W. Robert Patterson & Associates PV SOLAR PROJECT DEVELOPMENTS For the Plymouth Public Schools Bob Patterson November 22, 2010.

Similar presentations


Presentation on theme: "W. Robert Patterson & Associates PV SOLAR PROJECT DEVELOPMENTS For the Plymouth Public Schools Bob Patterson November 22, 2010."— Presentation transcript:

1 W. Robert Patterson & Associates PV SOLAR PROJECT DEVELOPMENTS For the Plymouth Public Schools Bob Patterson November 22, 2010

2 WRPA 2 Typical Flat Roof Mounted PV Solar

3 WRPA 3 PV Solar Project Groups Project A – South Middle, South Elementary, West Elementary & Plymouth Community Intermediate School 1.95 MWe solar capacity – $8 million to $8.8 million* Project B – Federal Furnace, Cold Spring, Indian Brook, Nathanial Morton, Manomet, Hedge & Admin. Building. 0.893 MWe solar capacity – $3.6 million to $4.0 million* Other Opportunities – South High School, Oak Street & Pre-School 100 to 200 kWe solar capacity – * Investment Cost paid for by Developer/Vendor under Lease.

4 WRPA 4 Timeline October 15 th - Preliminary Reviews & Designs – Done. November 5 th – Working with Town Counsel on RFP – Draft. November 30 th – RFP Issued. December 15 th - Vendor/Developer Site Visits. January 14 th - Vendor/Developer Proposals Due. January 21 st - PPS Selects Vendor/Developer. January 28 th – Facility Lease Contracts Approval by School Committee. February 25 th - Facility Lease Contracts - Signed. February thru May, 2011– PV Solar Arrays Installed & Commercial Operation.

5 WRPA 5 Important Contracting Documents Plymouth Public Schools – Request for Proposals Working with Town Counsel on RFP RFP Public Bidding under G.L. c. 30B sec. 16 Technical Proposal with Developer Qualifications. Facility Lease Proposal with payment terms & conditions. PPS Facility Lease Agreement – Stipulates access to and use of School Facility Roofs. Sets the Terms and Conditions of the PPS price of electricity. Lease Agreement – 20 years under G.L.c.40, sec 3

6 WRPA 6 PPS Project Steps Note: Approval of School Committee to Proceed. Preliminary review and design of solar panel mounting system. Preliminary review of electrical interconnection and metering. Issue request for proposals to qualified PV System developers. Negotiate Power Purchase Agreements and Facility Leases. Note: School Committee Approval of Power Purchase Agreement & Facility Leases. Local building permits awarded & Interconnection Agreement signed. Financial closing, PPA and Leases signed, start of construction. Mechanical/Electrical construction completed – commercial operations start.

7 WRPA 7 W. Robert Patterson & Associates - Assists Plymouth Public Schools (PPS) with electricity, natural gas & fuel oil contracting. - Assists many communities & school systems with PV Solar project development. - Assists many communities & school systems with energy contract negotiations.