STUBBLEFIELD LAKE ROAD Head Wall Failure
2
THE HEAD WALLS ARE GIVING AWAY AND THE ROAD IS SINKING
3
PILING TIMBERS HAVE GIVEN AWAY
4
EXACT DAMAGE IS NOT ACCESSIBLE UNTIL EXCAVATION BEGINS
5
This one is over four feet deep!!
6
LABOR COSTS Just recently Precinct 4 built bulkheads on Hostetter Rd. That project cost the county roughly $120 per foot. Stubblefield Lake Rd needs 180 feet of bulkheads constructed. $120/ft x 180’ = $21,600 *** This is just a rough estimate. ***
7
MATERIAL COSTS (STEEL) 38-7 5/8”Pilings, 8- 30’ x 5/16”sheet plate, 180’- 7”channel, 180’- 8”Angle, 40’-4” Angle, 40’-4” Flat Bar, 500’-3/4”Galvanized Cable, 50-3/4” Galvanized Cable Clamps $23,000.00 *** This is just a rough estimate. ***
8
ROAD MATERIAL COSTS Stabilized Sand 200tns * 30.14/tn = $6,028.00 Limestone Base 150tns * 24.59/tn = $3,688.50 Hot Mix 100tns * 67.69/tn = $6,769.00 $16,485.50 *** This is just a rough estimate. ***
9
APPROVAL REQUESTED Total Estimated Cost $61,085.50 Please approve purchasing to bid out this project.