4
ICAO WG-S 3 / Montreal 9th of July 2013 4 | PROJECT SCOPE OVERVIEW 01 INTRODUCTION TO P.15.02.07 PROJECT MEMBERS AENA, AIRBUS, DSNA, EUROCONTROL, INDRA, NATMIG, SELEX ES, THALES P.15.02.07 Airport Surface Datalink P.15.02.07 Airport Surface Datalink T01 Overall IEEE 802.16e/aero System Analysis & Design (Lead EUROCONTROL) T01 Overall IEEE 802.16e/aero System Analysis & Design (Lead EUROCONTROL) T02 Channel models and propagation analysis (Lead NATMIG) T02 Channel models and propagation analysis (Lead NATMIG) T03 IEEE 802.16e/aero profile (Lead EUROCONTROL) T03 IEEE 802.16e/aero profile (Lead EUROCONTROL) T04 Development & Integration Analysis (Lead AENA) T04 Development & Integration Analysis (Lead AENA) T05 System Implementation (Lead SELEX ES) T05 System Implementation (Lead SELEX ES) T06 Integration and Testing (Lead THALES) T06 Integration and Testing (Lead THALES) T07 Standardization and Global Interoperability (Lead EUROCONTROL) T07 Standardization and Global Interoperability (Lead EUROCONTROL) T08 Security and Safety Analysis (Lead DSNA) T08 Security and Safety Analysis (Lead DSNA) T09 Management (Lead INDRA) T09 Management (Lead INDRA) The project aims at defining, validating and demonstrating a technical profile and architecture for a new generation of airport surface data link system
5
ICAO WG-S 3 / Montreal 9th of July 2013 5 | 02 ACHIEVEMENTS Project has substantially contributed to the joint (EUROCAE and RTCA) development of the AeroMACS profile based on mobile WiMAX standard Extensive simulations have been carried out to validate the AeroMACS profile AeroMACS ground prototypes/mock-ups testbed platforms developed. Testbed will support laboratory and airport tests within the integration and testing activities Hardware prototypes are delivered to further validate the profile and confirm the simulation results and support both laboratory and Toulouse airport tests AeroMACS system implementation document delivered, including Ground Prototypes Description and Verification Objectives and Verification Strategy that supports the Integration and Testing activities Support to standardisation bodies for AeroMACS profile standardisation: Eurocae WG-82, RTCA SC-223, ICAO WG-S and Wimax Forum (AWG) Ongoing coordination with US/FAA ACHIEVEMENTS
6
ICAO WG-S 3 / Montreal 9th of July 2013 6 | 03 PROJECTS TATUS – CLOSED ACTIVITIES T01 Overall IEEE 802.16e/aero System Analysis & Design Status: Completed 23/11/2010 T02 Channel models and propagation analysis Status: Completed 01/07/2011 T03 IEEE 802.16e/aero Profile Status: Completed 11/11/2011 T04 Deployment & Integration Analysis Status: Completed 21/09/2012 T05 System Implementation Status: Completed: 31/05/2013 PROJECT STATUS – CLOSED ACTIVITIES
7
ICAO WG-S 3 / Montreal 9th of July 2013 7 | 04 PROJECTS TATUS – ONGOING ACTIVITIES PROJECT STATUS – ONGOING ACTIVITIES WA6 Integration and Testing (I) Description: T006 Integration and lab testing - Phase 1: The main goal of this activity is the design and implementation of a testbed platform encompassing the functionalities of specified 802.16e/aero profile This task will enable the project to progress from SESAR simulated datalink and SW based scenarios towards HW datalink proofs Tests on Thales and Selex BS prototypes will be performed in Laboratory covering Phase 1 Verification Objectives described in D05.2 Deliverable T010 Integration and testing - Phase 2: Continuation of Phase 1 Integration and testing, Phase 2 will plan, execute and report the set of mandatory Verification Objectives, notably the ones with Thales prototype at Toulouse airport, and the testing of interoperability on air interface
8
ICAO WG-S 3 / Montreal 9th of July 2013 8 | 04 PROJECTS TATUS – ONGOING ACTIVITIES PROJECT STATUS – ONGOING ACTIVITIES WA6 Integration and Testing (II) Description: T011 Additional Phase 2 testing - lab and Toulouse airport: Continuation of Phase 2 testing, this task will plan, execute and report the set of optional Verification Objectives described in the Verification Strategy The task covers both testing in laboratories and in real environment (Toulouse airport) The consolidated report will serve as input to refining the AeroMACS profile produced under WA3 T012 Final prototype Availability – Selex/Thales: This task will produce the Availability Note of the manufacturer's prototypes, revisited once the testings are completed.
9
ICAO WG-S 3 / Montreal 9th of July 2013 9 | 04 PROJECTS TATUS – ONGOING ACTIVITIES PROJECT STATUS – ONGOING ACTIVITIES WA6 Integration and Testing (III) Progress: Verification Plan (VP) for Phase 1 testing: first draft issued for P.15.02.07 internal review Verification Report (VR) Phase 1 : internal draft Thales and Selex Laboratory Tests: ongoing Toulouse Airport test: anticipated with DSNA (even if now planned in 2014), first site survey already occurred in 2012, new meeting for details confirmation under preparation Airport testing planning: 9.16 Airport testbed integrated and ready: 26/07/2013 15.2.7 Airport testbed integrated and ready: 18/03/2014
10
ICAO WG-S 3 / Montreal 9th of July 2013 10 | 04 PROJECTS TATUS – ONGOING ACTIVITIES PROJECT STATUS – ONGOING ACTIVITIES WA6 Integration and Testing (IV) Planning:
11
ICAO WG-S 3 / Montreal 9th of July 2013 11 | 04 PROJECTS TATUS – ONGOING ACTIVITIES PROJECT STATUS – ONGOING ACTIVITIES T07 Standardization and Global Interoperability Planning: Actual forecast date: 04/02/2014 Progress: Open Consultation Process for the AeroMACS MOPS just completed – publication is expected by end of year Draft MASPS available - completion planned by end of year WMF documents (AeroMACS PICS and CRSLv1.2) under finalisation for submission to WMF available Draft SARPS available Support to EUROCAE WG82, RTCA SC223, ICAO ACP WGS, Wimax Forum AWG
12
ICAO WG-S 3 / Montreal 9th of July 2013 12 | 04 PROJECTS TATUS – ONGOING ACTIVITIES PROJECT STATUS – ONGOING ACTIVITIES T08 Security and Safety Analysis Planning: Actual forecast date: 04/02/2014 Progress: AeroMACS Safety and Performance Analysis: internal draft AeroMACS Security Analysis: internal draft for review
13
ICAO WG-S 3 / Montreal 9th of July 2013 13 | THANK YOU FOR YOUR ATTENTION ANY QUESTIONS?
14
15.2.7 Project Manager: Hyung Woo Kim SD ATM & Airports SESAR Programme hkim@indra.es San Fernando Business Park – Kenia bldg. Avenida de Castilla 2, 28830. San Fernando de Henares, Madrid. España T +34 91 627 37 71 www.indracompany.com