1
BT Young Scientists & Technology Exhibition App Risk Management
2
Project Risk Staff Turnover - (Risk: Likely / Impact: Extreme / Manage as Emergency) Would effect development of App May take time to replace – hence project delayed Prevention: Tie down staff to Project Contract Document while developing and within coding Functionality - (Risk: Unlikely / Impact: Extreme / Manage as Proactively) Too much functionality, not easy to navigate – could delay delivery date Prevention: Strip out functionality not required
3
Project Risk Security - (Risk: Unlikely / Impact: Extreme/ Manage as Systematically) Information can be taken, changed/deleted Would damage BT’s image as provider of wifi and telephone services Prevention: Talk to BT and explain more time required, before launch Poor Productivity - (Risk: Unlikely / Impact: Medium/ Manage as Proactively) All it takes is one of the team members to produce poor work Prevention: Should have a back up plan/resources/quality control/document all steps/ QA
4
Business Risk Content Suitable for Students & Corporate - (Risk: Medium / Impact: Medium / Manage as Strategically) These are 2 different target markets, difficult to produce content for both Prevention: Talk to stakeholders and incorporate them into design process. Monitor traffic once application is launched, Analytic tools. 50 th Anniversary - (Risk: Medium / Impact: Medium / Manage as Strategically) The focus of the Market Manager is through Linked In Prevention: Run a Google Ad Campaign Facebook Page for BTYS
5
Business Risk BT Resources - (Risk: Medium / Impact: Medium / Manage as Strategically) After October 2012 BT will have to commit to resources for implementing the App Prevention: Team should be involved again at this stage Year Round Exposure- (Risk: Medium / Impact: Medium / Manage as Strategically) The App needs to change throughout the year to avoid becoming stale Prevention: Team need to be involved
6
Technical Risk Scoping - (Risk: Unlikely / Impact: High / Manage as Systematically) It’s not clear if the project was scoped out correctly at the start Prevention: Establish requirements and have BT sign off on them. Testing/Debugging - (Risk: Likely / Impact: Medium / Manage as Systematically) As this is a new App and functionality is changing this area is hard to estimate Prevention: Development & QA need more time Compatibility - (Risk: Unlikely/ Impact: Medium / Manage as Proactively) All Software features e.g. graphics need to be supported by IOS4&5 and HTML5 Prevention: All features should be tested on the above platforms
7
Technical Risk Synchronizing - (Risk: Likely / Impact: Medium / Manage as Systematically) It’s not clear how BT systems will be integrated. Prevention: This will need to be tested and will be time consuming. Security During the Event - (Risk: Unlikely / Impact: High / Manage as Extreme) Can the systems handle the traffic Prevention: Needs to be fully tested over & over again. Back Up Plan - (Risk: Unlikely / Impact: High / Manage as Emergency) If App fails on the day what contingency plan is in place. Prevention: Need to discuss with BT.
8
Reputational & Political Risks App Performance - (Risk: Unlikely / Impact: Extreme / Manage as Emergency) Negative exposure for BT BT will loose its year-round exposure BT wouldn’t use Digital Skills Academy again Prevention: Test using large numbers e.g. students in Digital Hub Identify critical path tasks Negative Posts on Social Media Sites - (Risk: Likely / Impact: Medium / Manage Systematically) Effects the event and sponsors in a negative manner If not dealt with can escalate further Prevention: Embrace the negative comments Make the relevant changes
9
Documentation/Training Hand Over Document - (Risk: Unlikely / Impact: Extreme / Manage as Emergency) It’s not clear if there is one Training document required for BT staff Prevention: Document needs to be drawn up Training plan needs to be put in place
10
Nature Risks Disaster Recovery Plan - (Risk: Unlikely / Impact: Extreme / Manage as Emergency) Fire Flooding Prevention: Back up Off-Site Daily, Weekly, Monthly. Always use version control
11
Four Main Phases of BTYS Project App Preparing for the Project Deliverable – Specification/Scope stick to clients brief and sign off. Delivery Date – October 2012 with LIVE DATE Jan 2013 doesn’t make sense Budget – seems to be no budget or is there Acceptance of Project – the Team seemed to change from the brief given. Setting up the Project Project Implementation Plan – Final delivery in October 2012 Technical Solution – kept changing, yet the technologies talked about are not new. Any Contracts, Terms & Conditions – seems to be only to meet October deadline. Implementing the Project Risks Monitored – continuous monitoring Manage Contract – contract seems to finish in October, 3 months before LIVE DAY The deliverable date is October for the Team. Review Project Implementation Structured Review this is clearly something that the team cannot do Requirements Met? How do they know if the requirements are 100% met, until LIVE DAY Lesson’s Learned – if the team is not going to be around how will they be able to identify What went wrong? – Only when the App goes LIVE will you ever know 100% what went wrong
12
Conclusion BTYS Digital Skills Academy Team Main Risk is that Team is finished in Oct 2012
13
Thanking You