Presentation is loading. Please wait.

Presentation is loading. Please wait.

Resource Requirements Planning:

Similar presentations


Presentation on theme: "Resource Requirements Planning:"— Presentation transcript:

1 Resource Requirements Planning:
Chapter 15 Resource Requirements Planning: MRP and CRP

2 Overview Resource Requirements Planning
Material Requirements Planning (MRP) Capacity Requirements Planning (CRP) Wrap-Up: What World-Class Companies Do

3 Resource Requirements Planning
Aggregate Planning Chapter 13 Master Production Scheduling (MPS) Resource Requirements Planning Material Requirements Planning (MRP) Chapter 15 Capacity Requirements Planning (CRP)

4 Material Requirements Planning (MRP)

5 Materials Requirements Planning (MRP)
Computer based system Explodes Master Schedule (MPS) into required amounts of raw materials and subassemblies to support MPS Nets against current orders and inventories to develop production and purchased material ordering schedules

6 Objectives of MRP Improve customer service Reduce inventory investment
Improve plant operating efficiency

7 Elements of MRP Inputs Outputs Service-Parts Orders and Forecasts
Inventory Transaction Data Order Changes Order Inventory Status File Planned Order Schedule MRP System Master Production Schedule Planning Report Performance Exception Reports Bill of Materials File

8 MRP Computer Program Begins with number of end items needed
Add service parts not included in MPS Explode MPS into gross requirements by consulting bill of materials file Modify gross requirements to get net requirements: Net Requirements = Gross Requirements + Allocated Inventory + Safety Stock - Inventory On Hand Offset orders to allow for lead time

9 Outputs of MRP Planned order schedule - quantity of material to be ordered in each time period Changes to planned orders - modifications to previous planned orders Secondary outputs: Exception reports Performance reports Planning reports

10 Example: MRP Schedule LocoMopeds is a manufacturer of off-road mopeds. The following product structure diagram represents the bill of materials for its dual-carburetor Model 442 moped. MOPED Level 0 ENGINE ASSEMBLY GAS TANK WHEEL ASSEMBLY (2) FRAME Level 1 MOTOR CARBURETOR (2) HUB ASSEMBLY TIRE Level 2

11 Example: MRP Schedule Bill of Material Parent Component Level Compon.
Code Code Code Description Req’d 442 0 #442 Moped 442 EA 1 Engine Assem. 1 GT 1 Gas Tank 1 WA 1 Wheel Assem. 2 F 1 Frame 1 EA M 2 Motor 1 C 2 Carburetor 2 WA HA 2 Hub Assem. 1 T 2 Tire 1

12 Example: MRP Schedule Inventory Status Report Item Code On- Hand
Safety Stock Lot Size Lead Time Sched. Receipts Qnty Week 442 500 200 LFL 1 -- EA 300 100 1000 10 GT 600 2 900 WA 400 2000 F 3 M 250 C 150 2500+ HA 2400 11 T 3000,2000 11,12

13 Example: MRP Schedule The company is currently planning production for weeks 10 through 16. Based on existing orders and demand forecasts, the master production schedule is as follows: Master Production Schedule: #442 Moped Determine the MRP schedule required to support the master production schedule for the Model 442 moped in weeks 11 1300 800 1200 1400 10 16 15 14 13 12 WEEK QUANTITY

14 Example: MRP Schedule MRP Schedule for #442 Mopeds for Weeks , considering that: Gross Requirements come from the moped MPS There is an On-Hand balance of 500 mopeds at the end of week 9 There are no Scheduled Receipts for mopeds A lot-for-lot rule is used for ordering mopeds Safety stock of 200 mopeds is desired Lead time for mopeds is one week

15 Example: MRP Schedule MRP Schedule for #442 Mopeds . . . Initially
GROSS REQUIREMENTS SCHEDULED RECEIPTS AVAILABLE (ON-HAND = 500) NET REQUIREMENTS PLANNED ORDER RECEIPTS PLANNED ORDER RELEASES ITEM: 442 MOPED LT: 1 LOT SIZE: LFL SS: 200 10 1300 11 12 13 800 15 14 1400 1200 16 WEEK

16 Example: MRP Schedule MRP Schedule for #442 Mopeds . . . Completed
GROSS REQUIREMENTS SCHEDULED RECEIPTS AVAILABLE (ON-HAND = 500) NET REQUIREMENTS PLANNED ORDER RECEIPTS PLANNED ORDER RELEASES ITEM: 442 MOPED LT: 1 LOT SIZE: LFL SS: 200 300 1000 10 1300 11 12 13 1200 800 1400 15 14 16 WEEK

17 Example: MRP Schedule MRP Schedule for Gas Tanks for Weeks , considering that: Gross Requirements come from moped Planned-Order-Releases There is an On-Hand balance of 600 gas tanks at the end of week 9 There is a Scheduled Receipt for 900 tanks in week 10 A lot-for-lot rule is used for ordering gas tanks Safety stock of 200 gas tanks is desired Lead time for gas tanks is two weeks

18 Example: MRP Schedule MRP Schedule for Gas Tanks . . . Initially
GROSS REQUIREMENTS SCHEDULED RECEIPTS AVAILABLE (ON-HAND = 600) NET REQUIREMENTS PLANNED ORDER RECEIPTS PLANNED ORDER RELEASES ITEM: GAS TANK LT: 2 LOT SIZE: LFL SS: 200 1000 900 10 1300 11 12 13 800 1200 15 14 1400 16 WEEK

19 Example: MRP Schedule MRP Schedule for Gas Tanks . . . Completed
GROSS REQUIREMENTS SCHEDULED RECEIPTS AVAILABLE (ON-HAND = 600) NET REQUIREMENTS PLANNED ORDER RECEIPTS PLANNED ORDER RELEASES ITEM: GAS TANK LT: 2 LOT SIZE: LFL SS: 200 1000 900 1300 10 800 1200 300 11 12 13 1400 15 14 16 WEEK

20 Example: MRP Schedule MRP Schedule for Frames for Weeks , considering that: Gross Requirements come from moped Planned-Order-Releases There is an On-Hand balance of 600 frames at the end of week 9 There is a Scheduled Receipt for 2000 frames in week 10 The firm uses a Lot Size (multiple) of 2000 for ordering frames No safety stock of frames is desired Lead time for frames is 3 weeks

21 Example: MRP Schedule MRP Schedule for Frames . . . Initially
GROSS REQUIREMENTS SCHEDULED RECEIPTS AVAILABLE NET REQUIREMENTS PLANNED ORDER RECEIPTS PLANNED ORDER RELEASES ITEM: FRAME LT: 3 LOT SIZE: SS: 0 1000 2000 10 1300 11 12 13 800 1200 15 14 1400 16 WEEK 600

22 Example: MRP Schedule MRP Schedule for Frames . . . Completed
GROSS REQUIREMENTS SCHEDULED RECEIPTS AVAILABLE (ON-HAND = 600) NET REQUIREMENTS PLANNED ORDER RECEIPTS PLANNED ORDER RELEASES ITEM: FRAME LT: 3 LOT SIZE: SS: 0 1000 2000 2600 10 1600 1300 11 12 13 800 500 300 900 1200 15 14 1400 16 WEEK 1500 1100

23 Example: MRP Schedule MRP Schedule for Engine Assemblies for Weeks , considering that: Gross Requirements come from moped Planned-Order-Releases There is an On-Hand balance of 300 engine assemblies at the end of week 9 There is a Scheduled Receipt for 1000 engine assemblies in week 10 The firm uses a Lot Size (multiple) of 500 for ordering engine assemblies Safety Stock of 100 engine assemblies is desired Lead time for engine assemblies is 1 week

24 Example: MRP Schedule MRP Schedule for Engine Assemblies Initially GROSS REQUIREMENTS SCHEDULED RECEIPTS AVAILABLE (ON-HAND = 300) NET REQUIREMENTS PLANNED ORDER RECEIPTS PLANNED ORDER RELEASES ITEM: ENGINE ASSEM LT: 1 LOT SIZE: SS: 100 1000 10 1300 11 12 13 800 1200 15 14 1400 16 WEEK

25 Example: MRP Schedule MRP Schedule for Engine Assemblies Completed GROSS REQUIREMENTS SCHEDULED RECEIPTS AVAILABLE (ON-HAND = 300) NET REQUIREMENTS PLANNED ORDER RECEIPTS PLANNED ORDER RELEASES ITEM: ENGINE ASSEM LT: 1 LOT SIZE: SS: 100 1000 1200 10 1500 200 500 1100 1300 11 12 13 800 400 100 15 14 1400 16 WEEK

26 Example: MRP Schedule MRP Schedule for Motors for Weeks , considering that: Gross Requirements come from engine assembly Planned-Order-Releases There is an On-Hand balance of 250 motors at the end of week 9 There are no Scheduled Receipts for motors A lot-for-lot rule is used for ordering motors No Safety Stock of motors is desired Lead time for motors is 1 week

27 Example: MRP Schedule MRP Schedule for Motors . . . Initially
GROSS REQUIREMENTS SCHEDULED RECEIPTS AVAILABLE (ON-HAND = 250) NET REQUIREMENTS PLANNED ORDER RECEIPTS PLANNED ORDER RELEASES ITEM: MOTOR LT: 1 LOT SIZE: LFL SS: 0 10 1500 500 11 12 13 1000 15 14 16 WEEK

28 Example: MRP Schedule MRP Schedule for Motors . . . Completed
GROSS REQUIREMENTS SCHEDULED RECEIPTS AVAILABLE (ON-HAND = 250) NET REQUIREMENTS PLANNED ORDER RECEIPTS PLANNED ORDER RELEASES ITEM: MOTOR LT: 1 LOT SIZE: LFL SS: 0 250 1250 10 500 1500 11 12 13 1000 15 14 16 WEEK

29 Example: MRP Schedule MRP Schedule for Carburetors for Weeks , considering that: Gross Requirements come from engine assembly Planned-Order-Releases (times 2) There is an On-Hand balance of 150 carburetors at the end of week 9 There are no Scheduled Receipts for carburetors A Lot Size of is used for ordering carburetors Safety Stock of 100 carburetors is desired Lead time for carburetors is 2 weeks

30 Example: MRP Schedule MRP Schedule for Carburetors . . . Initially
GROSS REQUIREMENTS SCHEDULED RECEIPTS AVAILABLE (ON-HAND = 150) NET REQUIREMENTS PLANNED ORDER RECEIPTS PLANNED ORDER RELEASES ITEM: CARBURETOR LT: 2 LOT SIZE: SS: 100 10 3000 1000 11 12 13 2000 15 14 16 WEEK

31 Example: MRP Schedule MRP Schedule for Carburetors . . . Completed
GROSS REQUIREMENTS SCHEDULED RECEIPTS AVAILABLE (ON-HAND = 150) NET REQUIREMENTS PLANNED ORDER RECEIPTS PLANNED ORDER RELEASES ITEM: CARBURETOR LT: 2 LOT SIZE: SS: 100 50 2500 10 3050 3000 950 1000 11 12 13 1450 1550 1050 2000 15 14 16 WEEK

32 Example: MRP Schedule MRP Schedule for Wheel Assemblies for Weeks , considering that: Gross Requirements come from moped Planned-Order-Releases (times 2) There is an On-Hand balance of 500 wheel assemblies at the end of week 9 There is a Scheduled Receipt for 2000 wheel assemblies in week 10 A Lot Size (multiple) of 500 is used for ordering wheel assemblies Safety Stock of 400 wheel assemblies is desired Lead time for wheel assemblies is 1 week

33 Example: MRP Schedule MRP Schedule for Wheel Assemblies Initially GROSS REQUIREMENTS SCHEDULED RECEIPTS AVAILABLE (ON-HAND = 500) NET REQUIREMENTS PLANNED ORDER RECEIPTS PLANNED ORDER RELEASES ITEM: WHEEL ASSEM LT: 1 LOT SIZE: SS: 400 2000 10 2600 11 12 13 1600 2400 15 14 2800 16 WEEK

34 Example: MRP Schedule MRP Schedule for Wheel Assemblies Completed GROSS REQUIREMENTS SCHEDULED RECEIPTS AVAILABLE (ON-HAND = 500) NET REQUIREMENTS PLANNED ORDER RECEIPTS PLANNED ORDER RELEASES ITEM: WHEEL ASSEM LT: 1 LOT SIZE: SS: 400 2000 2100 10 2500 100 2600 11 12 13 1600 2800 3000 400 200 2400 15 14 16 WEEK

35 Example: MRP Schedule MRP Schedule for Hub Assemblies for Weeks , considering that: Gross Requirements come from wheel assembly Planned-Order-Releases There is an On-Hand balance of 100 hub assemblies at the end of week 9 There is a Scheduled Receipt of 2400 hub assemblies in week 11 A lot-for-lot rule is used for ordering hub assemblies No Safety Stock of hub assemblies is desired Lead time for hub assemblies is 1 week

36 Example: MRP Schedule MRP Schedule for Hub Assemblies . . . Initially
GROSS REQUIREMENTS SCHEDULED RECEIPTS AVAILABLE (ON-HAND = 100) NET REQUIREMENTS PLANNED ORDER RECEIPTS PLANNED ORDER RELEASES ITEM: HUB ASSEM LT: 1 LOT SIZE: LFL SS: 0 10 2400 2500 2000 11 12 13 3000 15 14 16 WEEK

37 Example: MRP Schedule MRP Schedule for Hub Assemblies . . . Completed
GROSS REQUIREMENTS SCHEDULED RECEIPTS AVAILABLE (ON-HAND = 100) NET REQUIREMENTS PLANNED ORDER RECEIPTS PLANNED ORDER RELEASES ITEM: HUB ASSEM LT: 1 LOT SIZE: LFL SS: 0 100 10 2000 2500 2400 11 12 13 3000 15 14 16 WEEK

38 Example: MRP Schedule MRP Schedule for Tires for Weeks , considering that: Gross Requirements come from wheel assembly Planned-Order-Releases There is an On-Hand balance of 500 tires at the end of week 9 There are Scheduled Receipts for 3000 and 2000 tires weeks 11 and 12, respectively A Lot Size (multiple) of 1000 is used for ordering tires Safety Stock of 500 tires is desired Lead time for tires is 3 weeks

39 Example: MRP Schedule MRP Schedule for Tires . . . Initially
GROSS REQUIREMENTS SCHEDULED RECEIPTS AVAILABLE (ON-HAND = 500) NET REQUIREMENTS PLANNED ORDER RECEIPTS PLANNED ORDER RELEASES ITEM: TIRE LT: 3 LOT SIZE: SS: 500 10 3000 2500 2000 11 12 13 15 14 16 WEEK

40 Example: MRP Schedule MRP Schedule for Tires . . . Completed
GROSS REQUIREMENTS SCHEDULED RECEIPTS AVAILABLE (ON-HAND = 500) NET REQUIREMENTS PLANNED ORDER RECEIPTS PLANNED ORDER RELEASES ITEM: TIRE LT: 3 LOT SIZE: SS: 500 2000 10 3000 2500 11 12 13 1500 500 15 14 16 WEEK

41 Lot-Sizing in MRP Lot-size is the quantity ordered/produced at one time Large lots are preferred because: Changeovers cost less and capacity greater Annual cost of purchase orders less Price breaks and transportation breaks can be utilized Small lots are preferred because: Lower inventory carrying cost Reduced risk of obsolescence Shorter cycle time to produce customer order

42 Lot-Sizing Methods Typical MRP methods accommodates lumpy demand
Lot-for-Lot (LFL) Period Order Quantity (POQ) Comments on Economic Order Quantity (EOQ) does not consider quantity discounts does not always provide the most economical approach with lumpy demand

43 Example: Lot-Sizing Decision
The net requirements for a material from an MRP schedule are: It costs $400 to change over the machines for this material in the affected work center. It costs $0.40 per unit when one unit of this material must be carried in inventory from one week to the next. Identify the lot-sizing method that results in the least carrying and changeover costs for the 8-week schedule. NET REQUIREMENTS 1000 1 1300 2 3 4 800 1200 6 5 7 WEEK 8

44 Example: Lot-Sizing Decision
Lot-for-Lot Method Carrying Cost = 0($.40) = $0 Changeover Cost = 6($400) = $2,400 Total = $2,400 NET REQUIREMENTS BEGINNING INVENTORY PRODUCTION LOTS ENDING INVENTORY 1000 1 1300 2 3 4 800 1200 6 5 7 WEEK 8

45 Example: Lot-Sizing Decision
Economic Order Quantity (EOQ) Method S = $400.00 D = [(Net Req. for 8 wks)/8 weeks)](50 weeks/year) = (6400/8)(50) = 40,000 C = ($0.40 per week)(50 weeks/year) = $20.00

46 Example: Lot-Sizing Decision
Economic Order Quantity (EOQ) Method Carrying Cost = 4855($.40) = $1,942 Changeover Cost = 6($400) = $2,400 Total = $4,342 NET REQUIREMENTS BEGINNING INVENTORY PRODUCTION LOTS ENDING INVENTORY 1000 1265 265 1 230 1300 2 3 4 800 725 760 695 1200 6 5 7 WEEK 1190 8

47 Example: Lot-Sizing Decision
Period Order Quantity (POQ) Method POQ = (# Weeks/year)/(# Orders/year) = 50/(D/EOQ) = 50/(40,000/1,265) = or 2 weeks

48 Example: Lot-Sizing Decision
Period Order Quantity (POQ) Method Carrying Cost = 2900($.40) = $1,160 Changeover Cost = 4($400) = $1,600 Total = $2,760 NET REQUIREMENTS BEGINNING INVENTORY PRODUCTION LOTS ENDING INVENTORY 1000 1 800 2100 1300 2 3 4 2500 1200 6 5 7 WEEK 8

49 Example: Lot-Sizing Decision
Summary Carrying Chg.Ovr. Total Method Cost Cost Cost LFL 0 2,400 2,400 EOQ 1,942 2,400 4,342 POQ 1,160 1,600 2,760

50 Issues in MRP Lot-Sizing
Useful at lower levels but may drive excess inventory when applied at higher levels Net Change versus Regenerative MRP Net change may generate too many action notices Regenerative more costly to run but appears to be easier to manage . . . more

51 Issues in MRP Safety Stock
Use depends on uncertainty of demand..... more uncertain the greater the need for safety stock Assemble-to-Order Firms MPS and MRP treated separately from Final Assembly Schedule(FAS) FAS is prepared 1-2 weeks ahead Use Modular Bill of Material For each option with a demand forecast

52 MRP I to MRP II MRP I simply exploded demand (MPS) into required materials MRP II became Manufacturing Resource Planning which provides a closed-loop business management system Financial management Shop floor control Operations management Simulation capability

53 Evaluation of MRP Most beneficial to process-focused systems that have long processing times and complex multistage production steps Lead times must be reliable Must freeze MPS for some time before actual production... certain demand Difficult to implement

54 Capacity Requirements Planning (CRP)

55 Capacity Requirements Planning (CRP)
Tests MPS for feasibility Utilizes routings to determine labor/machine loads If schedule feasible, recommends freezing If schedule overloads resources, points out processes that are overscheduled

56 Load Schedules Compares actual labor and machine hours against available hours Offsets schedules between successive stages of production by lead times Provides feasible MPS and economically loaded work centers Promotes system operating efficiency ... lowers costs!

57 HW Chapter 15 HW #7 and 16 on page 612 and 617.

58 End of Chapter 15


Download ppt "Resource Requirements Planning:"

Similar presentations


Ads by Google