Download presentation
Presentation is loading. Please wait.
Published byOswin Underwood Modified over 9 years ago
1
AAQG Project Report Out Each Team Leader / Project Champion:Each Team Leader / Project Champion: –Use the Project Plate as part of their project folder information along with 4-square and Milestone chart –Start each project report out with: Page 1 being the Title PagePage 1 being the Title Page Page 2 being the Project PlatePage 2 being the Project Plate Page 3 being the listing of Team MembersPage 3 being the listing of Team Members Page 4 being the 4-squarePage 4 being the 4-square Page 5 being the Milestone chartPage 5 being the Milestone chart Page 6 and on - Any additional information the Team Leader / Project Champion wants included can followPage 6 and on - Any additional information the Team Leader / Project Champion wants included can follow
2
Americas Aerospace Quality Group AAQG Project Management Project #54 AIR5359 Update Team Reported by: Vince May Date of Report: 2005-09-14
3
Date of project approval:Project Plate Revision: Solution: Root Causes: Metrics: Deliverables: Success Criteria: Americas Aerospace Quality Group - Project Plate AAQG Project Leader: Champion: Problem Statement and Scope: P#54 – AIR5359 Update Team 2005-06-071 Vince May Mike Roberts 1.AIR5359 contains “shalls” therefore it should be an AS (Standard) 2.Need for implementation of AS9104 in the Americas’ Sector 1.Requirements for AS vs. AIR were not clearly understood 2.Release of AS9104 by the IAQG caused a re-write of AIR5359 1.Change AIR5359 to AS9014 2.Integrate AIR5359 and AS9104 requirements into a AS9014 as a single document 1.Develop a comparison matrix between AS9104 and AIR5359 2.Draft AS9014 3.Perform gap analysis of AS9014 vs. FAA 8120.12 and C.I. 21-011 4.Submit to SAE for 2 week review 5.Submit for balloting 6.Release AS9014 1.Successful ballot in the Americas 1.100% Project Milestones 2.Meeting Attendance
4
AIR5359 Re-Write Team Team Members Mike Roberts (Champion) Boeing Vince May (Leader) Honeywell Reg Blake BSI Fred Becker Intertek Luiz Brandao Embraer Buck Crenshaw Claudia Tobar JPLJPL Randy Dougherty ANAB Hollie Last SCC Darris Martin Lockheed-Martin Lori Scheid ANAB David Stevens Rolls-Royce Sidney Vianna Miguel Rocha Cindy Miller/Michael Carmody DNVINMETRORABQSA
5
Project description / benefits: AAQG Champion:Date of last report:Date of this report:Status: Unresolved issues & decisions (if any): Recent accomplishments (since last report): Next steps (30-60-90 day look ahead): Project Leader: Americas Aerospace Quality Group - Project 4-Square 1.Incorporated Approval of Auditor Authentication Bodies 2.Removed RMC Approval of Trainers 3.Added definition of Auditor Authentication Body from the AIR5493 Re-Write Team 4.Removed FAA 8120.12 requirement for suppliers and CRBs to notify the PAH when a supplier fails an initial registration audit * See additional issues/decisions in Additional Information Section P#54 – AIR5359 Update Team 1.Drafted AS9014 2.Performed Gap Analysis of AS9014 vs. FAA 8120.12 3.Updated AS9014 to Fill Identified Gaps 4.Submitted to SAE for Comments 5.Updated AS9014 to Resolve Issues from SAE Comments 6.Updated AS9014 to include SAE Comments dispositioned by the RMC 7.Submitted to SAE for balloting 1.Resolve comments from balloting 2.Submit for “quick turn” ballot 3.Release AS9014. Mike Roberts2005-06-072006-01-31 Vince May 1.Description of Project Update AIR5359 to AS9014 2.Benefit of project Americas Sector compliance to AS9104 YRG Y
6
Task Due Date % Complete AS9104 vs. AIR5359 Comparison Matrix06/07/05100% Draft AS901406/07/0599% Gap analysis of AS9014 vs. FAA 8120.12 and C.I. 21-01106/15/05100% Submit to SAE for 2 week review06/17/05100% Review and disposition SAE comments08/18/05100% Submit to SAE for balloting12/09/05100% Release AS901403/31/060% Milestones
7
Additional information Continued use of AAs in the Americas schemeContinued use of AAs in the Americas scheme Document only addresses IAQG/AAQG members responsibilities but does not preclude others from using the ICOP processDocument only addresses IAQG/AAQG members responsibilities but does not preclude others from using the ICOP process Added requirement that, at a minimum, certificates be in EnglishAdded requirement that, at a minimum, certificates be in English Removed allowance of auditors to perform 4 assessments while pending RMC approvalRemoved allowance of auditors to perform 4 assessments while pending RMC approval Add definition of the term Industry Controlled Other Party (ICOP)Add definition of the term Industry Controlled Other Party (ICOP) Replace the term “aerospace” industry with “aviation, space and defense”, where possibleReplace the term “aerospace” industry with “aviation, space and defense”, where possible Comments concerning changes to the main body of AS9104 will be passed on to Mike Roberts to forward to the AS9104 Re- Write TeamComments concerning changes to the main body of AS9104 will be passed on to Mike Roberts to forward to the AS9104 Re- Write Team Need SAE or other assistance in assuring document meets the SAE Style Guide upon releaseNeed SAE or other assistance in assuring document meets the SAE Style Guide upon release Need resolution from AAQG on removing or maintaining compliance to FAA Order 8120.12Need resolution from AAQG on removing or maintaining compliance to FAA Order 8120.12
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.