Facilities Modernization Program Funded by Measure B Project Report March 19, 2012.

Similar presentations


Presentation on theme: "Facilities Modernization Program Funded by Measure B Project Report March 19, 2012."— Presentation transcript:

1 Facilities Modernization Program Funded by Measure B Project Report March 19, 2012

2 PROJECT PROGRESS REPORT PE Phase III (Outside Loop Road) Project Team: Architect: WLC Architects / Carducci Landscape Architects Construction Manager: Parsons Brinckerhoff Contractor: Lathrop Construction Project Update: Project is complete. DSA Closeout is in progress. Occupancy: 04/2011 LAS POSITAS COLLEGE March 19, 2012

3 PROJECT PROGRESS REPORT Science Building, Phase II Project Team: Architect: Kwan Hemni Construction Manager: Parsons Brinckerhoff Contractor: Broward Builders, Inc Project Update: Interior Casework, Lighting and Fume hoods being installed. Exterior Painting is in progress. Interior Painting is Completed. Electrical and Data installation and termination is continuing at first and second floors. Flooring at 2 nd floor classrooms completed. Storefront installation and Glazing Completed. Stair Treads installed. Occupancy: 09/2012 LAS POSITAS COLLEGE March 19, 2012

4 PROJECT PROGRESS REPORT Student Services & Central Administration Project Team: Architect: Steinberg Architects Construction Manager: Parsons Brinckerhoff Contractor: Zovich Construction Project Update: GFRC installation complete. Storefront installation has started along with glazing. Site fine grading is complete. Building metal panels have to start within 2 weeks. Sheetrock has started on one side of the walls. Elevator installation to begin next week. Roofing is complete. Occupancy: Spring 2013 LAS POSITAS COLLEGE March 19, 2012

5 PROJECT PROGRESS REPORT Campus Boulevard Phase I-III Project Team: Architect: Gates & Associates Construction Manager: Parsons Brinckerhoff Contractor: TBD Project Update: 100% Design review completed, final design was Approved by DSA February 2012. Project was Bid on March 13, 2012 and Low Bid Contractor will be Board Approved April 17, 2012 Design Re-Start: 04/2011 DSA Permit Approval: 02/2012 Construction Start: 05/2012 Occupancy: TBD LAS POSITAS COLLEGE March 19, 2012

6 PROJECT PROGRESS REPORT Photovoltaic System Phase II Project Team: Design Build Contractor: Cupertino Electric Inc. Construction Manager: Parsons Brinckerhoff Project Update: Fencing Completed. Racking System and Array installation is completed. Inverters and Transformer installed and completed. New Switchgear tie in during Spring Break. Operational: February 2012 LAS POSITAS COLLEGE March 19, 2012


Download ppt "Facilities Modernization Program Funded by Measure B Project Report March 19, 2012."