Presentation is loading. Please wait.

Presentation is loading. Please wait.

IENG 217 Cost Estimating for Engineers Project Estimating.

Similar presentations


Presentation on theme: "IENG 217 Cost Estimating for Engineers Project Estimating."— Presentation transcript:

1 IENG 217 Cost Estimating for Engineers Project Estimating

2 Hoover Dam U.S. Reclamation Service opened debate 1926 Six State Colorado River Act, 1928 Plans released 1931, RFP Bureau completed its estimates 3 bids, 2 disqualified Winning bid by 6 companies with bid price at $48,890,955 Winning bid $24,000 above Bureau estimates

3 Project Methods Power Law and sizing CERs Cost estimating relationships Factor

4 Power Law and Sizing In general, costs do not rise in strict proportion to size, and it is this principle that is the basis for the CER

5 Power Law and Sizing

6 Ten years ago BHPL built a 100 MW coal generation plant for $100 million. BHPL is considering a 150 MW plant of the same general design. The value of m is 0.6. The price index 10 years ago was 180 and is now 194. A substation and distribution line, separate from the design, is $23 million. Estimate the cost for the project under consideration.

7 Class Problem

8

9 CER

10 Factor Method Uses a ratio or percentage approach; useful for plant and industrial construction applications

11 Factor Method Basic Item Cost Factor

12 Adjustment for Inflation

13 Example; Plant Project

14

15 4.1 1.7 1.1

16 Example; Plant Project

17 Other Project Methods Expected Value Range Percentile Simulation

18 Expected Value Suppose we have the following cash flow diagram. NPW = -10,000 + A(P/A, 15, 5) 1 2 3 4 5 A A A A A 10,000 MARR = 15%

19 Expected Value Now suppose that the annual return A is a random variable governed by the discrete distribution: A p p p          200016 3 23 4 16,/,/,/

20 Expected Value A p p p          200016 3 23 4 16,/,/,/ For A = 2,000, we have NPW = -10,000 + 2,000(P/A, 15, 5) = -3,296

21 Expected Value A p p p          200016 3 23 4 16,/,/,/ For A = 3,000, we have NPW = -10,000 + 3,000(P/A, 15, 5) = 56

22 Expected Value A p p p          200016 3 23 4 16,/,/,/ For A = 4,000, we have NPW = -10,000 + 4,000(P/A, 15, 5) = 3,409

23 Expected Value There is a one-for-one mapping for each value of A, a random variable, to each value of NPW, also a random variable. A 2,000 3,000 4,000 p(A) 1/6 2/3 1/6 NPW -3,296 56 3,409 p( NPW ) 1/6 2/3 1/6

24 Expected Value E[Return] = (1/6)-3,296 + (2/3)56 + (1/6)3,409 = $56 A 2,000 3,000 4,000 p(A) 1/6 2/3 1/6 NPW -3,296 56 3,409 p( NPW ) 1/6 2/3 1/6


Download ppt "IENG 217 Cost Estimating for Engineers Project Estimating."

Similar presentations


Ads by Google