NEW MEDICAL FACILITY BUILDING By: Vincent Cannatella and Shelbi Remy Advisor: Edward Rode Instructor: Cris Koutsougeras ET 493 - Senior Design 1.

Similar presentations


Presentation on theme: "NEW MEDICAL FACILITY BUILDING By: Vincent Cannatella and Shelbi Remy Advisor: Edward Rode Instructor: Cris Koutsougeras ET 493 - Senior Design 1."— Presentation transcript:

1 NEW MEDICAL FACILITY BUILDING By: Vincent Cannatella and Shelbi Remy Advisor: Edward Rode Instructor: Cris Koutsougeras ET 493 - Senior Design 1

2 Introduction  Our senior project this semester will involve complete development of a theoretical medical building.  We will determine preliminary design, building and fire code requirements, the site location, and begin the preliminary building estimates.  Rooms  Waiting Room  Play Room  Restroom  Utility Room  Break Room  Reception Room  X-Ray Room  Processing Room  Ambulatory Room  Doctor Office  Administration Office  Nurse Office  3 Exam Rooms  The building will be 2,378 square feet.

3 Preliminary Drawings  Floor Plan

4 Preliminary Drawings  North and South Elevations

5 Preliminary Drawings  East and West Elevations

6 Exterior Finishes  Roof ●“S” Tile Roofing material  Wall Finish ●Stucco (decorative wall finish) ●Owner will select color  Trim Pieces ●2x8 Fascia ●2x2 window trim ●Owner will select color

7 Building Codes  The building codes come from the Hammond Zoning Ordinance booklet.  Part 1: Principles and Objectives ● Section 1.3 - Commercial ○ 1.306  Part 3: Schedule of District Regulations Adopted ● Section 3.8 – C-1 Commercial District ○ 3.805 ○ 3.806 ○ 3.807  Part 5: Off-Street Parking and Loading Requirements ● Section 5.3 – Commercial ○ 5.301 ● Section 5.6 – Off-Street Loading Requirements ○ 5.601

8 Fire Codes  The fire codes came from the National Fire Protection Association 101 Life Safety Code booklet.  Chapter 26: New Building Occupancies ● Section 26-1: General Requirements ○ 26-1.7 ● Section 26-2: Means of Egress Requirements ○ 26-2.1.1 ○ 26-2.3.2 ○ 26-2.4 ○ 26-2.6 ○ 26-2.8 ● Section 26-3: Protection ○ 26-3.3.1 ○ 26-3.5

9 Determining Location  Hammond, LA  Main road  Zoning: Commercial  Easy access  Narrowed down to 3 locations

10 Location 1  1107 West University Ave.  1.15 acres  Price: $799,695  Lot is cleared and ready to build on

11 Location 2  On the corner of East University Ave. and North Cherry St.  5.5 acres  Price: $250,000  Not cleared

12 Location 3  Highway 190, West of I-55  3.07 acres  Price: $129,000  Not cleared

13 Final Location  We chose location 2  Decision was based on location, price, and lot size  Only 3 acres will be used  Sell the remaining 2.5 acres for roughly $100,000  A total of around $150,000 invested after selling land

14 Timeline/Deliverables Week 1-21/20/15 – 2/3/15Determine a project and the tasks involved Week 3-42/4/15 – 2/18/15Determine a site location and cost of the property Week 52/19/15 – 2/26/15Specify the building codes Week 62/27/15 – 3/6/15Specify the fire codes Week 73/7/15 – 3/14/15Work on preliminary drawings; floor plan and elevation plans Week 83/15/15 – 3/22/15Work on proposal document and presentation Week 9-133/23/15 – 4/27/15Begin estimation for materials Week 14-154/28/15 – 5/8/15Prepare final document and presentation