© ITC-AICE, 2007 E! 3792 ENIWEP TRIBOSTAND Kick-off meeting Castellón, 21 st January 2008
2
E!3792 – ENIWEP TRIBOSTAND Kick-off meeting Castellón, 21st January 2008 |© ITC-AICE, 2007 Meeting agenda 8:30 - 9:00Registration 9:00 - 9:15Welcome and introductory remarks, agenda presentation 9:15 - 10:00Project overview. Presentation of the project program, review of technical objectives, activities, Gantt 10:00 - 11:00Organisation and communication within the consortium and work groups, review of management structure 11:00 - 11:15Coffee break 11:15 - 12:00Current situation of the administrative and technical work carried out 12:00 - 12:30Workpackages timetable, spacially for the first year. Meetings schedule 12:30 - 13:30General conclusions
3
E!3792 – ENIWEP TRIBOSTAND Kick-off meeting Castellón, 21st January 2008 |© ITC-AICE, 2007 Project overview PROBLEM: Same property measured in different laboratories with different means gives: DIFFERENT RESULTS OBJECTIVES: To yield a group of common test protocols, which will allow for obtaining the same results, under the same conditions, at any laboratory that has the required means. Once these protocols have been obtained and their validity and traceability verified, a tribological analysis and test service will be established and will enable companies from different sectors to solve their problems at any member centre of the service.
4
E!3792 – ENIWEP TRIBOSTAND Kick-off meeting Castellón, 21st January 2008 |© ITC-AICE, 2007 Partners Instituto de Tecnología Cerámica (ITC-AICE) (Spain) Tekniker (Spain) Asociación de las Industrias Navarras (AIN) (Spain) Fritta S.A. (Spain) Falex (Belgium) Katholieke Universiteit Leuven (Belgium) Centrale Recherche SA - Ecole Centrale Paris (CRSA-ECP) (France) Tribotechnic (France) Departamento de Ingeniería Mecánica - Universidad de Coimbra (Portugal) Instituto Pedro Nunes - Associaçao para a inovaçao e desenvolvimento en ciência e tecnologia (Portugal) Laboratorie Dubois, S.A (*) (Switzerland) National Physical Laboratory (**) (England)
5
E!3792 – ENIWEP TRIBOSTAND Kick-off meeting Castellón, 21st January 2008 |© ITC-AICE, 2007 Project diagram 1 Bibliographic search 2 Selection of tests 5 Start-up of service 6.1 Submission of protocols 6.2 Dissemination of results 7 Project management 4 Study of the tests 3 Selection of equipment and samples
6
E!3792 – ENIWEP TRIBOSTAND Kick-off meeting Castellón, 21st January 2008 |© ITC-AICE, 2007 Activity 1. Bibliographic search Compilation of standards and regulations related to the methods under study
7
E!3792 – ENIWEP TRIBOSTAND Kick-off meeting Castellón, 21st January 2008 |© ITC-AICE, 2007 Activity 2. Selection of tests Each partner to supply a list of its own non-standardised tests to be included in the project. Result of activities 1 and 2: Join list of tests to be studied
8
E!3792 – ENIWEP TRIBOSTAND Kick-off meeting Castellón, 21st January 2008 |© ITC-AICE, 2007 Activity 3. Selection of equipment and samples for performance of the tests Task 3.1List of equipment available in each Research Centre Task 3.2Round-robin intercomparison of standard materials to validate the results of all the available equipment Task 3.3Selection of samples of different types and properties to be tested by the protocols listed in activity 2 (bulk materials, coatings, different roughness, different properties, etc.)
9
E!3792 – ENIWEP TRIBOSTAND Kick-off meeting Castellón, 21st January 2008 |© ITC-AICE, 2007 Activities 4. Study of the tests (one per test) Task 4.1Study of the different variables affecting the results. Selection of the best values of these variables by the responsible of the test Task 4.2Testing of samples with the conditions established in 4.1 Task 4.3Round-robin intercomparison among the centres which have the technique available Task 4.4Results analysis and uncertainty calculation where applicable Task 4.5Drawing up of a common definitive protocol
10
E!3792 – ENIWEP TRIBOSTAND Kick-off meeting Castellón, 21st January 2008 |© ITC-AICE, 2007 Activity 5. Start-up of a test service Launching of a external tribological test service Creation of a Website through which the requests for tests by clients can be channelled. Creation of a catalogue detailing the tests capabilities of each member of the consortium
11
E!3792 – ENIWEP TRIBOSTAND Kick-off meeting Castellón, 21st January 2008 |© ITC-AICE, 2007 Activity 6. Dissemination of results Task 6.1Submission of protocols to standardisation committees: The relevant protocols of the tests included in the service will be submitted to the corresponding standardization committees
12
E!3792 – ENIWEP TRIBOSTAND Kick-off meeting Castellón, 21st January 2008 |© ITC-AICE, 2007 Activity 6. Dissemination of results Task 6.2Dissemination of the project results: The results obtained will be disseminated by different channels (scientific publications, conferences, fairs, ENIWEP website, etc.)
13
E!3792 – ENIWEP TRIBOSTAND Kick-off meeting Castellón, 21st January 2008 |© ITC-AICE, 2007 Activity 7. Project management Facilitate administrative tasks and notifying the consortium of due dates Preparation of technical and cost justification reports Acting as a permanent contact point for all partners and maintaining a high level of communication in the consortium Coordination of meetings Operation of a project website with a restricted area for the consortium members. At the end of the project, it will be the tool for the tests service
14
E!3792 – ENIWEP TRIBOSTAND Kick-off meeting Castellón, 21st January 2008 |© ITC-AICE, 2007 Gantt diagram TASK QUARTERS OF THE YEAR First yearSecond yearThird yearFourth year 1234123412341234 1 2H1 3.1H1 3.2H2H3 4.1 4.2 4.3 4.4 4.5H4 5H5 6.1 6.2 7 H1: Tests and equipment list H2: Standards for verification of equipment. H3: Testing materials H4: Test protocols H5: Tribological analysis and test service
15
E!3792 – ENIWEP TRIBOSTAND Kick-off meeting Castellón, 21st January 2008 |© ITC-AICE, 2007 Organization and communication among the consortium
16
E!3792 – ENIWEP TRIBOSTAND Kick-off meeting Castellón, 21st January 2008 |© ITC-AICE, 2007 Activity 4 Organization Test 1 sub-consortium Test 2 sub-consortium Test 3 sub-consortium Test “n” sub-consortium Coordinator of test 1 (tasks 4.1 to 4.5) Coordinator of test 2 (tasks 4.1 to 4.5) Coordinator of test 3 (tasks 4.1 to 4.5) Coordinator of test “n” (tasks n.1 to n.5) Coordinator of activity 4
17
E!3792 – ENIWEP TRIBOSTAND Kick-off meeting Castellón, 21st January 2008 |© ITC-AICE, 2007 Activities distribution suggestion 1 Bibliographic search Instituto Pedro Nunes 2 Selection of tests Department of Metallurgy and Materials Engineering –KUL 3 Selection of equipment and samples Asociación de las Industrias Navarras (AIN) 4 Study of the tests Facultade de Ciencias e Tecnologia – UC
18
E!3792 – ENIWEP TRIBOSTAND Kick-off meeting Castellón, 21st January 2008 |© ITC-AICE, 2007 Activities distribution suggestion 5 Start-up of a tests service (website launche) ITC 6.1 Submission of protocols to standardisation comitees TEKNIKER 6.2 Dissemination of the project results Central Recherche S.A. – ACP 7 Project management ITC
19
E!3792 – ENIWEP TRIBOSTAND Kick-off meeting Castellón, 21st January 2008 |© ITC-AICE, 2007 Next meeting Coinciding with next ENIWEP general meeting?