Minnesota Department of Transportation Mn/DOTs Gradual Shift from Profile Index to IRI.

Similar presentations


Presentation on theme: "Minnesota Department of Transportation Mn/DOTs Gradual Shift from Profile Index to IRI."— Presentation transcript:

1 Minnesota Department of Transportation Mn/DOTs Gradual Shift from Profile Index to IRI

2 Chronology of Shift to IRI 1999: Participated in FHWAs Lightweight Profiler Study, hosting various vendors at MnRoad site Overall, LWP devices involved in study demonstrated moderate repeatability and poor reproducibility

3 Chronology of Shift to IRI 2001: Purchased Ames Lightweight Profiler and ARRB Walking Profiler Began performing random Quality Assurance on projects with ride incentive determined from 0.2 blanking band Profile Index

4 Mn/DOTs Lightweight Profiler

5 Chronology of Shift to IRI 2002: Initiated Profile Index Smoothness Measuring Device Program in spring During QA on job sites, experienced problems replicating contractors 0.2 blanking band Profile Index values

6 Empirical Data: Projects with 0.2 blanking band PI value of 0.0 possessed IRI values ranging from roughly 27 - 42 in/mi Projects with 0.2 blanking band PI value of 1.0 possessed IRI values ranging from roughly 29 - 46 in/mi 0.2 Blanking Band PI vs. IRI

7 Chronology of Shift to IRI 2002 - 2003: Analyzed extensive certification and construction data, finding a very weak correlation between 0.0 and 0.2 blanking band Profile Index results

8 Chronology of Shift to IRI 2005: Let 13 additional bituminous IRI pilot construction projects 2004: Let three bituminous IRI pilot construction projects

9 Chronology of Shift to IRI 2006: Let three concrete IRI pilot projects (results pending) Switched to IRI exclusively on bituminous construction projects Began using Pathways High Speed Profiler for Quality Assurance purposes

10 Mn/DOTs High Speed Profiler

11 Bituminous Ride Incentive Equations

12 Incentive per 528-Foot Segment Bituminous Ride Incentive Equations

13 Bituminous IRI % Improvement Table

14 Incentive/disincentive calculated for each 528-foot segment Payment is based on right wheel path IRI values (9 feet from left stripe) IRI data collected by contractor with certified profiler Bump/dips established with profilograph Ride Incentive Information

15 2007: Will use IRI exclusively to determine ride incentive for all construction projects Chronology of Shift to IRI

16 Any Questions?