1
1 23 CFR 635.105 Supervising agency (c) When a project is located on a street or highway over which the STD does not have legal jurisdiction, or when special conditions warrant, the STD, while not relieved of overall project responsibility, may arrange for the local public agency having jurisdiction over such street or highway to perform the work with its own forces or by contract; provided the following…….. –Compliance with all applicable Federal and State requirements. –The local public agency is adequately staffed and suitably equipped to undertake and satisfactorily complete the work. –In those instances where a local public agency elects to use consultants for construction engineering services, the local public agency shall provide a full-time employee of the agency to be in responsible charge of the project. LOCALLY ADMINISTERED PROJECTS
2
2 Delegation of Activities, not Responsibilities 23 CFR 635.105 Supervising agency…….. (a) The STD has responsibility for the construction of all Federal-aid projects, and is not relieved of such responsibility by authorizing performance of the work by a local public agency or other Federal agency. The STD shall be responsible for insuring that such projects receive adequate supervision and inspection to insure that projects are completed in conformance with approved plans and specifications. ODOT shall assume the responsibility and representation of FHWA. ODOT provides oversight for each activity to ensure conformance to plans and specifications and Federal requirements. LOCALLY ADMINISTERED PROJECTS
3
3 By written agreement with ODOT typical LPA activities include: Environmental studies Procurement of consultant services (ODOT oversight) Design Surveying Right of Way acquisition Work by railroads or utility companies Preparation of plans, specifications and estimates Preparation of bid proposal package Advertisement for letting Contracting (Bid Analysis, Award to lowest and Best) · Contract administration Inspection / Testing LOCALLY ADMINISTERED PROJECTS
4
4 Non-delegated activities: DBE Goals and Waivers (ODOT) Final Acceptance (ODOT) Sole Source and Proprietary Justification Approval (ODOT / FHWA) Labor Compliance Enforcement (ODOT) Rejection of Bids (ODOT) Project Cost Eligibility (ODOT / FHWA) Federal-aid Payments (ODOT) LOCALLY ADMINISTERED PROJECTS
5
5
6
6 National Review Best Practices Stewardship and Oversight Agreement for locally administered projects. Dedicated Staffing Oversight and Monitoring Program Qualification Program for Local Agencies Local Agency Guidance Manual LOCALLY ADMINISTERED PROJECTS
7
7 ODOT Identified Best Practices District LPA Training Construction Involvement with Participation Requirements Plan and Bid Document Review Gary QAR LOCALLY ADMINISTERED PROJECTS
8
8 Current Issues: DBE Monitoring Materials Management Participation Requirements Review for Local Agencies Prime Contractor Performance % District Communication & Resources LOCALLY ADMINISTERED PROJECTS
9
9 Current Efforts to Improve CM Meeting May 16th– Construction Contract Admin Chapter – LATP Manual NHI (FHWA) – Contract Administration Core Curriculum Local-let Invoicing – DBE & Prime Performance % Future DCE Meetings Materials Management Process - Appendix J LOCALLY ADMINISTERED PROJECTS
10
10
11
11 District-02 Construction Monitor Roles and Documentation Practices
12
12 Construction Monitor Responsibilities 1) Project Scope Meeting/Initial Project site visit 2) Pre- Bid Meeting 3) Pre-Construction Meeting 4) Online LPA Survey Reporting 5) Project Site Visits 6) Review and Approval of Invoice Reimbursements 7) Progress Meetings 8) Documentation Reviews 9) Initial Walkthrough Inspection 10) Final Inspection 11) Project Close Out and Final Documentation Review
13
13 1) Project Scope Meeting/Initial Project site visit The District -02 LPA Coordinator schedules and chairs this meeting usually held at the LPAs place of business, followed by a trip to the proposed project site. District attendees include representatives from Planning/Production, Real-estate, Environmental, and Construction. Provides an opportunity for the LPA and District to openly discuss all aspects of the project including administration requirements, eligibility, scheduling, and identification of potential issues.
14
14 ODOT 2008-2009 B USINESS P LAN 1) Project Scope Meeting/Initial Project site visit
15
15 2) Pre- Bid Meeting Preliminary information sent to the LPAs Project Engineer by email: Pre-con packet, Agenda items, links to the LPA homepage, OMM, and LPA Manual of Procedures, etc. Similar to ODOT Administered projects: Give a short overview of ODOT expectations and requirements with an emphasis on inspection documentation and materials. Assist the LPA in answering administration questions, policies, and procedures specific to the contract. Record general project information on the Pre-Award Checklist. *Send out pre-con information to FHWA, Central Office and District 02 personnel.
16
16 ODOT 2008-2009 BUSINESS PLAN
17
17
18
18
19
19 3) Pre-Construction Meeting Ensure all applicable agenda items are covered from Appendix A Gather LPA and Contractor submittals per the Precon Packet. Review LPA process and expectations of ODOT/FHWA oversight. Assist with policy and procedural items. Coordinate regular interval Progress meetings. Record information on Precon Form.
20
20
21
21 4) Online LPA Survey Reporting Required entry for all project site visits: Pre-cons Regular visits Progress meetings Documentation reviews Final Inspections.
22
22
23
23 5) Project Site Visits Monitor contract work and inspection practices. Discuss project issues, provide assistance and direction regarding materials, testing and contract administration. Identify deficiencies and opportunities for improvement. Review change order requests in the field and determine necessity. Provide CM Concurrence on Significant Change Orders
24
24
25
25 6) Review and Approval of Invoice Reimbursements Keep up to date with the project status. Monitor work in progress and work items completed. Compare Invoices with LPAs regular pay estimates. Review and approval of the Local Let Summary and Payable Invoices for: A) Construction Contract Work B) Construction Engineering and Inspection Work including Testing. Inquire and follow up on any discrepancies or unusual pay quantities. Watch for LPAs who simply pay Estimated Plan Qtys. (Verify)
26
26 7) Progress Meetings Progress meetings required every two weeks or monthly depending on complexity and track record of the project personnel. Follow applicable agenda items per Appendix B in the LPA Manual. Fill out Local Let Progress Report form.
27
27
28
28 8) Documentation Reviews Usually held after a scheduled progress meeting with the LPAs Inspector and or Engineer at the project field office. Review and audit of all documentation requirements: Refer to LPA Manual Appendix C and J Daily Diaries Reference item summaries Pay Quantities Materials, Testing, and support documentation Change Orders DBE, EEO, and PW requirements Claims, etc.
29
29 REFERENCE/PAY FILES Individual folder for each pay item of work Field Documentation Inspection Forms Seven identifiers Project Number, Item Number, Plan Reference Number, Work Description, Location, Date, Signature Plan quantity, field measurements, calculations, pay quantity Summarized final quantity Funding splits. (Also summarized on the L.L.S.P. Invoice) Non-performed items require documentation
30
30 MATERIALS ACCEPTANCE Systematic approach to managing materials ODOTs Office of Materials Management (OMM) Project Bill of Materials (PBOM) Appendix J OMM inspection of precast/pre-stressed concrete beams OMM inspection of structural steel Contractor/LPA should be familiar with Appendix J prior to bid ODOT District asphalt plant monitoring
31
31 MATERIALS ACCEPTANCE Any and all materials incorporated into the Work need documentation. Use C&MS Section 700 for documentation guidance Many Frequently used links from OMM website: Sampling and testing Manual, QPL, Certified Suppliers, Approved Lists, Approved Plants, Welders, Aggregates, etc. etc. Temporary materials are to be documented in this manner as well.
32
32
33
33 9) Initial Walkthrough Inspection Typically done when substantial work is complete. Coordinated By LPA with Contractor, Consultants and CM. Generate and record final punch list items. LPA distributes copies to all attendees. LPA specifies punch list completion deadline in writing to the Prime Contractor.
34
34 10) Final Inspection Finalization Per C&MS 109.12 Ensure all contract requirements are complete including punch list items and LPA approval. Issuance of the ODOT Final Inspection report (Appendix U)
35
35 11) Project Close Out and Final Documentation Review Approval of Final Invoices for Const. and CE&I. LPA Final Report (Appendix P) Certification of Payroll Affidavits. Affidavit of DBE or EDGE subcontractor payments. ODOT Final Inspection Report (Appendix U) ODOTs LPA Project Evaluation Form. Final Package reviewed and sent by CM to the office of Local Programs, FHWA and District reps. Also posted on the O Drive: O:\Local Programs\LPA Final Program Reports