Cargo Dock 16: Pre-Bid Meeting Presentation June 13, 2013
2
AGENDA 1. Introductions – Eddie Campirano, Port Director 2. Agenda Overview – Mike Krieber, HDR 3. Safety Discussion – Mike Davis, Harbormaster 4. Project Overview Presentation – Mike Krieber, HDR 5. Q & A Session – Mike Krieber, Moderator
3
AGENDA (continued) 6. Site Visit – Ariel Chávez II, Port Engineer Existing Cargo Dock 15 – similarities & differences to Cargo Dock 16 plans Contractor Limitations Due to Dock 15 Operations Storm water line – warehouse use & road crossings Water main crossing Vessel use of mooring structure during construction / new west side mooring structure construction Construction limits / laydown area Demolition / salvage New Railroad Crossing - construction access point 7. Return to Board Room – Q&A 8. Closing Comments – Eddie Campirano, Port Director
4
Dock 15 / 16 Area
5
TIGER Grant
6
TIGER Grant Requirements Buy American 10% Minimum DBE Requirement Buy American
7
BASE BID Match Channel Depth
8
BASE BID Cross Section
9
ALTERNATE BID Deep Water
10
ALTERNATE BID Cross Section
11
PRIMARY DIFFERENCES Base Bid PZ 40 Sheet Pile on Face 6 Bents in Relieving Platform Same mooring structure on east and west sides Alternate Bid Combination Wall (longer piles) 7 Bents in Relieving Platform (longer piles) West mooring structure connects to existing mooring structure 300 LF “In-fill” Bulkhead
12
DREDGING US Army Corps of Engineer Permit Mechanical excavation required adjacent to bulkhead (see Note 10, Sheet 01 C01) Side casting allowed DMPA 8 disposal; permit allows for use of additional DMPAs – to be coordinated and approved by Port
13
WORK RESTRICTIONS Found in Specification 01 14 00 Coordinate with the Harbormaster Storm Sewer Road Crossings East Mooring Structure $5000 FINE if Dock 15 secure area is breached Ship mooring line handlers need access to wood pile bollard within project area
14
ANTICIPATED ADDENDUMS Bid Submittal Due: July 10, 5:00 pm Bid Opening: July 10, 5:30 pm Bid Award: July 24, 2013 BND Board Meeting Substantial completion: February 28, 2015 Final Completion: March 31, 2015 Base Bid required Bid Bond clarification Bid Form clarifications
15
ANTICIPATED ADDENDUMS (cont’d) Job trailer for Port’s on-site representative to be provided by Contractor $5000 fine for Dock 15 security area breach Access for use of wood pile bollard & delayed demolition Early completion of West Bollard construction
16
BASIS OF AWARD 2 Bids to be evaluated: Base Bid & Alternate Bid. Based upon the bids and other financial conside- rations, the Brownsville Navigation District may make a selection of the desired facility (Base Bid OR Alternate Bid). Once the desired facility is determined, the Dis- trict may award the contract to the responsible bidder submitting the lowest and best bid for the selected facility. The District may reject any or all bids.
17
Schedule Bids Due5:00 PM – July 10, 2013 Bid Opening5:30 PM – July 10, 2013 Award Contract July 24, 2013 Board Mtg. Notice to ProceedAugust, 2013 Substantial CompletionFebruary 28, 2015 Final CompletionMarch 31, 2015
18
Thank You Discussion
19
Questions 1. 2. 3. 4. 5. 6. 7. 8.