LINK2000+ Status Søren Dissing
ICAO ACP / WG-M, Bruxelles, 4 June 2009
2
Overview History Status Standards Baseline Regulation
Eurocontrol Specification Community Specification ESSIP This will provide a planning tool for stakeholder implementation as well as a mechanism for stakeholder implementation progress to be monitored
3
LINK 2000+ Objectives Implementing En-route CPDLC over ATN/VDL2
Baseline ICAO standards Forward compatible with new services/technology Programme Objectives Above FL285 ACL – ATC Clearances ACM – ATC Microphone Check ACM – ATC Communications Management This shows the scope of the LINK Programme and the SES Datalink Implementing Rule (IR). MAAS UAC has been operational since 2003 Key IR Dates LINK Region in yellow by Feb 2013 Rest of EU by Feb 2015 New Aicraft by Jan 2011 Retrofit by Jan 2015
4
3 - Step Approach to Implementation
Pioneers Objective: 100+ aircraft equipped/ MAAS UAC Achieved: 400+ aircraft recruited/ MAAS UAC operational Incentives Objective: accelerate Airborne equipage to gain early benefits, return on investment EU agrees in principle Mandatory Implementation (SES IR) For Operators and ANSPs Objective: more than 75% of flights in LINK airspace by 2014 Pioneers Incentives Mandate 1 2 3
5
Pioneer Success Lufthansa Lufthansa CityLine
15 Airlines > 400 Airframes (many more are VDL M2) Rockwell, Honeywell and Airbus all Certified
6
2 - Step Incentive Scheme
equipage Forward fit Retro fit Mandatory Carriage 75% Incentives b – Route Charge scheme Earlier Benefits Better flight profiles Less misunderstandings Higher Productivity Less delay Pioneers 25% a – Public funds - first 25% Combined Scheme ANSPs 2008/9 2011 2013 2015
7
Mandatory Implementation
Always part of the LINK implementation strategy Single European Sky provided the mechanism - and it also applies to the ANSPs!
8
It Took 3 Years 5 Months May 2005 EC gave EUROCONTROL a Mandate to
Develop an Implementing Rule (IR) for Datalink Services Adoption DELIVERY Initial Plan Feb 06 RA Consult Regulatory Approach May 06 RA Delivery Draft IR RU Update Q3 07 IR Delivery SSC LAW Q2 07 IR Consult
9
Done!
10
ANSPs LINK/Core Region
IR Key Dates Aircraft Forward Fit New aircraft conform ANSPs LINK/Core Region Aircraft Retrofit Fit ANSPs Whole of EU 1st Jan 2011 7th Feb 2013 5th Feb 2015 2009 2010 2011 2012 2013 2014 2015 2016
11
Datalink IR Dates LINK Region Feb 2013 All of EU Feb 2015 Forward Fit
Jan 2011 Retrofit Old a/c reg before Dec 97 Dec 2017 New FANS a/c Jan 2014 Transport-type State a/c Jan 2014 (if equiping)
12
Eurocontrol Specification
Standards Baseline Doc 9705 ed. 2 with PDRs Link Baseline 1.2/1.4 Eurocontrol Specification Community Specification