1 Belle II IR 2 Shuji Tanaka KEK Joint Belle II & superB Background meeting 2012//Feb/ 8-9th 1
2
2 Requested to discuss about IR IR magnets –magnetic filed calculation, canceling coils,canceling solenoid, leak filed, fabrication status,cryostat (Ohuchi-san'talk) IR mechanical design –beam pipe design, fabrication process, cooling, heavy metal shield,installation procedure, assembly, cabling space), –Movable collimator(shape, material, instability, impedance, secondary particles) –Vertex detectors –Beast II( Belle II comissioning)
3
3 Beam pipe : R in = 2.0 cm SVD1 : R = 3.0, 4.5, 6.0 cm CDC : 3 layers of Cathode part Beam pipe : R in = 1.5 cm SVD2 : R = 2.0, 4.35, 7.0, 8.8 cm CDC : 2 layers of small cell chamber History of Belle Vertex detector SVD1->SVD2
4
4 History of Vertex detector SVD2-> BelleII SVD 1,Slant structure 2,Hgh speed readout (800ns->20ns) 3, 20mm diameter beam pipe 4, PXD detector (NEW: R=14, 22mm) Beam pipe radius: @IP (Tsukuba hall) Topaz: 50mm Belle (SVD1): 20mm (SVD2): 15 mm BelleII: 10mm More challenge on mechanics design 4 times larger volume coverage
5
5 Assembly procedure
6
6 Half Mask Temporary mask supports Beam pipe positioner made of the heavy metal Beam masks
7
7 Beam pipe Beam pipe temporary support The mass of the masks are supported at these points (close to the center of gravity of masks) The position of the beam pipe is defined in the backward at this point after installation to CDC. We need a mechanism that constrains the r-φ position of the beam pipe while allowing a slide in the Z direction. Otherwise, the PXD position can not be defined.
8
8 Mask2 (1) The left side and right side masks are screwed into one piece. (2) Rotate by 90° so that the masks support the beam pipe form left and right.
9
9 Support flange Support flange will be put in the forward side. The support flange for supporting the IR system to QCS in the installation and to CDC after the installation
10
10 Masks are completed The heavy metal masks are completed.
11
11 PXD PXD is assembled to two halves in another stage and put together to the beam pipe. Cables and tubes will go to the slot in the masks. need some flexibility for relative movement between beam pipe and heavy metal shield
12
12 Combine with SVD SVD is also assembled in another stage. The forward and backward support cones are then fixed with the outer cover, made of CFRP. Then they are put together around the beam pipe.
13
13 VXD installation procedure
14
14 Assembly at KEK Combined with QCS at Tsukuba hall SVD support ring Vertex detector installation
15
15 The sled guide is fixed on backward side Vertex detector installation
16
16 How to connect with backward sled 16 Adapting support ring Connected with sled
17
17 Vertex detector installation Guide pin to fix the VXD angle
18
18 Vertex detector installation Temporal support guide The VXD weight is keep by support guide and QCS
19
19 Vertex detector installation This guide ring keep weight
20
20 Vertex detector installation The backward weight is shift to this guide SVD cover should not attach to another structure on installation at evertime
21
21 Vertex detector installation Remove backward sled
22
22
23
23 How to fix at SVD backward 23 VXD detector is fixed at backward end for x, y, z axis Remove sled Remove support ring and adopt a bracket connecting with CDC inner structure
24
24 SVD support ring at forward region Guide roller to keep weight of SVD Positioning guide pin (CDC side) Release control rod after install (QC cryostat side) The VXD center position is arranged by those rollers. Forward region is fixed only for x and y axis
25
25 Vertex detector installation
26
26 Vertex detector installation
27
27 2011 Optimizing production procedure(writing rough sketch note for each procedure) for first prototype. –Service space allocation will be decided –Validate the technology of connectivity for each materials. 2012 From the end of 2012 –Starting VXD mock-up assembly Mechanics check -> installation test, Cooling test Beam pipe production(for BEASTII) Freezing the mechanics design (including cooling system, cabling, monitors) 2013 SVD Ladder mount start (SVD) (2013 Sep.) Beam pipe production 2014 End of 2014 -> BEAST Beam pipe production 2015 Starting VXD assembly(Aug-Sep) (CR test ) and installation 27 Schedule (IR mechanics)