Research Phase, Indiana 811, Initial Notice, Verification Deborah Porter Project Engineer/Utility Coordinator Clark Dietz, Inc.
2
Utility Research Know how to get started: Review the project scope and intent Review the project schedule Know the UC process 105 IAC 13 Indiana Design Manual (IDM) Chapter 104 Utility Coordination Utility Accommodation Policy (UAP) INDOT Utility Coordination page http://www.in.gov/indot/2389.htm
3
Utility Research Create the UC Schedule: INDOT’s SPMS contains most information needed to create the schedule and start the Research INDOT PM or Utility Oversight Agent Reference post information www.in.gov/indot/2376.htm How does the schedule align with the project intent?
4
Utility Research
5
What is the product? After each Research step, record: Utility companies’ names, or no data found Name of person recording the information Date when information obtained Name of person supplying the information At conclusion of Research phase, summarize all information and submit to Designer and Oversight Agent
6
Utility Research Specific link to Authorized Rep http://www.in.gov/indot/div/public/utilities/sec ure/UtilityAddressList.htm http://www.in.gov/indot/div/public/utilities/sec ure/UtilityAddressList.htm Username and password needed – use the link on the page to send an email to request the information Research Examples
7
Utility Research Permit Search
8
Utility Research
11
Design Ticket
12
Utility Research
27
Utility Initial Notice
28
Know who receives the Notice Include a map of the project area If no response within 30 days, follow up A project contact should be assigned
29
Utility Initial Notice
30
Utility Verification Verification Includes Obtain accurate utility locations Potential for SUE Septic systems and wells
31
Utility Verification Face to Face meeting Discuss complications and types of facilities Discuss design alternatives Obtain accurate utility locations Avoid utility impacts whenever feasible Ballpark estimate for relocation Establish reimbursable positions Discuss work in contract relocations
32
Utility Verification
36
Indiana 811 Indiana “Dig” Law IC-8-1-26 IUPPS is the association An operator that has underground facilities located in Indiana must become a member of the association
37
Indiana 811 Locate flags must be maintained during construction Notice must be received at least 2 full working days, but not more than 20 calendar days prior to work Separate requests made if: Within incorporated area, every 1500’ In unincorporated area, every 2500’
38
Indiana 811 Locate markings Know your colors for different utilities Excavation responsibilities