Presentation is loading. Please wait.

Presentation is loading. Please wait.

Cnoc Windfarms Ltd Presented by Thomas Cooke Director.

Similar presentations


Presentation on theme: "Cnoc Windfarms Ltd Presented by Thomas Cooke Director."— Presentation transcript:

1 Cnoc Windfarms Ltd Presented by Thomas Cooke Director

2 Company Locally owned and developed 4 partners 3 are landowners Self financed and developed

3 LOCATION

4 On Tipperary Kilkenny Border

5 Highest point on Slieveardagh Hills 340 metres elevation

6 Planning History Planning lodged in 2001 for 17 turbines 600 kw each 10.2 MW, full EIS etc by Fehily Timoney. Granted by South Tipperary County Council Refused by ABP in 2002, main reason was visibility on nearby Cistercian Abbey (Inspectors report mentioned no need for onshore wind farms as Ireland could meet its 500MW target from the Arklow Bank offshore wind farm!)

7 Planning Contd. Revised planning application in 2009 for 5 x 2.3MW turbines,4 have 65 metre hub height and 1, 55 metre hub all with 70m diameter blades total installed capacity 11.5MW EXTENSIVE consultations with state agencies etc. Full EIS etc by Eamon O’Domhnaill Aeolas New EIA guidelines arrived mid planning Again granted by South Tipperary County Council and appealed to ABP by third parties ABP granted planning on a majority decision on March 2011, no onerous planning conditions

8 Grid Connection Applied for Grid in 2005 Missed Gate 2 In Gate 3 H1 Thurles Node Got Grid offer March 2011 same week as ABP granted Planning! Accepted Grid offer in November 2011

9 Grid Connection Contd. Grid offer connection to Thurles OHL in association with two other wind farms in Blanchfield sub group c.35MW total Unfeasible to build OHL due principally to planning timescale, 63 landowners, 24 km, 3 Local Authorities Currently applying for modification to UHL with Blanchfield Group

10 Wind resource Two masts on site 30 metre radio mast operating for a few years 65m lattice mast erected by Lynx Metmasts in 2011 Wind speed 8.5m/s +

11 Lynx Mast 65 metre Lattice Guyed Ammonit logger Web access to logger data Theiss anenometer

12 Head for heights

13 Projected costs C. €15 – €16m

14 Build date Start construction 2014

15 Current work Due diligence Land leases Engaging with banks Access issues Wind data analysis

16 Consultants Aeolas - Planning Connellan and associates – Planning Poe Kiely Hogan Lanigan – Legal O’Neill Foley – Company Accountants Mullan Grid – Grid Connection Irish Wind Farmers Cooperative – Financial EMD - Wind analysis

17 The last word Persistence !


Download ppt "Cnoc Windfarms Ltd Presented by Thomas Cooke Director."

Similar presentations


Ads by Google