1 WP1 Technical Overview Progress since last meeting Barcelona 4-5 th March 2005 Milan Lalovic, BT.

Similar presentations


Presentation on theme: "1 WP1 Technical Overview Progress since last meeting Barcelona 4-5 th March 2005 Milan Lalovic, BT."— Presentation transcript:

1 1 WP1 Technical Overview Progress since last meeting Barcelona 4-5 th March 2005 Milan Lalovic, BT

2 2 WP1 tasks WP 1.1 Applications and Service Development WP 1.2 Business Modelling WP 1.3 Architecture and Inter-working BT 6,4,4 Bute 0,0,6 UPC 6,0,0 Polito 3,0,0 GSI 0,0,3 Skylinc 1,1,0

3 3 WP1 Overview WP1 : Applications and Services WP1.1 Applications and Services Development D01 was delivered in Feb 04 No activity since last meeting WP1.2 Business Modelling M9 delivered in July 04 M12 delivered 17 th Nov 2004 on business models, acceptance criteria and some example models of services HAPS Strategy Document (work started) WP1.3 Architecture Design / Interworking Trial and measurements for Internet to trains and moving vehicles, report issued 5 th Oct 04 Network and applications designed and demonstrated in trial 1 at Pershore, report issued 10 th Nov 04 No activity since last meeting

4 4 Exploration and Audit 26 th January 2005, IEE Satellite Broadband Seminar, London, “Mobile Hotspots” (WLAN on trains) paper presented Fairly wide audience Very well received 31 st January 2005, ISM Mobile and Wireless Summit, Japan, June 2005, Capanina paper sent out (BT co- author) 10 th February 2005, Brussels, Annual Review Meting and Audit Passed – Congratulations !!!

5 5 Audit – Concluding Remarks The project seems to be off to a good start and has the opportunity to produce state-of-the-art results on HAP communications. The project should carry on its technical work, but more attention on the business models validation needs to be provided. The issue of frequency availability needs to be urgently addressed. Matrix work on WP1 and contributions to other WPs need improving,…

6 6 WP1 Remaining work WP1 : Applications and Services WP1.1 Applications and Services Development Deliverable document “Revised applications and Services for BB HAP delivery” (due October 2006) – post trial WP1.2 Business Modelling Deliverable D10: “Strategy Document: Delivering Broadband for All from Aerial Platforms including commercial and technical risk assessments” (due May 2005) Milestone M20: “Development of commercial risk assessment methodology” (due Jun 2005) Milestone M24: “Reviewed and updated Strategy Document” (due October 2005) WP1.3 Architecture Design / Interworking Deliverable D11: “General network architecture requirements” (due May 2005) Milestone M20: “Development of technical risk assessment methodology” (due Jun 2005)

7 7 BT future work Due to the company restructuring, BT is unable to contribute to CAPANINA after the end of April 2005 BT will however stay within the consortium if possible (pending internal agreement) as a silent partner.

8 8 Contribution to other WPs – Possible Hand-over WP1Applications and Services WP2.5Networking and QoS Aspects Deliverable D24: Report defining network architecture and protocols (M36) WP3.1Communications equipment for trials Trial II contributions WP4.4Trials and Measurements Deliverable D19: Test Results Summary Report (M34) WP6Project Management

9 9 WP1 Discussion