1 Facilities Modernization Program Funded by Measure B Project Report November 21, 2011

2 PROJECT PROGRESS REPORT Child Development Center Project Team: Architect: Beverly Prior Architects Construction Manager: Parsons Brinckerhoff Contractor: Lathrop Construction Associates Project Update: Project is complete. Project is in Warranty Period. OccupancySpring 2011 LAS POSITAS COLLEGE November 21, 2011

3 PROJECT PROGRESS REPORT PE Phase III (Outside Loop Road) Project Team: Architect: WLC Architects / Carducci Landscape Architects Construction Manager: Parsons Brinckerhoff Contractor: Lathrop Construction Project Update: Project is complete. We are in Warranty Period. DSA Closeout is in progress. Occupancy: 04/2011 LAS POSITAS COLLEGE November 21, 2011

4 PROJECT PROGRESS REPORT Science Building, Phase II Project Team: Architect: Kwan Hemni Construction Manager: Parsons Brinckerhoff Contractor: Broward Builders, Inc Project Update: Interior/Exterior framing on first and second floors are being completed. Exterior insulation is being installed. Plumbing installation is continuing on first and second floors. Electrical and Data installation is continuing at first and second floors. Roofing on High Roof is complete, Low roof is 85% complete. Storefront installation will start week of Nov 28, 2011. Occupancy: 09/2012 LAS POSITAS COLLEGE November 21, 2011

5 PROJECT PROGRESS REPORT Student Services & Central Administration Project Team: Architect: Steinberg Architects Construction Manager: Parsons Brinckerhoff Contractor: Zovich Construction Project Update: GFRC installation erection complete, plumbing and lining remain. Mechanical, Electrical, Plumbing rough in continues. Interior wall partitions underway, exterior framing 50% complete. Occupancy: Spring 2013 LAS POSITAS COLLEGE November 21, 2011

6 PROJECT PROGRESS REPORT Campus Boulevard Phase I-III Project Team: Architect: Gates & Associates Construction Manager: Parsons Brinckerhoff Contractor: TBD Project Update: 100% Design review completed, final design schedule for December 2011. Design Re-Start: 04/2011 DSA Permit Approval: 02/2012 Construction Start: 03/2012 Occupancy: TBD LAS POSITAS COLLEGE November 21, 2011

7 PROJECT PROGRESS REPORT Photovoltaic System Phase II Project Team: Design Build Contractor: Cupertino Electric Inc. Construction Manager: Parsons Brinckerhoff Project Update: Fencing Completed. Racking System completed and ready for Array installation. PV Arrays installation will start week of November 28, 2011. Inverters and Transformer install Mid December 2011. Occupancy: January 2012 LAS POSITAS COLLEGE November 21, 2011


Download ppt "Facilities Modernization Program Funded by Measure B Project Report November 21, 2011."