Download presentation
Presentation is loading. Please wait.
Published byOsborn Johnson Modified over 9 years ago
1
Frankfurt (Germany), 6-9 June 2011 W. Niederhuemer – Austria – RIF Session 4 – Paper 1100 1 PROBABILISTIC PLANNING FOR A HIGHER INTEGRATION OF WIND TURBINES TO MV DISTRIBUTION NETWORKS Walter Niederhuemer Karl Derler Linz Strom Netz GmbH
2
Frankfurt (Germany), 6-9 June 2011 W. Niederhuemer – Austria – RIF Session 4 – Paper 1100 2 Introduction Feed in by onshore wind turbines into MV-grids is a particular challenge for the DSO Requests for connections primarily for several wind turbines or small wind farms Power range of a few MW Connections distributed across the same part of the MV- distribution network To enable the feed in and guarantee the power quality Reduction of the installed feed in power is necessary Extending the distribution network
3
Frankfurt (Germany), 6-9 June 2011 W. Niederhuemer – Austria – RIF Session 4 – Paper 1100 3 Introduction Producer and DSO with different optimum Producer Deliver full feed in power at any time Increase the energy output and thus to optimize the return Low direct grid connection costs DSO Keep the network cost as low as possible To support the objectives of the EU and to enable more feeding in, it is necessary To find an overall economic optimum To find a compromise between network investments and produces energy quantity
4
Frankfurt (Germany), 6-9 June 2011 W. Niederhuemer – Austria – RIF Session 4 – Paper 1100 4 Method of calculation Probabilistic calculation Taking into account the statistical behavior of Output voltage in the substation Current in the branch Feed in power of the wind turbine
5
Frankfurt (Germany), 6-9 June 2011 W. Niederhuemer – Austria – RIF Session 4 – Paper 1100 5 Result of the conventional assessment Reduction of installed feed in power to 2,2 MW is necessary Alternatively, 0,5Mio€ investment to the grid for a 3km long MV cable Selected network 1,2MW wind turbine + 250kW biogas plant connected New 2MW wind turbine is planned Connection via 17,5km overhead line 95mm² Aldrey Conventional assessment Peak load with and without feeding Off-peak load with and without feeding
6
Frankfurt (Germany), 6-9 June 2011 W. Niederhuemer – Austria – RIF Session 4 – Paper 1100 6 Result of the probabilistic calculation Installed wind turbine power 3,2MW Voltage exceeds the voltage limit only for a few hours. Theoretically generated annual amount of energy about 3.000 MWh With active power control 0,03% not feed in energy Reduction of active power up to max. 1370kW Annual revenue loss is less than 100€ (with feed-in tariff of 9,6ct/kWh)
7
Frankfurt (Germany), 6-9 June 2011 W. Niederhuemer – Austria – RIF Session 4 – Paper 1100 7 Result of the probabilistic calculation Theoretically generated annual amount of energy about 7.000 MWh With active power control 5% not feed in energy Real feed in energy 6.650 MWh Reduction of active power up to max. 3,8MW (50% of installed feed in power) 2 times higher energy yield without additional grid investments If a not feed in energy amount of 5% is acceptable for producers 7,5MW wind turbine power could be installed at the PCC Yearly earning of energy of on-shore wind turbines and loss because of control or switch off if voltage level is too high
8
Frankfurt (Germany), 6-9 June 2011 W. Niederhuemer – Austria – RIF Session 4 – Paper 1100 8 Conclusion Probabilistic planning allows a better simulation of real network conditions More than 2 times higher generation capacity by minimal network costs Acceptance by producers of a certain amount of not feed in energy is necessary Need of construction cost contribution for future grid investments Need of suitable legal frameworks
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.