Overview of AMS-02 Changes due the addition of the Permanent Magnet
05/04/2010 Joseph Kastelic / ESCG
2
AMS-02 Payload Design Changes due to the addition of the Permanent Magnet.
Major Cryogenic Hardware Removed from the AMS-02 Payload Superconducting Cryomagnet Superfluid Helium Tank (SFHe) Cryogenic Support Hardware Removed from AMS-02 Payload Onboard Vacuum Pump Cryomagnet Support Straps (suspension system) Flight Vacuum case Cryocooler Loop Heat Pipe (LHP) SFHe Tank Burst Disk Vacuum Case Burst Disk CAB Loop Heat Pipe, accumulators, evaporators Warm Helium Tank and WHT MMOD. 2500 liters of Liquid/Gas Helium
3
Major Electrical Hardware removed from AMS-02 Payload
CAB (Cryomagnet Avionics Box) Cryomagnet Dump Diodes (CDD) Uninterruptible Power Supply (UPS) Electrical Support Hardware removed from AMS-02 Payload Baroswitch Electronics (BSE) RTD Cabling Charge/Discharge Cabling Cryomagnet Pilot Valve Switch (CPVS)(Magic Box) OBP (Onboard Pump) Cabling from IPA CCEB electronics (Leave Box On) Components of the Tracker Alignment System Major Thermal Hardware Removed from the AMS-02 Payload Zenith radiator MLI (Reconfigured for new thermal requirements)
4
Major Hardware Added to Payload
STA Vacuum Case Permanent Magnet (Inside the STA Vacuum Case) Permanent Magnet Support Structure (Inside the STA Vacuum Case) Tracker Plane 1N (above TRD) Tracker Plane 6 added between RICH and ECAL New TTCS loop for Plane 6 Major Hardware Unaffected by the Change USS-02 PAS assembly (except envelope) Grapple fixtures Debris Shields ROEU EVA Connector Panel Umbilical Mechanism Assembly Hardware Reconfigured Electronic Calorimeter (ECAL) moved 35mm Tracker Plane 1N relocated above TRD.
5
External Parts to be Removed From Payload
Debris Shield, ROEU, and Interface Panel A removed for clarity Zenith Radiator (Cryomagnet cooling) Cryomagnet Pilot Valve Switch Box (CPVS) BSE (Baroswitch) Cryomagnet Dump Diode (CDD) Cryomagnet Avionics Box (CAB) and CAB Loop Heat Pipe Vent Pump Uninterruptable Power Supply (UPS) Cryocooler
6
External Parts to be Removed From Payload
Cryocooler Vacuum Case Burst Disk SFHe Tank Burst Disks Warm Helium Tank and MMOD Shield Cryocooler
7
Superconducting Cryomagnet and external Cryogenic Hardware.
Most will be removed from the AMS-02 Payload 4 Cryocooler Burst Disk Warm Helium Tank and MMOD Shielding Various Tubes. Fittings, Valves, etc. to be removed.
8
Cryomagnet Vacuum Case Internal Hardware that will be removed
Helium tank Sixteen Support straps (magnet suspension system)
9
STA Vacuum Case to be Configured for Fight with permanent Magnet
10
Permanent Magnet originally flow on STS-91 June1998
Mounts to structure with bolts and shear pins in 8 locations on the cylinder and 4 places on each flange Top flange (structural) Bottom Flange (structural) Magnet material core (non-structural)
11
STA Vacuum Case with Permanent Magnet
Support Struts (16) (Titanium Alloy) Permanent Magnet Aluminum X Structure 7075-T7351 VC Upper and Lower Support rings Top View :Struts (exactly along Original Action Line) Conical flanges and Outer Cylinder not shown
12
Outer Support Structure with 4 Identical Structures
STA Vacuum Case with Permanent Magnet Outer Support Structure with 4 Identical Structures All Joints: Bolted and Shear Pin Clevis and Spherical Bearing Joint Titanium Strut VC attachment Fitting AMS02 Permanent Magnet
13
Vacuum Case with PM Cross Section
Upper Conical Flange Lower Conical Flange Permanent Magnet Outer Cylinder Upper Support Ring Lower Support Ring Permanent Magnet X-Structure
14
Vacuum Case with PM Installed in the AMS-02 Unique Support Structure
STA Shown Installed in Pre-Integration Activities
15
AMS-02 Tracker Assembly (Reconfigured)
Tracker Design Prior to PM Tracker was Contained within the inner bore of the Vacuum Case Tracker Assembly
16
Original Configuration Plane 5 will be moved to the top of the TRD
Tracker Consist of 5 Planes of Carbon Fiber and 8 layers of Silicone Plane 1: Layer 1 Plane 2: Layer 2 and 3 Plane 3: Layer 4 and 5 Plane 4: Layer 6 and 7 Plane 5: Layer 8 Original Configuration Plane 5 will be moved to the top of the TRD Relocated Plane 5 or Plane 1N New Tracker Plane 6 Layer 9 Tracker Plane P9 will be made from parts taken from layer 8, layer 1, and spares.
17
AMS-02 Experiment Core and Tracker Assembly Reconfigured
Transition Radiation Detector (TRD) Electronic Calorimeter (ECAL) Ring Image Cherenkov Counter (RICH) Silicone Tracker
18
Honeycomb Support Structure with CF face sheets
Plane 1N Configuration TRD Silicone layer Carbon Fiber Plane 1N Honeycomb Support Structure with CF face sheets Plane 1N TRD Plane 1N will include MLI and debris containment.
19
AMS-02: Upper TRD Cover with Plane1N Support
Plane1N Support Structure TRD Unique Support Structure (USS) Permanent Magnet Assembly
20
AMS-02: Upper TRD Cover with Plane1N Support
Plane1N Support Structure shown translucent Plane 1N
21
AMS-02: Upper TRD Cover with Plane1N Support
Silicon Layer Honeycomb Support Structure with CF face sheets
22
AMS-02: Upper TRD Cover with Plane1N Support
Silicon Layer PlatenN Plane1N Support
23
New Tracker Plane 6 Layer 9
New Tracker Plane will be located between the ECAL and the RICH Assembly The ECAL will be lowered by 35mm giving room for the new plane Tracker Lower Time of Flight The empty space from Plane 5 will be replaced with a dummy plane Plane 6 will include MLI and debris containment.
24
New Tracker Plane 6 Layer 9
Tracker Plane Mounting Hardware. Interfaces Existing ECAL Mounting Locations ECAL Silicone Layer Carbon Fiber Plane
25
New Tracker Plane 6 Integrated
New Cooling Loop
26
New Tracker Plane Cooling Loop
Tracker Plane Cooling Loop (TTCS) Loop for Plane 6 (Evaporator)
27
Capture Bar Clearance issue due to the lowering of the ECAL
Passive PAS Capture Claw Clearance Envelope ISS Keep out zone The Configuration prior to lowering the ECAL AMS-02 Active Common Attach System (CAS) Capture Claw
28
Lowering The ECAL 35mm produces a violation of the Capture Claw Envelope of 19mm
There is no known impact of the envelope violation that concerns AMS-02 Nominal Clearance to Claw 24mm
29
MLI Considerable MLI changes are anticipated. Some will be eliminated and others will be added. Ram Wake Starboard Side of Payload
30
MLI Considerable MLI changes are anticipated. Some will be eliminated and others will be added. Ram Wake Port Side of Payload
31
AMS-02 Hardware that will not be changed
USS-02 Assembly (Primary Structure) Payload Attach System (PAS) Umbilical Mechanism Assembly (UMA) Power and Video Grapple Fixture (PVGF) EVA Handrails Port Debris Shield
32
AMS-02 Hardware that will not be changed
Remotely Operated Electrical Umbilical (ROEU/PDA) Starboard Debris Shield Flight Releasable Grapple Fixture (FRGF) Interface Panel A USS Handrails Keel Assembly EVA Connector Panel Keel Handrails
33
Backup Slides
35
Parts to be Removed From Payload