1
Activity 5 Drawing a Gantt chart for the development of a school attendance system Suppose when developing a school attendance system, the following activities are identified. Activity Dependent on Concurrent with Duration (week) 1. Feasibility study — Activity 2 2 2. Collect user requirements Activity 1 3. Write requirement specifications Activity 1, 2 1 4. Design data structure Activity 3 Activity 5, 6 5. Design user interface and menu
2
Activity 5 Drawing a Gantt chart for the development of a school attendance system Suppose when developing a school attendance system, the following activities are identified. Activity Dependent on Concurrent with Duration (week) 6. Design system functions Activity 3 Activity 4, 5 4 7. Purchase hardware Activity 5 — 1 8. Implement system Activity 6 2 9. Perform system testing Activity 8 10. Train system users Activity 9 Complete the Gantt chart using the above information. What is the minimum number of weeks required to complete the project? 12
3
Activity 5 Drawing a Gantt chart for the development of a school attendance system Activity Week 1 2 3 4 5 6 7 8 9 10 11 12 1. Feasibility study 2. Collect user requirements 3. Write requirement specifications 4. Design data structure 5. Design user interface and menu
4
Activity 5 Drawing a Gantt chart for the development of a school attendance system Activity Week 1 2 3 4 5 6 7 8 9 10 11 12 6. Design system functions 7. Purchase hardware 8. Implement system 9. Perform system testing 10. Train system users
5
Activity 5 Drawing a Gantt chart for the development of a school attendance system Activity Week 1 2 3 4 5 6 7 8 9 10 11 12 6. Design system functions 7. Purchase hardware 8. Implement system 9. Perform system testing 10. Train system users