Presentation is loading. Please wait.

Presentation is loading. Please wait.

OSBORNE HOLLOW CREEK ROAD PROTECTION PROJECT. Gravel-Cobble Bed Stream – Rural, Pool-Riffle-Pool, Stream Slope 2-3% Goals: Halt bank erosion to protect.

Similar presentations


Presentation on theme: "OSBORNE HOLLOW CREEK ROAD PROTECTION PROJECT. Gravel-Cobble Bed Stream – Rural, Pool-Riffle-Pool, Stream Slope 2-3% Goals: Halt bank erosion to protect."— Presentation transcript:

1 OSBORNE HOLLOW CREEK ROAD PROTECTION PROJECT

2 Gravel-Cobble Bed Stream – Rural, Pool-Riffle-Pool, Stream Slope 2-3% Goals: Halt bank erosion to protect NY State Highway 7, & Widen Road Shoulder Solution: Install Deeply-Keyed (weighted toe) Vegetated Riprap

3 Let’s think this thing through!!!! OSBORNE HOLLOW CR. – DEC 12, 2006

4 THE FIRST PLAN

5 Double Boil-UP Pools- Osborne Hollow Cr.- Near Binghamton, NY Planform View Flow Stable Riprap with veg-1 ton/ft Riprap with veg-3 tons/ft Stable Riprap with veg-3 tons/ft Riprap with veg-1 ton/ft Dig Boil-Up Pool, 35 ft in diameter, 4 ft deep Dig Boil-Up Pool, 30 ft in diameter, 4 ft deep Riprap with veg-2 tons/ft Riprap with veg-1 ton/ft

6 THE LANDOWNER BOO BOO

7 Osborne Hollow Cr.- Near Binghamton, NY Planform View Flow Landowner channel Stable Severe erosion Some erosion Landowner levee Landowner dredged area

8 Looking US at landowner dug channel in stream. OSBORNE HOLLOW CR. – JUNE 24, 2007 - PIX BY DERRICK

9 Looking DS at landowner cutoff channel & levee OSBORNE HOLLOW CR. – JUNE 24, 2007 - PIX BY DERRICK

10 Looking US from within landowner cutoff channel. Note steep slope of bottom of dug trench. OSBORNE HOLLOW CR. – JUNE 24, 2007 - PIX BY DERRICK

11 Landowner cutoff channel is aimed at his house, which is 35 ft from top bank!! OSBORNE HOLLOW CR. – JUNE 24, 2007 - PIX BY DERRICK

12 Looking US. Headcuts migrating US thru the landowner cutoff channel. OSBORNE HOLLOW CR. – DEC 20, 2007 - PIX BY DERRICK

13 During our in-field meeting with the landowner, he felt his channel aimed at his house will work, so we decided to abandon our first plan (double- boil-up pool) & go with a pure road protection scheme. We will not touch the landowner’s work, in fact we photo-documented the site pre- & post project construction

14 THE SECOND PLAN VEGETATED KEYS & RIPRAP

15 Osborne Hollow Cr.- Near Binghamton, NY Planform View Flow Landowner channel Stable Severe erosion Some erosion Landowner levee Landowner dredged area State Highway 7 Vegetated keys & riprap

16 Looking DS. White painted line will be toe trench for riprap OSBORNE HOLLOW CR. – JUNE 24, 2007 - PIX BY DERRICK

17 Gravel-Cobble Bed Stream–Install Soil- Choked Vegetated (Single-Row Bent Willow Pole) Weighted-Toe Full-Bank Height Riprap Pre-project profile view. Looking upstream State Hwy 7 Varies between 6 & 13 ft

18 Let the actual construction begin !!!! June 25, 2007

19 Looking DS at toe-down trench for riprap OSBORNE HOLLOW CR. – JUNE 25, 2007 - PIX BY DERRICK

20 Looking US at toe-down trench for riprap OSBORNE HOLLOW CR. – JUNE 25, 2007 - PIX BY DERRICK

21 Gravel-Cobble Bed Stream–Install Soil- Choked Vegetated (Single-Row Bent Willow Pole) Weighted-Toe Full-Bank Height Riprap Weighted toe trench dug 5 ft down & 4 ft wide State Hwy 7

22 Gravel-Cobble Bed Stream–Install Soil- Choked Vegetated (Single-Row Bent Willow Pole) Weighted-Toe Full-Bank Height Riprap Bedload cobble-gravel used as fill material to provide a 2 on 1 slope State Hwy 7

23 700 STREAMCO WILLOW PLANTS WERE HARVESTED BY NYS-DOT PERSONNEL FROM THE NRCS PLANT MATERIAL CENTER, BIG FLATS, NY. AVERAGE PLANT SIZE WAS 12-15 FT LONG & 1- 1.5 INCH BUTT DIAMETER

24 Gravel-Cobble Bed Stream–Install Soil- Choked Vegetated (Single-Row Bent Willow Pole) Weighted-Toe Full-Bank Height Riprap 12-16 ft long Streamco Willow placed @ a density of 5 stems/ft State Hwy 7

25 Looking US. Placing streamco willow in toe-down trench OSBORNE HOLLOW CR. – JUNE 26, 2007 - PIX BY DERRICK

26 Looking US. Installing a thick layer of willow & toe stone. OSBORNE HOLLOW CR. – JUNE 26, 2007 - PIX BY DERRICK

27 Gravel-Cobble Bed Stream–Install Soil- Choked Vegetated (Single-Row Bent Willow Pole) Weighted-Toe Full-Bank Height Riprap Trench & bank toe area filled with DOT graded “Heavy” riprap State Hwy 7

28 Looking US. Filling toe-down trench with DOT heavy stone OSBORNE HOLLOW CR. – JUNE 26, 2007 - PIX BY DERRICK

29 Looking DS. Willows in place, setting riprap toe stone OSBORNE HOLLOW CR. – JUNE 26, 2007 - PIX BY DERRICK

30 Looking US. Weighted-toe trench almost filled with stone. OSBORNE HOLLOW CR. – JUNE 26, 2007 - PIX BY DERRICK

31 THE “SINGLE ROW” BENT WILLOW POLE METHOD Willow placed at a density of 5 stems/ft.

32 Gravel-Cobble Bed Stream–Install Soil- Choked Vegetated (Single-Row Bent Willow Pole) Weighted-Toe Full-Bank Height Riprap Log Using an available log held in the bucket of the trackhoe, willows are pulled streamward State Hwy 7

33 A long 2 by 4 was used to bend willows away from the bank. OSBORNE HOLLOW CR. – JUNE 26, 2007 - PIX BY DERRICK

34 Stone was then placed from above onto the upper section of the bank. OSBORNE HOLLOW CR. – JUNE 26, 2007 - PIX BY DERRICK

35 Gravel-Cobble Bed Stream–Install Soil- Choked Vegetated (Single-Row Bent Willow Pole) Weighted-Toe Full-Bank Height Riprap Using the front end loader, riprap is placed on mid & upper bank areas {landward of the willows} State Hwy 7

36 Placing stone on mid & upper sections of bank. OSBORNE HOLLOW CR. – JUNE 26, 2007 - PIX BY DERRICK

37 Gravel-Cobble Bed Stream–Install Soil- Choked Vegetated (Single-Row Bent Willow Pole) Weighted-Toe Full-Bank Height Riprap Bedload cobble- gravel is used to choke all riprap. This resulted in a 2 to 3 ft wider road shoulder. State Hwy 7

38 Stone is then “choked” with bed material from stream, then compacted. OSBORNE HOLLOW CR. – JUNE 26, 2007 - PIX BY DERRICK

39 Looking US. Stone & choke material results in a wider highway shoulder. OSBORNE HOLLOW CR. – JUNE 26, 2007 - PIX BY DERRICK

40 Gravel-Cobble Bed Stream–Install Soil- Choked Vegetated (Single-Row Bent Willow Pole) Weighted-Toe Full-Bank Height Riprap Seed or hydroseed all disturbed areas State Hwy 7

41 THE US KEY IS A STONE KEY WITH DEEPLY PLANTED VEGETATION

42 Looking US. Placing DOT graded “heavy” stone in US key OSBORNE HOLLOW CR. – JUNE 26, 2007 - PIX BY DERRICK

43 Looking DS at US key. Note angle of key to stream. OSBORNE HOLLOW CR. – JUNE 27, 2007 - PIX BY DERRICK

44 Looking DS at US key. OSBORNE HOLLOW CR. – JUNE 27, 2007 - PIX BY DERRICK

45 Looking DS at US key. Key construction is complete. OSBORNE HOLLOW CR. – JUNE 27, 2007 - PIX BY DERRICK

46 WHAT HAPPENS OVER TIME ??? 5 MONTHS LATER

47 Looking US at willow & stone protection by the road. OSBORNE HOLLOW CR. – DEC 20, 2007 - PIX BY DERRICK

48 Looking US at willow & stone protection. OSBORNE HOLLOW CR. – DEC 20, 2007 - PIX BY DERRICK

49 Looking US at stream & road. OSBORNE HOLLOW CR. – DEC 20, 2007 - PIX BY DERRICK

50 CLEOPHUS SPEED ELVIS DERRICK, AT REST Questions?Questions?


Download ppt "OSBORNE HOLLOW CREEK ROAD PROTECTION PROJECT. Gravel-Cobble Bed Stream – Rural, Pool-Riffle-Pool, Stream Slope 2-3% Goals: Halt bank erosion to protect."

Similar presentations


Ads by Google