Truro sewer upgrade Timetable of work and maps. Key plan Victoria Square Kenwyn Street New / upsized combined sewer - red New / upsized surface water.

Similar presentations


Presentation on theme: "Truro sewer upgrade Timetable of work and maps. Key plan Victoria Square Kenwyn Street New / upsized combined sewer - red New / upsized surface water."— Presentation transcript:

1 Truro sewer upgrade Timetable of work and maps

2 Key plan Victoria Square Kenwyn Street New / upsized combined sewer - red New / upsized surface water sewer - blue Little Castle Street St Dominic Street Ferris Town Frances Street

3 September 2013 Local hoarding within Victoria Square with buses still operating Site office

4 October 2013 Local hoarding within Victoria Square with buses still operating Hoarding to be extended late October and Victoria Square closed to all traffic Site office Auger bore launch pit Auger bore and pipework

5 November 2013 Victoria Square closed to all traffic until November 15 Sewer laying up to Calenick Street junction. Kenwyn Street remains open Auger bore in Thomas Johnson Court Site office Access only to Upper Kenwyn Street

6 December 2013 Site office Victoria Square cleared of all hoarding and buses running Gas main diversion Auger Bore in Thomas Johnson Court Access only to Upper Kenwyn Street

7 January 2014 Surface water sewers Site office Auger bore and pipework Kenwyn Street closed Short length of open cut sewers Access to businesses will be maintained outside the immediate work area Route of traffic leaving Victoria Square

8 February 2014 Foul sewers along Kenwyn Street Route of traffic leaving Victoria Square Site office Foul sewers along Frances Street Access to businesses will be maintained outside the immediate work area

9 March 2014 Surface water sewers across St Dominic Street and junction with City Road Final reinstatements in Kenwyn Street Site office Surface water sewers Ferris Town and St Dominic Street Access to businesses will be maintained outside the immediate work area Foul sewers into Little Castle Street

10 April 2014 Little Castle Street CSO and sewers Site office Access to businesses will be maintained outside the immediate work area Surface water sewers in St Dominic Street

11 May 2014 Little Castle Street CSO and sewers Surface water sewers in St Dominic Street Site office Access to businesses will be maintained outside the immediate work area

12 June 2014 Little Castle Street CSO and sewers Site office Foul sewers along Little Castle Street