5 SHOVELS Front shovels are used predominately for hard digging above track level and for loading haul units. Loading of shot rock would be a typical application.

6 STEP 1: BUCKET SIZE Shovels can usually be equipped with different size buckets. Bottom dump buckets are also available.

7 STEP 1: BUCKET SIZE Buckets are rated in both heaped and struck capacities. Both PCSA and SAE use a 1:1 angle of repose for evaluating heaped bucket capacity. CECE specifies a 2:1 angle of repose. Heaped Capacity is the rating of interest for Production Estimating.

8 STEP 2: FILL FACTOR The Fill Factor adjusts Heaped Capacity in lcy based on the type of material being handled. Table 9.1, page 258

9 STEP 2: FILL FACTOR HEAPED BUCKET CAPACITY  FILL FACTOR
= VOLUME (lcy)

10 STEP 3: CYCLE TIME There are four elements in the production cycle of a shovel: Load bucket Swing with load Dump load Return swing See page 260

11 STEP 3: CYCLE TIME Height of cut affects shovel production. Optimum height of cut ranges from 30 to 50% of maximum digging height, with the lower percentage being representative of easy-to-load materials, such as loam, sand, or gravel. Table 9.2

12 STEP 3: CYCLE TIME Angle of swing affects shovel production. If the angle of swing is increased, the time for a cycle will be increased, whereas if the angle of swing is decreased, the time for a cycle will be decreased. Table 9.2

13 STEP 3: CYCLE TIME Ideal production of a shovel is based on operating at a 90° swing and optimum height of cut. The effect of the angle of swing on the production of a shovel is illustrated in Table 9.2.

14 STEP 4: EFFICIENCY FACTOR
When selecting a minutes per hour efficiency factor visualize the work site and consider: Materials being handled, bank or broken Size of the shovels’s dumping target, (large or small)

15 STEP 5: CLASS of MATERIAL
Production will be in lcy, will need swell factor to adjust to bcy. TABLE 4.3

16 STEP 6: PRODUCTION X Heaped Capacity (lcy) X Fill Factor
X height/swing factor = Production (lcy/hr)