MSD II Week 5 Update P13265: Motorcycle Safety Lighting and Portable Electronics Charging System
2
Mike: Action Items Status Lens Covers o Incomplete: Shell is ~2 weeks behind schedule Material arrived early this week Test XBee's and Bullet Connectors on Bike w/TJ o Incomplete, due to XBee units o Will test this weekend depending on XBee status Tech Paper o In Progress o Need to review with TJ, no more content to add from me until build is furthered
3
Mike: Next Steps for Week 6 Begin Making Lens Covers ~ ? Assist with light wiring~ 2 hrs
4
Tyler: Action Items Status Shell Rework/Remake o Incomplete o Have not been able to complete much because of Killian being sick. Material purchased and cut, will be pieced together today and sanded to form. Plan to get shell manufactured Sunday. Assembly Plan 75% Done o Complete Poster o Incomplete, not much time to work on Poster due to Killian being sick and other work. Major work to be completed on it once shell is finished.
5
Tyler: Next Steps for Week 6 Finish new mold ~6 hrs Finish shell ~3 hrs Shell Assembly ~15 hrs Poster Work ~5hrs Assembly Plan (Final details will be completed alongside the actual assembly of thr backpack) EDGE update ~3 hrs
6
Ben: Action Items Status Finish electronics housing box o complete, minus glue o This took far more time than I anticipated o Machine screws were changed in favor of sheet metal screws Other: o I tried to reach Andy this week but prior commitments prevented us from meeting (this is to take measurement of his motorcycle) o Quick connect assembly plan was written o Tx box alterations are still on hold until internal components are configured
7
Ben: Next Steps for Week 5 Glue remaining pieces in place Meet with Andy Nauss and complete work on quick connect
8
Eric: Action Item Status Continue MSP430 Development o In Progress o Framework is continuously being modified. Board error identification o Complete o All errors located, documented.
9
Eric: Next Steps for Week 6 MSP430 Development ~ 15 hours Assist TJ with board build and test
10
TJ: Action Items Status Continue Tech Paper o Complete o Added more paragraphs to revise with Mike Populate PCBs o In Progress o Meeting with Dr. Fuller to manufacture adapters o Will spend Friday in the lab Test XBee Units and Document Tests o In Progress o New Units in and Old Units sent to Digikey for review
11
TJ: Next Steps for Week 6 Continue Tech Paper ~ 2 Hours Populate PCBs ~ 10 Hours Test XBee's in Lab and on Bike ~ 2 Hours EDGE Update ~ 2 Hours
12
Killian: Action Items Status Vacuum Form the control panel 3 times, sand and assemble: In Progress Continue Sketching internal pockets/configurations: In Progress Develop possible branding (product name, logo): In progress
14
Killian: Next Steps for Week 4 Refine Sketches and concepts and start to render in photoshop and illustrator~8 hours Assist Tyler in backpack assembly~5 hours Assist Tyler with poster layout?~2 hours?
15
Major Week 6 Action Items Mike- Lens Covers (hopefully) TJ - Populate PCBs
16
Lessons Learned Mike o A backup plan will be necessary to complete our final assembly by Imagine RIT. Tyler o A good fallback plan for the mold was not in place which has pushed it's completion time back even more. Ben o What i said about being in the machine shop after 9 isn't necessarily true anymore- a student was caught with an illegal item they supposedly fabricated in the machine shop so now hours are more rigidly enforced o check, check and then check again when making measurements
17
Lessons Learned cont. Eric o Travelling for interviews takes more time and is more distracting than expected. TJ o Capabilities to make small 'adaptors' for the EH board and can do this in house, thus saving the group some money Killian o I'm not surprisingly good at not sleeping, I get sick the next week.