Download presentation
1
Chapter 15 MRP and ERP
2
MRP Material requirements planning (MRP): Computer-based information system for ordering and scheduling of dependent demand inventories
3
Dependant Demand Dependent demand: Demand for items that are subassemblies or component parts to be used in production of finished goods.
4
Dependent vs Independent Demand
Time Demand Stable demand “Lumpy” demand Amount on hand Safety stock
5
Bill of materials Inventory records
MRP Inputs MRP Processing MRP Outputs Master schedule Bill of materials Inventory records MRP computer programs Changes Order releases Planned-order schedules Exception reports Planning reports Performance- control reports transaction Primary Secondary
6
Master Production Schedule
MPR Inputs Master Production Schedule Time-phased plan specifying timing and quantity of production for each end item. Material Requirement Planning Process Product Structure Tree Lead Times
7
Master Schedule Master schedule: One of three primary inputs in MRP; states which end items are to be produced, when these are needed, and in what quantities. Cumulative lead time: The sum of the lead times that sequential phases of a process require, from ordering of parts or raw materials to completion of final assembly.
8
Planning Horizon Figure 14-4 1 2 3 4 5 6 7 8 9 10 Fabrication Assembly
Procurement Fabrication Subassembly Assembly
9
Bill-of-Materials Bill of materials: One of the three primary inputs of MRP; a listing of all of the raw materials, parts, subassemblies, and assemblies needed to produce one unit of a product. Product structure tree: Visual depiction of the requirements in a bill of materials, where all components are listed by levels.
10
Product Structure Tree
Figure 15-5 Chair Seat Legs (2) Cross bar Side Rails (2) Back Supports (3) Leg Assembly Level 1 2 3
11
MRP Processing Gross requirements Schedule receipts Projected on hand Net requirements Planned-order receipts Planned-order releases
12
Typical MRP Matrix
13
MRP Outputs Planned orders - schedule indicating the amount and timing of future orders. Order releases - Authorization for the execution of planned orders. Changes - revisions of due dates or order quantities, or cancellations of orders.
14
MRP Secondary Reports Performance-control reports Planning reports Exception reports
15
Other Considerations Safety Stock Lot sizing Lot-for-lot ordering
Economic order quantity Fixed-period ordering Part-period model
16
resource requirements
MRP Planning Develop a tentative master production schedule Use MRP to simulate material requirements Convert material requirements to resource requirements Firm up a portion of the MPS Is shop capacity adequate? Can capacity be changed to meet Revise tentative Change Yes No
17
MRP in Services Food catering service Hotel renovation
End item => catered food Dependent demand => ingredients for each recipe, i.e. bill of materials Hotel renovation Activities and materials “exploded” into component parts
18
Benefits of MRP Low levels of in-process inventories Ability to track material requirements Ability to evaluate capacity requirements Means of allocating production time
19
Computer and necessary software Accurate and up-to-date
Requirements of MRP Computer and necessary software Accurate and up-to-date Master schedules Bills of materials Inventory records Integrity of data
20
MRP: Problem 1 Suppose you are to produce 100 units of product A in period 8 with the product structure shown below. If no stock is on hand or on order, determine when to release orders for each component and the size of each order. Product A with a lead time of 4 periods is made from components B and C with lead times of 3 and 2 periods, respectively; C is made from components D and E with a lead time of 1 period each.
21
MRP: Problem 1 Product Structure A B (1) C (2) D (1) E (2)
22
MRP: Problem 1 - Solution
Master Production Schedule (MPS) Week 1 2 3 4 5 6 7 8 Demand 100
23
MRP: Problem 1 - Solution (cont.)
The following can be calculated in this problem since there is zero available-on-hand for item A and all of its components. End Item A Requirements: 100 Component B Requirements: 100 Component C Requirements: 200 Component D Requirements: 200 Component E Requirements: 400
24
MRP: Problem 1 – Solution (cont.)
100 Planned Order Release Gross Requirements A 4 8 7 6 5 3 2 1 Item Lead-Time
25
MRP: Problem 1 – Solution (cont.)
100 Planned Order Release Gross Requirements B 3 8 7 6 5 4 2 1 Item Lead-Time
26
MRP: Problem 1 – Solution (cont.)
200 Planned Order Release Gross Requirements C 2 8 7 6 5 4 3 1 Item Lead-Time
27
MRP: Problem 1 – Solution (cont.)
200 Planned Order Release Gross Requirements D 1 8 7 6 5 4 3 2 Item Lead-Time
28
MRP: Problem 1 – Solution (cont.)
400 Planned Order Release Gross Requirements E 1 8 7 6 5 4 3 2 Item Lead-Time
29
MRP: Problem 2 In the MRP table below, indicate the available on hand requirements, the planned order receipts, and the planned order releases. The lead-time is two periods. Available on hand are 20 units. Consider a) the lot size is the same as the net requirements {Lot-For-Lot (LFL) or lot size = 1} and b) lot size equals 15.
30
MRP: Problem 2
31
MRP: Problem 2 (a)- Solution
32
MRP: Problem 2 (a)- Solution
33
MRP: Problem 2 (a)- Solution
34
MRP: Problem 2 (a)- Solution
35
MRP: Problem 2 (a)- Solution
36
MRP: Problem 2 (a)- Solution
37
MRP: Problem 2 (a)- Solution
38
MRP: Problem 2 (a)- Solution
39
MRP: Problem 2 (a)- Solution
40
MRP: Problem 2 (a)- Solution
41
MRP: Problem 2 (b) - Solution
42
MRP: Problem 2 (b) - Solution
43
MRP: Problem 2 (b) - Solution
44
MRP: Problem 2 (b) - Solution
45
MRP: Problem 2 (b) - Solution
46
MRP: Problem 2 (b) - Solution
47
MRP: Problem 2 (b) - Solution
48
MRP: Problem 2 (b) - Solution
49
MRP: Problem 2 (b) - Solution
50
MRP: Problem 3 A company produces two products: Product A and Product Q. The owner has received an order from a customer of 103 units of product A for week 8 and 200 units of product Q for week 7. The product structures and other pertinent information are given below in the table as well as on top of each MRP table. Develop a materials requirements plan that will provide the customer the two products.
51
MRP: Problem 3
52
MRP: Problem 3 - Solution
53
MRP: Problem 3 – Solution (cont.)
54
MRP: Problem 3 – Solution (cont.)
55
MRP: Problem 3 – Solution (cont.)
56
MRP: Problem 3 – Solution (cont.)
57
MRP: Problem 3 – Solution (cont.)
58
MRP: Problem 3 – Solution (cont.)
59
MRP: Problem 3 – Solution (cont.)
60
MRP: Problem 3 – Solution (cont.)
61
MRP: Problem 3 – Solution (cont.)
62
MRP: Problem 3 – Solution (cont.)
63
MRP: Problem 3 – Solution (cont.)
64
MRP: Problem 3 – Solution (cont.)
65
MRP: Problem 3 – Solution (cont.)
66
MRP: Problem 3 – Solution (cont.)
67
MRP: Problem 3 – Solution (cont.)
68
MRP: Problem 3 – Solution (cont.)
69
MRP: Problem 3 – Solution (cont.)
70
MRP: Problem 3 – Solution (cont.)
71
MRP: Problem 3 – Solution (cont.)
72
MRP: Problem 3 – Solution (cont.)
73
MRP: Problem 3 – Solution (cont.)
74
MRP: Problem 3 – Solution (cont.)
75
MRP: Problem 3 – Solution (cont.)
76
Expanded MRP with and emphasis placed on integration
MRP II Expanded MRP with and emphasis placed on integration Financial planning Marketing Engineering Purchasing Manufacturing
77
MRP II Market Demand Production plan Problems? Yes No Finance
Rough-cut capacity planning Yes No Finance Marketing Manufacturing Adjust production plan Master production schedule MRP Capacity planning Requirements schedules Adjust master schedule
78
ERP Enterprise resource planning (ERP): An expanded effort to integrate standardized record-keeping that will permit information sharing throughout the organization
79
Expanded MRP with and emphasis placed on integration
MRP II and ERP Systems Expanded MRP with and emphasis placed on integration Financial planning Marketing Engineering Purchasing Manufacturing Other Capabilities
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.