1 Hans Koolen NMOC/CFMU Network Operations Services
A-CDM – Integration of Airport into the Network Implementation Steps & Status Edition June 2012 Hans Koolen NMOC/CFMU Network Operations Services

2 Purpose of presentation
Introduction Purpose of presentation To describe which implementation steps are applicable for Integrating a CDM airport into the Network via DPI and FUM messages. To provide the latest available planning information Target Audience Management Airport CDM Project Team All others who would like to have a global overview of the planning

3 AGENDA Introduction DPI/FUM Implementation Steps Last available planning info

4 Airport CDM Integration Plan
A-CDM is implemented in phases It is a Cooperation between: At the airport: AO, handler, Airport, ATC/TWR EUROCONTROL: Airport CDM-team, NMOC/CFMU The process requires: Clear roles & responsibilities of EUROCONTROL Identification of clear & transparent criteria The process has been defined together by APT and NMOC/CFMU

5 DPI/FUM Implementation Procedure
Decision Gap Analysis Completeness Assessment Elements (1 - 5) CBA DPI Message Go No Decision NMOC/CFMU Operational Evaluation Not Ready Advice Airport Interest in Airport CDM Information More Analysis Operational DPI Transmission to NMOC/CFMU Phase DPI Operational Evaluation Phase DPI Element * * The technical support for the DPI element can be implemented e ither in parallel with elements 1 5 or after their completion Local Airport CDM Operating Status CDM Airport

6 Five A-CDM Implementation Phases
Information Phase NMOC/CFMU provides general info about DPI/FUM and NMOC/CFMU’s role in the A-CDM project Analysis Phase NMOC/CFMU does not actively participate but is ready to answer to questions if necessary. Implementation Phase NMOC/CFMU provides DPI implementation details NMOC/CFMU and Airport CDM Project team draft DPI-ICD Airport CDM platform software is updated with DPI/FUM processing NMOC/CFMU and Airport CDM Project team agree planning of the DPI Operational Evaluation Phase DPI Operational Evaluation Phase Before start: Evaluate CDM Completeness Criteria Evaluate DPI messages Put DPIs into operations

7 CDM Implementation Phases (1/3)
Information Phase Information Collection Airport is interested in A-CDM Decision to analyse the options Gap Analysis CBA Decision to Implement A-CDM Analysis Phase Mainly Airport CDM Activities – NMOC/CFMU provides information

8 CDM Implementation Phases (2/3)
Decision to implement Airport CDM Implement CDM Elements 1 to 5 Implement FUM (local) CDM in Operations Implement DPI CDM Completeness Assessment Not yet Ready Ready Decision to start DPI transmission to NMOC/CFMU Implementation Phase Activity managed by Airport CDM with support from NMOC/CFMU

9 DPI Implementation Steps
First Information Exchange Development of the DPI-ICD FUM used by A-CDM Validation of Local Data accuracy and Timelines DPI Operational Evaluation Communication and Message Syntax Evaluation of Live Data ATFCM Impact Assessment Operational Trial DPIs Fully operational

10 DPI Implementation Steps
First Information Exchange Development of DPI-ICD Validation of Local Data Accuracy and Timelines FUM used by A-CDM DPI Operational Evaluation DPIs Operational at NMOC/CFMU

11 First Information Exchange
Purpose NMOC/CFMU provides Global Overview of DPI/FUM messages. Airport provides overview of the A-CDM project. First contact between the A-CDM project team and the NMOC/CFMU team. When After the A-CDM project has been approved The A-CDM project wants to include DPI/FUM into the project planning Duration 1 day meeting Required participants A-CDM project team (preferably a representative of each stakeholder such as Airport, ATC-TWR ATC-FMP, AO,…) NMOC/CFMU staff

12 Development of the DPI-ICD
Purpose NMOC/CFMU provides DPI messages implementation details. NMOC/CFMU provides detailed presentation on the DPI Operational Evaluation process. NMOC/CFMU and A-CDM project team start drafting the DPI-ICD. When When the A-CDM project is approaching the implementation phase. Before the A-CDM software requirements for the DPI messages are written. Duration Start with a 1-2 day meeting Finalisation of the DPI-ICD is estimated to take 1-2 months Required participants A-CDM project team, especially TWR OPS staff, FMP representative, Software Requirements Specialist. NMOC/CFMU staff

13 Required participants
FUM used by A-CDM Purpose NMOC/CFMU will provide FUM on request. The A-CDM team can send request to NMOC/CFMU. When After the A-CDM info sharing platform is ready to receive the FUM. Duration Provision of FUM can be arranged on short notice. Required participants A-CDM project Mgr. ODSG representative of ANSP concerned.

14 Validation of Local Data Accuracy and Timelines
Purpose To assess accuracy of CDM Data Provision To prevent unnecessary long DPI Operational Evaluation See “CDM Completeness Criteria” in Airport CDM Manual. When After A-CDM has been put into operations. Before DPI Operational Evaluation is started. Duration Estimated duration: 1 week – 1 month. Required participants A-CDM project team to asses the Criteria. EUROCONTROL CND Airport team to discuss the Criteria.

15 CDM Completeness Criteria (1/2)
Implement 5 Airport CDM Concept Elements Airport CDM Information Sharing Airport CDM Turn-around process – Miles Stones Approach Variable Taxi-Time (VTT) Calculation Collaborative Pre-Departure Sequence (TSAT) CDM in Adverse conditions Inclusion of the following major events in the CDM process Verification of the flight plan with the airport slot Establishment of the TOBT Issue of the TSAT Actual Off-Block Adherence to Operational Procedures CDM procedures documented in AIP and Airport Operating Instructions See Airport CDM Implementation Manual – Attachment 6

16 CDM Completeness Criteria (2/2)
Accuracy & Coverage of the provided data DPIs received for at least 97% of the flights Accuracy of TTOT based upon TOBT <= 12min Accuracy of TTOT based upon TSAT <= 10min Accuracy of TTOT based upon AOBT <= 5min The accuracy of the provided TOTs must be for 95% of the flights during normal circumstances Adherence to ATFM Slots Must be 80% or better during the last month before the CDM Completeness Assessment Agreements MoU signed by all partners at the airport DPI-ICD with NMOC/CFMU agreed LoA with NMOC/CFMU ready

17 DPI Operational Evaluation
Purpose To evaluate completeness and accuracy of DPI messages. See “DPI & FUM Implementation Roadmap” for details. When After local A-CDM has been put into operations. Before DPI messages are put into operations in NMOC/CFMU. Duration Estimated duration: 3-6 months. Required participants A-CDM project (OPS and ENG expertise). NMOC/CFMU (URB and OPS expertise).

18 CDM Implementation Phases (3/3)
Decision to start DPI transmission to NMOC/CFMU DPI Operational Evaluation Phase System & Operations Improvements DPI Operational Evaluation Not yet Ready Ready Operations Activity managed by NMOC/CFMU

19 Required participants
DPI in Operations Purpose To do the last preparations (admin). To put DPIs into operations (at NMOC/CFMU). When After successful DPI Operational Evaluation Duration Estimated duration: 1 month. Required participants A-CDM project team. NMOC/CFMU.

20 DPI Implementation Steps
First Information Exchange Development of DPI-ICD Validation of Local Data Accuracy and Timelines FUM used by A-CDM DPI Operational Evaluation DPIs Operational at NMOC/CFMU

21 DPI Operational Evaluation – Major Steps
Communication and Message Syntax Evaluation of Live Data ATFCM Impact Assessment Operational Trial Operations Post Operations Support

22 Operational Evaluation Phases
1. Communication and Message Syntax Purpose: Initial and quick verification of message syntax and connections in order to save time during testing with live data. How: transmission of copies of several DPI message types via and via AFTN. How Long: one or several s and a few messages via AFTN. Report: feedback is given by NMOC/CFMU via .

23 Operational Evaluation Phases
2. Evaluation of Live Data Purpose: Determine accuracy and consistency of Live Data and suitability for ATFCM purposes. How: transmission of DPIs for operational traffic to the ETFMS OPS evaluation (test) system. How Long: initially 1 hour, later 24hours to several days. Report: initial feedback is given by NMOC/CFMU via . Later statistics reports will be produced and discussed with the airport concerned. Note that this phase may take several months dependent on the results of the first evaluations. It is required to have at least one long duration test of 7-14 days.

24 Operational Evaluation Phases
3. ATFCM Impact Assessment Purpose: Determine the impact of the provided DPIs on the ATCFM process managed by ETFMS. How: transmission of DPIs for operational traffic to the ETFMS OPS evaluation (test) system. How Long: at least 24 hours without interruption. Report: Analysis and reports will be done via the ETFMS standard HMI (count graphs, oplog query,..).

25 Operational Evaluation Phases
4. Operational Trial Purpose: to verify the correct working of DPI/FUM messages in a fully operational environment. How: transmission of DPIs for operational traffic to the ETFMS OPS system and FUMs to the airport OPS system. How Long: several hours on 2 different days. Report: Analysis and reports will be done via the ETFMS standard HMI (count graphs, oplog query,..) and via the airport CDM system.

26 Operational Evaluation Phases
5. Operations (prepare for…) Purpose: to organise a GoNoGo meeting and take the last actions for final operations How: Organise the meeting, do last actions. How Long: takes approximately 1 week. Report: Go or NoGo decision and completed action-list.

27 Operational Evaluation Phases
6. Post Operations Support Purpose: to learn from operations and to iron-out last problems How: Closely monitor operations and ensure the availability of Operations Support. How Long: approximately 2 weeks close monitoring and after that normal operations support. Report: Incident reports and others.

28 Summary - Evolutionary Approach

29 DPI Operational Evaluation Criteria
DPI Quality Indicators DPI Completeness; i.e. DPIs for almost all flights DPI Update rate; i.e. sufficient nr of updates per flight DPI to Flight plan correlation; no DPIs for VFR/OAT flights Rejected/ignored DPIs; must be below 3% Filing time behaviour; must be as agreed in the ICD DPI performance Indicators TOT predictability; must be better than flight plan predictability

30 AGENDA Implementation Phases CDM Completeness Criteria DPI Operational Evaluation Process Summary Documentation & Contacts

31 Summary Four main A-CDM Implementation Phases
Phases 1,2 : Information & Analysis Phases (NMOC/CFMU provides info) Phase 3: (local) Implementation Phase (NMOC/CFMU provides support) Phase 4: DPI Operational Evaluation Phase (managed by NMOC/CFMU) Phase 3 ends with: CDM Completeness Assessment Determines if Airport is ready be integrated in the ATM Network Phase 4: DPI Operational Evaluation System integration testing & putting into Operations Takes 3-6 months

32 AGENDA Implementation Phases CDM Completeness Criteria DPI Operational Evaluation Process Summary Documentation & Contacts

33 Documentation (1/2) Airport CDM Manual
Contains CDM Milestones approach and a general Description of DPI messages Ref: Edition 3.1, July 2010. NM/CFMU Flight Progress Messages Document Contains DPI and FUM message syntax and semantics, general trigger events Ref: URB/USD/MSG_INTF, version 1.900, dated 01/02/2012 DPI Implementation Guide Contains a details of DPI messages, including trigger events and processing by ETFMS Ref: URB/USD/DPI_Impl_Guide, version 1.600, dated 01/02/2012

34 Documentation (2/2) FUM Implementation Guide
Contains a details of FUM messages, including accuracy info and implementation guidelines Ref: URB/USD/FUM_Impl_Guide, version 1.200, dated 01/02/2012 DPI & FUM Implementation Road Map Contains description of steps for the DPI & FUM evaluation and Evaluation Criteria Ref: URB/USD/DPI_FUM_Impl_RM, version 1.400, dated 01/02/2012 DPI ICD Contains the Airport specific DPI interface with the actual implementation of the DPI contents and trigger events

35 Contacts Contacts: Hans Koolen, tel +32 2 729 9876
Ioana Coliban, tel

36 Thank you for your attention
Hans Koolen