1
Construction Phase October 21, 2014
2
City of Palm Coast Brian Rothwell, Purchasing Manager Team Leader Stephen Flanagan, Utility Development Manager Carl Cote, Construction Manager Dianne Torino, Contracts & Risk Manager Christopher Quinn, Finance Director Virginia Smith, City Clerk Beau Falgout, City Administration Coordinator C.T. Hsu & Associates, Inc. Jim Hughes, Principal Tim McNicholas, Principal Gilbane Building Company Joe Frisco, Senior Project Executive
3
Appropriate Project Size and Scope Built for Immediate Needs No Increase in Existing Residents’ Taxes Use Existing Financial Resources City Hall Offices = $6.9 Million Building Permit Fund Excess Revenues=$1.1 Million Repayment of SR100 CRA (Town Center) Loan=$5.8 million Central Park Community Areas Allow for phasing as CRA (Town Center) revenues are available Available CRA Funds in FY2015=$0.5 million
4
Completed Space Needs and Cost Analysis Refinanced Inter-Fund Loan Allocated Funds for Project Approved Service Contracts Architectural Services Construction Management Services (at-risk) City Council Preliminary Design Presentation Marketing Efforts to Encourage Local Bidders Final Design Completed Construction Manager Bids Project Guaranteed Maximum Price Ground Breaking Occupancy
5
Presented to City Council on March 11, 2014
6
PHASES | City Hall and Community Spaces Community Event Lawn Future Parking as Needed Future Additional Offices City Hall 32,000 s.f. Phase 1 Parking CommunityMeeting 8,000 s.f. AdditionalParking Promenade and and Public Plaza 1 2 3 4
7
LAKE VIEW IN CONTEXT
8
LAKEFRONT PLAZA VIEW
9
Phase 1 – City Hall Offices Phase 2a – Infrastructure for Central Park Community Areas
13
1 st Floor
14
2 nd Floor
15
Vendor Roundtables Vendor Pre-Qualification Local & Market Area Participation 17 Vendor Packages (e.g. Concrete, Elevators, etc.) 8 Likely Awards to Local and Market Area Vendors
16
Guaranteed Maximum Price of $6,613,743 33,420 s.f. City Hall Office Building Includes Furnishings, Fixtures, and Equipment 1,697 s.f. of Unfinished Areas for Future Build Out Phase 2a: Infrastructure Work for Central Park Community Areas LEED Certification
17
Existing Contract Construction Manager (CM) At-Risk Cost Overruns CM Responsibility, Not City Cost Savings Returned 80% to City 20% to CM Amendment to Contract Establishes Guaranteed Maximum Price of $6,613,743
18
PROJECT COSTS PROJECT FUNDING Design Fees$794,230 Pre-Construction Fees $41,890 Construction$6,613,743 Total$7,449,863 Approved Project Budget Loan Repayment$5,792,529 Bldg. Reserves** $1,111,334 CRA Funds***$546,000 Total$7,449,863 **Building Department Reserves for Building Function of City Offices ***CRA Funds for Design and Phase 2a Project Costs
19
GMP ApprovalOctober 21, 2014 GroundbreakingOctober 29, 2014 ConstructionNov. 2014 – Aug. 2015 Substantial CompletionAugust 2015 FFE InstallationSeptember 2015 City OccupancyOctober 2015 Marketplace Lease EndsNovember 2015